The following table shows the various activities of the development of a new product in your organization. Activity Event Immediate Predecessor(s) Estimates of Activity Duration (Weeks) Optimistic (To) Most Likely (Tm) Pessimistic (Tp) Average (Te) 1 A - 2 3 4 ? 2 B A 1 2 ? 2 3 C A 1 ? 4 2.2 4 D B ? 5 6 5 5 E B 3 ? 5 4 6 F C 2 3 ? 3 7 G D ? 2 4 2.2 8 H E,F, G 3 4 6 ? 9 I H 3 ? 5 4 10 J I 2 1 3 ? Questions: Calculate ALL the missing (?) data points. Draw the PERT network from the given data. Determine ALL the paths, the critical path and its total duration in days. Explain the limitations of the Gantt Cart as a planning tool.
The following table shows the various activities of the development of a new product in your organization. Activity Event Immediate Predecessor(s) Estimates of Activity Duration (Weeks) Optimistic (To) Most Likely (Tm) Pessimistic (Tp) Average (Te) 1 A - 2 3 4 ? 2 B A 1 2 ? 2 3 C A 1 ? 4 2.2 4 D B ? 5 6 5 5 E B 3 ? 5 4 6 F C 2 3 ? 3 7 G D ? 2 4 2.2 8 H E,F, G 3 4 6 ? 9 I H 3 ? 5 4 10 J I 2 1 3 ? Questions: Calculate ALL the missing (?) data points. Draw the PERT network from the given data. Determine ALL the paths, the critical path and its total duration in days. Explain the limitations of the Gantt Cart as a planning tool.
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
100%
- The following table shows the various activities of the development of a new
product in your organization.
Activity |
Event |
Immediate Predecessor(s) |
Estimates of Activity Duration (Weeks) |
|||
Optimistic (To) |
Most Likely (Tm) |
Pessimistic (Tp) |
Average (Te) |
|||
1 |
A |
- |
2 |
3 |
4 |
? |
2 |
B |
A |
1 |
2 |
? |
2 |
3 |
C |
A |
1 |
? |
4 |
2.2 |
4 |
D |
B |
? |
5 |
6 |
5 |
5 |
E |
B |
3 |
? |
5 |
4 |
6 |
F |
C |
2 |
3 |
? |
3 |
7 |
G |
D |
? |
2 |
4 |
2.2 |
8 |
H |
E,F, G |
3 |
4 |
6 |
? |
9 |
I |
H |
3 |
? |
5 |
4 |
10 |
J |
I |
2 |
1 |
3 |
? |
Questions:
- Calculate ALL the missing (?) data points.
- Draw the PERT network from the given data.
- Determine ALL the paths, the critical path and its total duration in days.
Explain the limitations of the Gantt Cart as a planning tool.
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 4 steps with 5 images
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Recommended textbooks for you
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.