a) Draw the network diagram showing ES, EF, LS, LF, and the critical path. b) Perform CPM calculations and complete the table below. c) Crash the schedule one day at time and show the effect of crashing each activity on the network by crossing out values and writing the new ones immediately above or below it. d) Calculate the normal, least-cost, and crash duration for the project. Then calculate the cost associated with each duration. Indirect cost (overhead) is $100 per day. e) Draw the graph of the total cost corresponding to the crashing exercise:
a) Draw the network diagram showing ES, EF, LS, LF, and the critical path. b) Perform CPM calculations and complete the table below. c) Crash the schedule one day at time and show the effect of crashing each activity on the network by crossing out values and writing the new ones immediately above or below it. d) Calculate the normal, least-cost, and crash duration for the project. Then calculate the cost associated with each duration. Indirect cost (overhead) is $100 per day. e) Draw the graph of the total cost corresponding to the crashing exercise:
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question

Transcribed Image Text:a) Draw the network diagram showing ES, EF, LS, LF, and the critical path.
b) Perform CPM calculations and complete the table below.
c) Crash the schedule one day at time and show the effect of crashing each activity on the network by
crossing out values and writing the new ones immediately above or below it.
d) Calculate the normal, least-cost, and crash duration for the project. Then calculate the cost associated
with each duration. Indirect cost (overhead) is $100 per day.
e) Draw the graph of the total cost corresponding to the crashing exercise:
Activity IPA
A
B
H
Activity
A
B
с
D
E
F
G
A
B
B, C
C
D, F
E, F
G, H
IPA
A
A
B
B, C
C
D, F
Duration
Normal
7
6
18
10
6
+
7
Duration
7
6
10
6
4
4
Crash
5
7
4
3
2
14
2
ES
Cost $
Normal
$500
$550
$800
$1,200
$600
$500
$700
$650
$300
EF
Crash
$640
$630
$935
$1,440
$700
$590
$1,000
$950
$300
LS
LF
TF
FF
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 7 steps with 10 images

Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education


Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning

Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.