alculate for the labor cost per square meter of CHB laying considering the following data: Labor Productivity = 12 sq.m. per day Gang Rates: Labor Rate @ 1 mason per diem = Php 856.00 Labor Rate @ 1 Labor per diem = Php 581.00
alculate for the labor cost per square meter of CHB laying considering the following data: Labor Productivity = 12 sq.m. per day Gang Rates: Labor Rate @ 1 mason per diem = Php 856.00 Labor Rate @ 1 Labor per diem = Php 581.00
Fundamentals Of Construction Estimating
4th Edition
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Pratt, David J.
Chapter10: Pricing Excavation And Backfill
Section: Chapter Questions
Problem 4RQ
Related questions
Question
Calculate for the labor cost per square meter of CHB laying considering the following data:
Labor Productivity = 12 sq.m. per day
Gang Rates:
Labor Rate @ 1 mason per diem = Php 856.00
Labor Rate @ 1 Labor per diem = Php 581.00
a. Php 119.75 per sq.m
b. Php 958.00 per sq.m
c. Php 1,077.75 per sq.m
d. Php 2,155.50 per sq.m
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,