Your company has won a contract to provide and compact the fill material for an earth levee, with the dimensions shown below. The levee fill is a silty clay to be compacted at least 95% of maximum Standard Proctor of dry unit weight of 106 kN/m³ at an optimum moisture content of 18%. Yours borrow pit has a silty clay with an in-situ density of 112.1 pcf at 18%, and a specific gravity of 2.68. When the soil is excavated and loaded on to your trucks, the void ratio of the material is e = 1.47. Your trucks cam haul 15 cubic yards of material per trip. a -) Determine the volume of fill required for the leave, b -) Determine the volume required from the borrow pit 20 ft 3:1 20 ft 60 ft 20 ft 40 ft 2:1
Your company has won a contract to provide and compact the fill material for an earth levee, with the dimensions shown below. The levee fill is a silty clay to be compacted at least 95% of maximum Standard Proctor of dry unit weight of 106 kN/m³ at an optimum moisture content of 18%. Yours borrow pit has a silty clay with an in-situ density of 112.1 pcf at 18%, and a specific gravity of 2.68. When the soil is excavated and loaded on to your trucks, the void ratio of the material is e = 1.47. Your trucks cam haul 15 cubic yards of material per trip. a -) Determine the volume of fill required for the leave, b -) Determine the volume required from the borrow pit 20 ft 3:1 20 ft 60 ft 20 ft 40 ft 2:1
Principles of Foundation Engineering (MindTap Course List)
8th Edition
ISBN:9781305081550
Author:Braja M. Das
Publisher:Braja M. Das
Chapter16: Soil Improvement And Ground Modification
Section: Chapter Questions
Problem 16.12P
Related questions
Question

Transcribed Image Text:Your company has won a contract to provide and compact the fill material for an earth levee, with
the dimensions shown below. The levee fill is a silty clay to be compacted at least 95% of maximum
Standard Proctor of dry unit weight of 106 kN/m³ at an optimum moisture content of 18%. Yours
borrow pit has a silty clay with an in-situ density of 112.1 pcf at 18%, and a specific gravity of 2.68.
When the soil is excavated and loaded on to your trucks, the void ratio of the material is e = 1.47.
Your trucks cam haul 15 cubic yards of material per trip. a -) Determine the volume of fill required
for the leave, b -) Determine the volume required from the borrow pit
20 ft
3:1
20 ft
60 ft
20 ft
40 ft
2:1
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 3 steps

Recommended textbooks for you

Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781305081550
Author:
Braja M. Das
Publisher:
Cengage Learning

Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning

Fundamentals of Geotechnical Engineering (MindTap…
Civil Engineering
ISBN:
9781305635180
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning

Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781305081550
Author:
Braja M. Das
Publisher:
Cengage Learning

Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning

Fundamentals of Geotechnical Engineering (MindTap…
Civil Engineering
ISBN:
9781305635180
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning

Principles of Geotechnical Engineering (MindTap C…
Civil Engineering
ISBN:
9781305970939
Author:
Braja M. Das, Khaled Sobhan
Publisher:
Cengage Learning

Construction Materials, Methods and Techniques (M…
Civil Engineering
ISBN:
9781305086272
Author:
William P. Spence, Eva Kultermann
Publisher:
Cengage Learning