1). Based on the below table: (a) Construct a network for this problem. (b) Determine the expected time and variance for each activity. (c) Determine ES, EF, LS, LF, and slack for each activity. (d) Determine the critical path and project completion time. (e) Determine the probability that the project will be finished in 70 days or less. (f) Determine the probability that the project will be finished in 80 days or less. (g) Determine the probability that the project will be finished in 90 days or less. IMMEDIATE PREDECESSORS DAYS ACTIVITY 10 12 7 3 3 4 D 10 20 30 6 7 8 9 10 6 7 10 15 E R D, E R D, E 11 14 16 10 11 13 7 G,H 4 7 1 2 4.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
ull Tsel-PakaiMasker LTE
1 09.03
O 1 0 70%
Assignment c..
Assignment chapter 17: Project Management
1). Based on the below table:
(a) Construct a network for this problem.
(b) Determine the expected time and variance for each activity.
(c) Determine ES, EF, LS, LF, and slack for each activity.
(d) Determine the critical path and project completion time.
(e) Determine the probability that the project will be finished in 70 days or less.
(f) Determine the probability that the project will be finished in 80 days or less.
(g) Determine the probability that the project will be finished in 90 days or less.
IMMEDIATE
PREDECESSORS
DAYS
ACTIVITY
8 10 12
6 7 9
B
3
3
4
10 20 30
6 7 8
9 10
6 7 10
E
11
R D, E
R, D, E
H
14
15
16
F
10
11
13
F
6
7 8
G.H
K
4 7
L.
2
4
G,H
2). Based on the below table:
a. Construct the network.
b. How long will it take to finish the project?
C.. What is the critical path activities?
d. If the project is to be finished in 16 weeks, which activities should be crashed?
e. If the project is to be finished in 15 weeks, which activities should be crashed?
NORMAL CRASH
TIME
IMMEDIATE
TIME NORMAL CRASH
ACTIVITY PREDECESSOR (WEEKS) (WEEKS) COST (S) COST (S)
KO00
4.
3
9,000
10.p00
12,000
15000
2.
15,000
15,500
5,000
8,700
7,500
DE
KO00
9,400
FG
3
5,000
6,0
Transcribed Image Text:ull Tsel-PakaiMasker LTE 1 09.03 O 1 0 70% Assignment c.. Assignment chapter 17: Project Management 1). Based on the below table: (a) Construct a network for this problem. (b) Determine the expected time and variance for each activity. (c) Determine ES, EF, LS, LF, and slack for each activity. (d) Determine the critical path and project completion time. (e) Determine the probability that the project will be finished in 70 days or less. (f) Determine the probability that the project will be finished in 80 days or less. (g) Determine the probability that the project will be finished in 90 days or less. IMMEDIATE PREDECESSORS DAYS ACTIVITY 8 10 12 6 7 9 B 3 3 4 10 20 30 6 7 8 9 10 6 7 10 E 11 R D, E R, D, E H 14 15 16 F 10 11 13 F 6 7 8 G.H K 4 7 L. 2 4 G,H 2). Based on the below table: a. Construct the network. b. How long will it take to finish the project? C.. What is the critical path activities? d. If the project is to be finished in 16 weeks, which activities should be crashed? e. If the project is to be finished in 15 weeks, which activities should be crashed? NORMAL CRASH TIME IMMEDIATE TIME NORMAL CRASH ACTIVITY PREDECESSOR (WEEKS) (WEEKS) COST (S) COST (S) KO00 4. 3 9,000 10.p00 12,000 15000 2. 15,000 15,500 5,000 8,700 7,500 DE KO00 9,400 FG 3 5,000 6,0
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 5 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.