a) Construct the project network. (Submit a file with a maximum size of 1 MB.) This answer has not been graded yet. (b) Based solely on the critical path, estimate the probability that the project will be complete within 12 weeks. (Round your answer to four decimal places.) (c) Using all paths through the project network, estimate the probability that the project will be complete within 12 weeks. (Round your answer to four decimal places.)
Time (Weeks) | |||||
---|---|---|---|---|---|
Activity | Description | Immediate Predecessor |
Optimistic | Most Probable | Pessimistic |
A | Report generation | 2 | 9 | 13 | |
B | Web scraping | 6 | 10 | 12 | |
C | Testing | A, B | 1 | 1 | 1 |
This answer has not been graded yet.
As per Bartleby guidelines, we can only solve the first three subparts of one question at a time...Kindly upload the other subparts of the question separately for a quick response. THANK YOU!
Conceptual Introduction:-
A network diagram shows the sequence of the task that is done to complete a project. It usually shows the link of each task with the duration taken by each activity with respect to the completion of the project. Each task is shown with the nodes that are connected with each other with the help of arrows. There are 2 types of network diagrams:- CPM and PERT.