A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 150 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and Grespectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task Gneeded, task F to be completed. The processing times for tasks, A, B, C, D, E. F, and Gare 2.3, 2.1,0.9, 1.0, 1.2, 1.8, and 1.5 minutes respectively. Applying the most remaining tasks rule for balancing the assembly line, with ties broken according to longest task time first, the tasks that will be assigned to the FIRST workstation are O a. None O b. None is the correct answer Oc AB O d. Aonly O e AB, andC
A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 150 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and Grespectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task Gneeded, task F to be completed. The processing times for tasks, A, B, C, D, E. F, and Gare 2.3, 2.1,0.9, 1.0, 1.2, 1.8, and 1.5 minutes respectively. Applying the most remaining tasks rule for balancing the assembly line, with ties broken according to longest task time first, the tasks that will be assigned to the FIRST workstation are O a. None O b. None is the correct answer Oc AB O d. Aonly O e AB, andC
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter4: Linear Programming Models
Section: Chapter Questions
Problem 111P
Related questions
Question
I want the answer
![A manufacturer is designing a product layout for a new product production. It plans to use a production
line for 8 hours per day in order to meet forecasted demand of 150 units per day. The product requires 7
tasks in total. These tasks are namely, A, B, C, D, E, F, and Grespectively. Task A does not have any
predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task
B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon
completion of Task C. Whereas starting task Fneeds the completion of both the tasks Dand E. Finally,
starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and Gare
2.3, 2.1,0.9, 1.0, 1.2, 1.8, and 1.5 minutes respectively. Applying the most remaining tasks rule for
balancing the assembly line, with ties broken according to longest task time first, the tasks that will be
assigned to the FIRST workstation are
O a. None
O b. None is the correct answer
Oc AB
O d. A only
Oe.
A, B, and C](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F19c43934-1648-4b88-85be-3c19702fce8b%2Fa4ba8bc4-9fd8-4fcf-aaeb-9b0dc9a1e4a4%2Fdocn1hb_processed.jpeg&w=3840&q=75)
Transcribed Image Text:A manufacturer is designing a product layout for a new product production. It plans to use a production
line for 8 hours per day in order to meet forecasted demand of 150 units per day. The product requires 7
tasks in total. These tasks are namely, A, B, C, D, E, F, and Grespectively. Task A does not have any
predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task
B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon
completion of Task C. Whereas starting task Fneeds the completion of both the tasks Dand E. Finally,
starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and Gare
2.3, 2.1,0.9, 1.0, 1.2, 1.8, and 1.5 minutes respectively. Applying the most remaining tasks rule for
balancing the assembly line, with ties broken according to longest task time first, the tasks that will be
assigned to the FIRST workstation are
O a. None
O b. None is the correct answer
Oc AB
O d. A only
Oe.
A, B, and C
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps with 1 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Recommended textbooks for you
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,