A contractor has a contract to construct a 12,000-ft-long tunnel in 30 months. He is trying to decide whether to do the job with his own forces or subcontract the job. He asks you to calculate the equivalent monthly cost of each alternative. His i = 1 percent per month. Production under both alternatives will be 300 ft per month. Alternative A Buy a tunneling machine and work with contractor's own forces. cost of tunneling and machine = $ 2,400,000 paid now salvage value of machine at EOM 30 = $ 540,000 cost of labor and materials = $ 250/ft for the first 10 months, increasing by 0.5%/month at EOM each month thereafter Alternative B Subcontract the work. Cost $500 per foot of advance of the tunnel heading, for the full 12,000 ft.

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question
A contractor has a contract to construct a
12,000-ft-long tunnel in 30 months. He is
trying to decide whether to do the job with
his own forces or subcontract the job. He asks
you to calculate the equivalent monthly cost
of each alternative. His i = 1 percent per
month. Production under both alternatives
will be 300 ft per month.
Alternative A
Buy a tunneling machine and work with
contractor's own forces.
cost of tunneling and machine = $ 2,400,000
paid now
salvage value of machine at EOM 30 = $
540,000
cost of labor and materials = $ 250/ft for the
first 10 months, increasing by 0.5%/month at
EOM each month thereafter
Alternative B
Subcontract the work. Cost $500 per foot of
advance of the tunnel heading, for the full
12,000 ft.
%3D
Transcribed Image Text:A contractor has a contract to construct a 12,000-ft-long tunnel in 30 months. He is trying to decide whether to do the job with his own forces or subcontract the job. He asks you to calculate the equivalent monthly cost of each alternative. His i = 1 percent per month. Production under both alternatives will be 300 ft per month. Alternative A Buy a tunneling machine and work with contractor's own forces. cost of tunneling and machine = $ 2,400,000 paid now salvage value of machine at EOM 30 = $ 540,000 cost of labor and materials = $ 250/ft for the first 10 months, increasing by 0.5%/month at EOM each month thereafter Alternative B Subcontract the work. Cost $500 per foot of advance of the tunnel heading, for the full 12,000 ft. %3D
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 5 images

Blurred answer
Knowledge Booster
Pricing of General Work
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning