A Social Project manager is faced with a project with the following activities:  Activity-ID                                          Description                                                         Duration 1-2                                          Social Work Team to live in Village                            5 Weeks 1-3                                          Social Research Team to do survey                          12 Weeks   3-4                                          Analyse results of survey                                            5 Weeks 2-4                                          Establish Mother & Child Health Program              14 Weeks 3-5                                          Establish Rural Credit Programme                             15 Weeks 4-5                                          carry out Immunisation of under Fives                   4 Weeks   Draw the arrow diagram, using the helpful numbering of the activities, which suggests the following logic: Unless the Social Work team lives in the village, the Mother and Child Health Programme cannot be started due to ignorance and superstition of the villagers The Analysis of the survey can obviously be done only after the survey is complete. Until rural survey is done, the Rural Credit Programme cannot be started Unless Mother and Child Programme is established, the Immunization of Under Fives cannot be started – Calculate the Earliest and Latest Event Times – Tabulate and Analyze the Activities – Schedule the Project Using a Gantt Char

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
100%

A Social Project manager is faced with a project with the following activities:

 Activity-ID                                          Description                                                         Duration

1-2                                          Social Work Team to live in Village                            5 Weeks

1-3                                          Social Research Team to do survey                          12 Weeks  

3-4                                          Analyse results of survey                                            5 Weeks

2-4                                          Establish Mother & Child Health Program              14 Weeks

3-5                                          Establish Rural Credit Programme                             15 Weeks

4-5                                          carry out Immunisation of under Fives                   4 Weeks

 

  • Draw the arrow diagram, using the helpful numbering of the activities, which suggests the following logic:
  • Unless the Social Work team lives in the village, the Mother and Child Health Programme cannot be started due to ignorance and superstition of the villagers
  • The Analysis of the survey can obviously be done only after the survey is complete.
  • Until rural survey is done, the Rural Credit Programme cannot be started
  • Unless Mother and Child Programme is established, the Immunization of Under Fives cannot be started
  • – Calculate the Earliest and Latest Event Times
  • – Tabulate and Analyze the Activities
  • Schedule the Project Using a Gantt Char
A Social Project manager is faced with a project with the following activities:
Duration
5 Weeks
12 Weeks
5 Weeks
Activity-ID
1-2
Description
Social Work Team to live in Village
Social Research Team to do survey
Analyse results of survey
Establish Mother & Child Health Program 14 Weeks
Establish Rural Credit Programme
Carry out Immunisation of Under Fives
1-3
3-4
2-4
3-5
4-5
15 Weeks
4 Weeks .
Draw the arrow diagram, using the helpful numbering of the activities, which suggests the following
logic:
• Unless the Social Work team lives in the village, the Mother and Child Health Programme cannot
be started due to ignorance and superstition of the villagers
The Analysis of the survey can obviously be done only after the survey is complete.
Until rural survey is done, the Rural Credit Programme cannot be started
Unless Mother and Child Programme is established, the Immunisation of Under Fives cannot be
started
- Calculate the Earliest and Latest Event Times
- Tabulate and Analyse the Activities
- Schedule the Project Using a Gantt Char
HANGL
Transcribed Image Text:A Social Project manager is faced with a project with the following activities: Duration 5 Weeks 12 Weeks 5 Weeks Activity-ID 1-2 Description Social Work Team to live in Village Social Research Team to do survey Analyse results of survey Establish Mother & Child Health Program 14 Weeks Establish Rural Credit Programme Carry out Immunisation of Under Fives 1-3 3-4 2-4 3-5 4-5 15 Weeks 4 Weeks . Draw the arrow diagram, using the helpful numbering of the activities, which suggests the following logic: • Unless the Social Work team lives in the village, the Mother and Child Health Programme cannot be started due to ignorance and superstition of the villagers The Analysis of the survey can obviously be done only after the survey is complete. Until rural survey is done, the Rural Credit Programme cannot be started Unless Mother and Child Programme is established, the Immunisation of Under Fives cannot be started - Calculate the Earliest and Latest Event Times - Tabulate and Analyse the Activities - Schedule the Project Using a Gantt Char HANGL
Expert Solution
steps

Step by step

Solved in 5 steps with 5 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.