(3) A project was planned using PERT. Its expected completion time was determined to be 85 days. The variance of 1 path is 49. What is the probability the project will be completed within 75 days (5 decimal places) Let X=the project completion time. PLX Please show how you use the Normal Curve Table to obtain your a (4) Perform a project nagement analysis for the data given below to determine ES, EF, LS, LF, and slack for each activity, the total peoyut oompletion time, and the critical puthe Activity || Time (weeks) | Predecessors A in the space below. 11 13 С 10 A 17 C.E D A 14 D.F (a) Draw a network with t, ES, EF, LS, and LF (follow the same format as Figure 11.5 on p.394) B С (b) Complete the following table (similar in format to Table 11.3 on p.396) Activity ES EF LS A D E F G H Activity | Time (weeks) | Predecessors B E F B (c) Identify the critical path(s): (4) Based on your analysis, the project completion time is: LF Slack Critical weeks and the least critical activity is
(3) A project was planned using PERT. Its expected completion time was determined to be 85 days. The variance of 1 path is 49. What is the probability the project will be completed within 75 days (5 decimal places) Let X=the project completion time. PLX Please show how you use the Normal Curve Table to obtain your a (4) Perform a project nagement analysis for the data given below to determine ES, EF, LS, LF, and slack for each activity, the total peoyut oompletion time, and the critical puthe Activity || Time (weeks) | Predecessors A in the space below. 11 13 С 10 A 17 C.E D A 14 D.F (a) Draw a network with t, ES, EF, LS, and LF (follow the same format as Figure 11.5 on p.394) B С (b) Complete the following table (similar in format to Table 11.3 on p.396) Activity ES EF LS A D E F G H Activity | Time (weeks) | Predecessors B E F B (c) Identify the critical path(s): (4) Based on your analysis, the project completion time is: LF Slack Critical weeks and the least critical activity is
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 3 steps with 6 images
Recommended textbooks for you
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.