A proposed earth embankment requires 60,000 cubic meters of soil. The soil will be compacted to a void ratio of 0.85. Two borrow pits designated as A and B are available near the site. The void ratio of the soil in each pit and the estimated cost per cubic meter for moving the soil to the site are as shown below. Pit Void Ratio Cost ($/m3) A 1.10 5.00 B 1.80 3.70 Which will have the lowest cost to move and be the most economical to use?

Fundamentals Of Construction Estimating
4th Edition
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Pratt, David J.
Chapter4: Measuring Site Work, Excavation, And Piling
Section: Chapter Questions
Problem 4RQ
icon
Related questions
Question

A proposed earth embankment requires 60,000 cubic meters of soil. The soil will be compacted to a void ratio of 0.85. Two borrow pits designated as A and B are available near the site. The void ratio of the soil in each pit and the estimated cost per cubic meter for moving the soil to the site are as shown below.

Pit Void Ratio Cost ($/m3)
A 1.10 5.00
B 1.80 3.70

Which will have the lowest cost to move and be the most economical to use?

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 9 images

Blurred answer
Knowledge Booster
Pricing excavation and backfill
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Fundamentals Of Construction Estimating
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning