Amelio Rodriguez Computing wants to establish an assembly line for producing a new product, the Personal Digital Assistant (PDA). The tasks, task times, and immediate predecessors for the tasks are as follows: Task Time (sec) Immediate Predecessor ABCDE 11 14 A 8 A 4 18 B, C D Amelio's goal is to produce 180 PDAs per hour. a) The cycle time for the production of a PDA = seconds (round your response to two decimal places). (round your b) The theoretical minimum number of workstations that Amelio can achieve in this assembly line = response up to the next whole number). c) For one to assign the tasks to the actual workstations and be able to use the "theoretical minimum" number, the activity assignment should be: Workstation # Tasks Assigned to Workstation 1 A B 2 3 Were you able to assign all the tasks to the theoretical minimum number of workstations?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter4: Linear Programming Models
Section: Chapter Questions
Problem 111P
icon
Related questions
Question
Amelio Rodriguez Computing wants to establish an assembly line for producing a new product, the Personal Digital
Assistant (PDA). The tasks, task times, and immediate predecessors for the tasks are as follows:
Task
Time
(sec)
Immediate
Predecessor
ABCDE
11
14
A
8
A
4
18
B, C
D
Amelio's goal is to produce 180 PDAs per hour.
a) The cycle time for the production of a PDA =
seconds (round your response to two decimal places).
(round your
b) The theoretical minimum number of workstations that Amelio can achieve in this assembly line =
response up to the next whole number).
c) For one to assign the tasks to the actual workstations and be able to use the "theoretical minimum" number, the
activity assignment should be:
Workstation #
Tasks Assigned to Workstation
1
A
B
2
3
Were you able to assign all the tasks to the theoretical minimum number of workstations?
Transcribed Image Text:Amelio Rodriguez Computing wants to establish an assembly line for producing a new product, the Personal Digital Assistant (PDA). The tasks, task times, and immediate predecessors for the tasks are as follows: Task Time (sec) Immediate Predecessor ABCDE 11 14 A 8 A 4 18 B, C D Amelio's goal is to produce 180 PDAs per hour. a) The cycle time for the production of a PDA = seconds (round your response to two decimal places). (round your b) The theoretical minimum number of workstations that Amelio can achieve in this assembly line = response up to the next whole number). c) For one to assign the tasks to the actual workstations and be able to use the "theoretical minimum" number, the activity assignment should be: Workstation # Tasks Assigned to Workstation 1 A B 2 3 Were you able to assign all the tasks to the theoretical minimum number of workstations?
Expert Solution
steps

Step by step

Solved in 2 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,