Consider the project given below with the normal and crash costs (in thousands of PhP) and times (in weeks): Activity Immediate Predecessor Normal Time Crash Time Normal Cost Crash Cost A 2 200 250 B A 3 600 850 A 1 100 100 D B,C 2 650 900 450 500 E B 2 500 F E,D 3 620 G F 1 500 600 H E,D 4 2 600 900 1. Construct the AOA network for the project. 2. Determine the expected completion time of the project using both normal and crash times and the corresponding costs. Also include the critical path for each situation. 3. What is optimal cost of the project if the decision maker wants to finish it in 14 weeks? 351 43
Consider the project given below with the normal and crash costs (in thousands of PhP) and times (in weeks): Activity Immediate Predecessor Normal Time Crash Time Normal Cost Crash Cost A 2 200 250 B A 3 600 850 A 1 100 100 D B,C 2 650 900 450 500 E B 2 500 F E,D 3 620 G F 1 500 600 H E,D 4 2 600 900 1. Construct the AOA network for the project. 2. Determine the expected completion time of the project using both normal and crash times and the corresponding costs. Also include the critical path for each situation. 3. What is optimal cost of the project if the decision maker wants to finish it in 14 weeks? 351 43
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question

Transcribed Image Text:Consider the project given below with the normal and crash costs (in thousands of PhP) and
times (in weeks):
Activity Immediate Predecessor Normal Time | Crash Time Normal Cost Crash Cost
3
A
200
250
В
A
5
3
600
850
A
1
1
100
100
D
B,C
4
2
650
900
E
B
3
2
450
500
F
E,D
3
500
620
500
600
900
F
2
1
H
E,D
4
2
600
1. Construct the AOA network for the project.
2. Determine the expected completion time of the project using both normal and crash
times and the corresponding costs. Also include the critical path for each situation.
3. What is optimal cost of the project if the decision maker wants to finish it in 14 weeks?
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 3 images

Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education


Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning

Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.