alculate for the labor cost per square meter of CHB laying considering the following data:             Labor Productivity                                = 12 sq.m. per day              Gang Rates:                      Labor Rate @ 1 mason per diem   =  Php 856.00                      Labor Rate @ 1 Labor per diem    =    Php 581.00

Fundamentals Of Construction Estimating
4th Edition
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Pratt, David J.
Chapter10: Pricing Excavation And Backfill
Section: Chapter Questions
Problem 4RQ
icon
Related questions
icon
Concept explainers
Question

Calculate for the labor cost per square meter of CHB laying considering the following data:
            Labor Productivity                                = 12 sq.m. per day
             Gang Rates:
                     Labor Rate @ 1 mason per diem   =  Php 856.00
                     Labor Rate @ 1 Labor per diem    =    Php 581.00

 

a. Php 119.75 per sq.m
b. Php 958.00 per sq.m
c. Php 1,077.75 per sq.m
d. Php 2,155.50 per sq.m
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Management of Labor
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Fundamentals Of Construction Estimating
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,