Bronson Construction must complete six road repair projects before winter weather ends the construction season, In each case, Bronson has been hired to remove an old road in a process known as milling, and then replace that road with new pavement. How much time is required to mill and then pave a certain road depends on how much of the old road needs removal, whether Bronson is allowed to completely close that road while working, and the total area of new paving. Based on these factors, Bronson has developed the following estimates for each of the six road repair projects: DETOUR Location Milling (days) Paving (days) Site A Union Road Site B Seneca Street Site C Transit Road 7. 6 Site D Bailey Avenue 3. Site E Main Street 4 Site F Losson Road 3. Bronson Construction has one milling operation and one paving operation avail- able to work on these six projects. Because Bronson Construction is worried about bad weather ending the construction season, the company intends to operate every day until these projects are completed. Questions 1. Using Johnson's rule, determine the sequence in which Bronson Construction should complete the six road repair projects. 2. Prepare a Gantt chart illustrating this sequence. What is the makespan of this schedule? 3. If Bronson Construction started work tomorrow, when would the paving operation actually start work? After the paving operation starts work, how many days would that operation be idle during the time required to complete all the projects? 4. Bronson Construction is allowed to close Site F, Losson Road, while working at that site. Assuming that October 1st is the first day of work toward completing the entire schedule, when will Losson Road be closed and when will it reopen?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

snip

Bronson Construction must complete six road repair projects before winter
weather ends the construction season, In each case, Bronson has been hired
to remove an old road in a process known as milling, and then replace that
road with new pavement. How much time is required to mill and then pave
a certain road depends on how much of the old road needs removal, whether
Bronson is allowed to completely close that road while working, and the
total area of new paving. Based on these factors, Bronson has developed the
following estimates for each of the six road repair projects:
DETOUR
Location
Milling (days) Paving (days)
Site A
Union Road
Site B
Seneca Street
Site C
Transit Road
7.
6
Site D
Bailey Avenue
3.
Site E
Main Street
4
Site F
Losson Road
3.
Bronson Construction has one milling operation and one paving operation avail-
able to work on these six projects. Because Bronson Construction is worried about bad
weather ending the construction season, the company intends to operate every day until
these projects are completed.
Questions
1. Using Johnson's rule, determine the sequence in which Bronson Construction should
complete the six road repair projects.
2. Prepare a Gantt chart illustrating this sequence. What is the makespan of this schedule?
3. If Bronson Construction started work tomorrow, when would the paving operation
actually start work? After the paving operation starts work, how many days would
that operation be idle during the time required to complete all the projects?
4. Bronson Construction is allowed to close Site F, Losson Road, while working at that
site. Assuming that October 1st is the first day of work toward completing the entire
schedule, when will Losson Road be closed and when will it reopen?
Transcribed Image Text:Bronson Construction must complete six road repair projects before winter weather ends the construction season, In each case, Bronson has been hired to remove an old road in a process known as milling, and then replace that road with new pavement. How much time is required to mill and then pave a certain road depends on how much of the old road needs removal, whether Bronson is allowed to completely close that road while working, and the total area of new paving. Based on these factors, Bronson has developed the following estimates for each of the six road repair projects: DETOUR Location Milling (days) Paving (days) Site A Union Road Site B Seneca Street Site C Transit Road 7. 6 Site D Bailey Avenue 3. Site E Main Street 4 Site F Losson Road 3. Bronson Construction has one milling operation and one paving operation avail- able to work on these six projects. Because Bronson Construction is worried about bad weather ending the construction season, the company intends to operate every day until these projects are completed. Questions 1. Using Johnson's rule, determine the sequence in which Bronson Construction should complete the six road repair projects. 2. Prepare a Gantt chart illustrating this sequence. What is the makespan of this schedule? 3. If Bronson Construction started work tomorrow, when would the paving operation actually start work? After the paving operation starts work, how many days would that operation be idle during the time required to complete all the projects? 4. Bronson Construction is allowed to close Site F, Losson Road, while working at that site. Assuming that October 1st is the first day of work toward completing the entire schedule, when will Losson Road be closed and when will it reopen?
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 1 images

Blurred answer
Knowledge Booster
Introduction to Forecasting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.