A maintenance building construction project also includes an external electrical generator and water tank. The first activity is to excavate which requires two weeks. Following excavation, the maintenance building will be built, and then both the generator and the water tank can be installed. These three activities, building, generator, and tank, require six, four, and two weeks, respectively. Once this set of three activities is completed, the tank and generator can be connected to the building, an activity that requires five weeks. After the maintenance. building is built, maintenance equipment can also be installed inside the building and this activity takes four weeks. Painting the maintenance building is also required, following its construction, and this takes three weeks. Finally, after the maintenance equipment is installed and the connection is completed, it will take two weeks to inspect the new maintenance facility. Suppose the costs of the activities are: Activity Excavate Construct Building Install Generator Install Tank Connect Install Maintenance. Paint Inspect Cost ($1000s) $50 $150 $120 $50 $40 $30 $30 $10 Suppose 5 weeks of the project have elapsed. The following work has occurred: Activity Percent Complete Actual Cost (1000s) Excavate 100% $60 Construct Building 50% $75 Install Generator Install Tank 75% 80% What is the current cost performance index and an assessment of performance? Note: Answers rounded to 2 significant digits. 0.89 and the project is behind with respect to budget. 0.96 and the project is ahead with respect to budget. 1.00 and the project is on budget. 1.04 and the project is ahead with respect to budget. 1.12 and the project is behind with respect to budget. $100 $50 None of the answers are correct.
A maintenance building construction project also includes an external electrical generator and water tank. The first activity is to excavate which requires two weeks. Following excavation, the maintenance building will be built, and then both the generator and the water tank can be installed. These three activities, building, generator, and tank, require six, four, and two weeks, respectively. Once this set of three activities is completed, the tank and generator can be connected to the building, an activity that requires five weeks. After the maintenance. building is built, maintenance equipment can also be installed inside the building and this activity takes four weeks. Painting the maintenance building is also required, following its construction, and this takes three weeks. Finally, after the maintenance equipment is installed and the connection is completed, it will take two weeks to inspect the new maintenance facility. Suppose the costs of the activities are: Activity Excavate Construct Building Install Generator Install Tank Connect Install Maintenance. Paint Inspect Cost ($1000s) $50 $150 $120 $50 $40 $30 $30 $10 Suppose 5 weeks of the project have elapsed. The following work has occurred: Activity Percent Complete Actual Cost (1000s) Excavate 100% $60 Construct Building 50% $75 Install Generator Install Tank 75% 80% What is the current cost performance index and an assessment of performance? Note: Answers rounded to 2 significant digits. 0.89 and the project is behind with respect to budget. 0.96 and the project is ahead with respect to budget. 1.00 and the project is on budget. 1.04 and the project is ahead with respect to budget. 1.12 and the project is behind with respect to budget. $100 $50 None of the answers are correct.
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 2 images
Recommended textbooks for you
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.