A contractor is planning a job that will require a large amount of gravel and sand. The estimates for the necessary gravel and sand are: Coarse gravel Fine gravel Sand 20,000 yd³ 29,000 yd³ 20,000 yd³ There are two pits from which material can be obtained, and the plan is to haul from these two pits and to separate (screen) on the job whatever material is needed. Analysis shows that the material at each pit has the following composition: Pit A Pit B Coarse gravel Fine gravel Sand Waste 20% 14% 25% 41% 30% 50% 20% 0%

Advanced Engineering Mathematics
10th Edition
ISBN:9780470458365
Author:Erwin Kreyszig
Publisher:Erwin Kreyszig
Chapter2: Second-order Linear Odes
Section: Chapter Questions
Problem 1RQ
icon
Related questions
Question
A contractor is planning a job that will require a large amount of gravel and sand. The
estimates for the necessary gravel and sand are:
Coarse gravel
Fine gravel
Sand
20,000 yd³
29,000 yd³
20,000 yd³
There are two pits from which material can be obtained, and the plan is to haul
from these two pits and to separate (screen) on the job whatever material is needed.
Analysis shows that the material at each pit has the following composition:
Pit A
Pit B
Coarse gravel
Fine gravel
Sand
Waste
20%
14%
25%
41%
30%
50%
20%
0%
It costs $8/yd³ for material and hauling from pit A and $16/yd³ from pit B. Set
this up as a linear programming problem to minimize delivered cost.
Formulate and Solve with graphical solution method AND with Excel (Provide
Model, Answer and Sensitivity Report)
Transcribed Image Text:A contractor is planning a job that will require a large amount of gravel and sand. The estimates for the necessary gravel and sand are: Coarse gravel Fine gravel Sand 20,000 yd³ 29,000 yd³ 20,000 yd³ There are two pits from which material can be obtained, and the plan is to haul from these two pits and to separate (screen) on the job whatever material is needed. Analysis shows that the material at each pit has the following composition: Pit A Pit B Coarse gravel Fine gravel Sand Waste 20% 14% 25% 41% 30% 50% 20% 0% It costs $8/yd³ for material and hauling from pit A and $16/yd³ from pit B. Set this up as a linear programming problem to minimize delivered cost. Formulate and Solve with graphical solution method AND with Excel (Provide Model, Answer and Sensitivity Report)
Expert Solution
steps

Step by step

Solved in 5 steps with 14 images

Blurred answer
Similar questions
Recommended textbooks for you
Advanced Engineering Mathematics
Advanced Engineering Mathematics
Advanced Math
ISBN:
9780470458365
Author:
Erwin Kreyszig
Publisher:
Wiley, John & Sons, Incorporated
Numerical Methods for Engineers
Numerical Methods for Engineers
Advanced Math
ISBN:
9780073397924
Author:
Steven C. Chapra Dr., Raymond P. Canale
Publisher:
McGraw-Hill Education
Introductory Mathematics for Engineering Applicat…
Introductory Mathematics for Engineering Applicat…
Advanced Math
ISBN:
9781118141809
Author:
Nathan Klingbeil
Publisher:
WILEY
Mathematics For Machine Technology
Mathematics For Machine Technology
Advanced Math
ISBN:
9781337798310
Author:
Peterson, John.
Publisher:
Cengage Learning,
Basic Technical Mathematics
Basic Technical Mathematics
Advanced Math
ISBN:
9780134437705
Author:
Washington
Publisher:
PEARSON
Topology
Topology
Advanced Math
ISBN:
9780134689517
Author:
Munkres, James R.
Publisher:
Pearson,