A shop makes coffees to order with a separate person working at each of the steps. Assume an 8 hour work day. Take the order 1 min/order Grind beans; make coffee 3 min/order Add toppings 4 min/order b) What is the total flow time? [Select] Add lid or straw 2 min/order a) What is the current maximum output ("capacity") of the process? 120 orders per day c) What is the total cycle time? [Select] d) Is there a benefit if we shift 1 min from grind beans to the order taking step? (e.g., make grinding beans take less time) [Select] e) Is there any benefit if we shift 1 min from toppings to the add lid step? (e.g., make toppings take less time) [Select] f) Go back to the original problem. If we add another person, where would we add him/her? [Select] What would the benefit be? [Select]
A shop makes coffees to order with a separate person working at each of the steps. Assume an 8 hour work day. Take the order 1 min/order Grind beans; make coffee 3 min/order Add toppings 4 min/order b) What is the total flow time? [Select] Add lid or straw 2 min/order a) What is the current maximum output ("capacity") of the process? 120 orders per day c) What is the total cycle time? [Select] d) Is there a benefit if we shift 1 min from grind beans to the order taking step? (e.g., make grinding beans take less time) [Select] e) Is there any benefit if we shift 1 min from toppings to the add lid step? (e.g., make toppings take less time) [Select] f) Go back to the original problem. If we add another person, where would we add him/her? [Select] What would the benefit be? [Select]
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
Please do not give solution in image format thanku
![A shop makes coffees to order with a separate person working at each of the steps. Assume an 8
hour work day.
Take the
order
1 min/order
Grind beans;
make coffee
3 min/order
Add toppings
4 min/order
b) What is the total flow time? [Select]
Add lid
or straw
2 min/order
a) What is the current maximum output ("capacity") of the process? 120 orders per day
c) What is the total cycle time? [Select]
d) Is there a benefit if we shift 1 min from grind beans to the order taking step? (e.g., make grinding
beans take less time) [Select]
e) Is there any benefit if we shift 1 min from toppings to the add lid step? (e.g., make toppings take
less time) [Select]
f) Go back to the original problem. If we add another person, where would we add him/her?
[Select]
What would the benefit be? [Select]](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2Fda8c3394-7575-4b90-9d88-13d960683781%2F4123c7d5-9f53-4882-9fd5-ef9f81aa6264%2Fnlxms7_processed.png&w=3840&q=75)
Transcribed Image Text:A shop makes coffees to order with a separate person working at each of the steps. Assume an 8
hour work day.
Take the
order
1 min/order
Grind beans;
make coffee
3 min/order
Add toppings
4 min/order
b) What is the total flow time? [Select]
Add lid
or straw
2 min/order
a) What is the current maximum output ("capacity") of the process? 120 orders per day
c) What is the total cycle time? [Select]
d) Is there a benefit if we shift 1 min from grind beans to the order taking step? (e.g., make grinding
beans take less time) [Select]
e) Is there any benefit if we shift 1 min from toppings to the add lid step? (e.g., make toppings take
less time) [Select]
f) Go back to the original problem. If we add another person, where would we add him/her?
[Select]
What would the benefit be? [Select]
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Step 1: State the given information
VIEWStep 2: a) Find the current maximum output of the process
VIEWStep 3: b) & c) Calculate the total flow time and total cycle time
VIEWStep 4: d) Discuss the benefit if 1 min is shifted from grind beans to order taking step
VIEWStep 5: e) Discuss the benefit if 1 min is shifted from toppings to add lid step
VIEWStep 6: f) Discuss the impact of adding another person
VIEWSolution
VIEWTrending now
This is a popular solution!
Step by step
Solved in 7 steps with 6 images

Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education


Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning

Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.