Q5. Estimate cost of laying a 300mm concrete pipe The following data are extracted from a pipe-laying contract: Concrete pipe diameter: inside 300mm, outside 334mm • Overall pipe length • Width of trench • The trench depths and lengths are in table 6. = 425m = 750mm Page 3 of 4 Table 6: Trench depths Depth (m) Length (m) 1.50 131 2.00 2.50 274 20 Calculate the total cost, and cost for each depth, to a contractor of excavation, planking and strutting, laying pipes, surrounding concrete as shown in Figure 2 and backfilling, using the following data. Labour and plant for pipe-laying (up to 300mm diameter): One JCB 3C excavator =£31.64/h • Small plant, pumps and compactor One pipe layer = £5.85/h = £15.00/h Two labourers =£26.00/h Assume a working week is 50 hours. Also, assume an average output of 50 linear meters of pipe laid per week, the output varying with the depth of trench. The output includes excavating, trimming, pipe laying, concreting and backfilling. Labour allowance for planking and strutting are shown in Table 7. Planking and strutting materials are recoverable (reusable) and the material cost is £1.30 per m' for this project.

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question

please help my homneworkkk  ı need a good solution 

Q5. Estimate cost of laying a 300mm concrete pipe
The following data are extracted from a pipe-laying contract:
• Concrete pipe diameter: inside 300mm, outside 334mm
• Overall pipe length
• Width of trench
• The trench depths and lengths are in table 6.
= 425m
= 750mm
Page 3 of 4
Table 6: Trench depths
Depth (m)
1.50
Length (m)
131
2.00
274
2.50
20
Calculate the total cost, and cost for each depth, to a contractor of excavation, planking and
strutting, laying pipes, surrounding concrete as shown in Figure 2 and backfilling, using the following
data. Labour and plant for pipe-laying (up to 300mm diameter):
. One JCB зC еxcavator
= £31.64/h
• Small plant, pumps and compactor
• One pipe layer
• Two labourers
= £5.85/h
= £15.00/h
=£26.00/h
Assume a working week is 50 hours. Also, assume an average output of 50 linear meters of pipe laid
per week, the output varying with the depth of trench. The output includes excavating, trimming,
pipe laying, concreting and backfilling. Labour allowance for planking and strutting are shown in
Table 7. Planking and strutting materials are recoverable (reusable) and the material cost is £1.30
per m' for this project.
Transcribed Image Text:Q5. Estimate cost of laying a 300mm concrete pipe The following data are extracted from a pipe-laying contract: • Concrete pipe diameter: inside 300mm, outside 334mm • Overall pipe length • Width of trench • The trench depths and lengths are in table 6. = 425m = 750mm Page 3 of 4 Table 6: Trench depths Depth (m) 1.50 Length (m) 131 2.00 274 2.50 20 Calculate the total cost, and cost for each depth, to a contractor of excavation, planking and strutting, laying pipes, surrounding concrete as shown in Figure 2 and backfilling, using the following data. Labour and plant for pipe-laying (up to 300mm diameter): . One JCB зC еxcavator = £31.64/h • Small plant, pumps and compactor • One pipe layer • Two labourers = £5.85/h = £15.00/h =£26.00/h Assume a working week is 50 hours. Also, assume an average output of 50 linear meters of pipe laid per week, the output varying with the depth of trench. The output includes excavating, trimming, pipe laying, concreting and backfilling. Labour allowance for planking and strutting are shown in Table 7. Planking and strutting materials are recoverable (reusable) and the material cost is £1.30 per m' for this project.
Assume a working week is 50 hours. Also, assume an average output of 50 linear meters of pipe laid
per week, the output varying with the depth of trench. The output includes excavating, trimming,
pipe laying, concreting and backfilling. Labour allowance for planking and strutting are shown in
Table 7. Planking and strutting materials are recoverable (reusable) and the material cost is £1.30
per m? for this project.
Suitable material
Concrete class
E 150 mm min. cover
may be formed
horizontal surface
334 mm
100 mm
Width of trench = 750 mm
Figure 2: Concrete surround to pipe
Table 7: Labour allowance for planking and strutting
Depth (m)
Labour hours per
metre
1.50
0.2
2.00
0.3
2.50
0.7
• Ready-mix concrete for bedding (assume wastage of 5%)
• Pipe, concrete class L 300mm diameter (assume wastage of 3%)
= £100.00/m?
= £26.56/m
Allowance for disposal of surplus material
Assume all excavated material is suitable as backfill and compacts to original volume
The excavator is used to load tipper trucks with surplus material. The loading, travel,
discharge and return cycle time of one 4m3 tipper-truck is 21 minutes. The cost of a 4m3
tipper-truck including driver is £32.16 per hour.
Transcribed Image Text:Assume a working week is 50 hours. Also, assume an average output of 50 linear meters of pipe laid per week, the output varying with the depth of trench. The output includes excavating, trimming, pipe laying, concreting and backfilling. Labour allowance for planking and strutting are shown in Table 7. Planking and strutting materials are recoverable (reusable) and the material cost is £1.30 per m? for this project. Suitable material Concrete class E 150 mm min. cover may be formed horizontal surface 334 mm 100 mm Width of trench = 750 mm Figure 2: Concrete surround to pipe Table 7: Labour allowance for planking and strutting Depth (m) Labour hours per metre 1.50 0.2 2.00 0.3 2.50 0.7 • Ready-mix concrete for bedding (assume wastage of 5%) • Pipe, concrete class L 300mm diameter (assume wastage of 3%) = £100.00/m? = £26.56/m Allowance for disposal of surplus material Assume all excavated material is suitable as backfill and compacts to original volume The excavator is used to load tipper trucks with surplus material. The loading, travel, discharge and return cycle time of one 4m3 tipper-truck is 21 minutes. The cost of a 4m3 tipper-truck including driver is £32.16 per hour.
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Measuring carpentry and miscellaneous items
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning