0 5 4 A 5 What is the Early Finish for Activity B? A: 10 B: 12 C: 3 Answer: 0 10 B 10 D: 13 0 10 C 3 If the network was Contiguous, what would be the Early Start for Activity C? A: 5 C: 3 B: 10 D: 7 Answer:
Q: Activity 2: Consider the following immediate preceding activity table. Draw the network and…
A: A network diagram is a visual representation of a project which helps to identify the activity…
Q: Which project management approach follows a deterministic approach and assumes the activity duration…
A: The principal network-linked project management approaches that show the flow & order of…
Q: Consider the following data for a project to install a new server at the Northland Pines High…
A: ActivityActivity time Immediate predecessors A1-B4AC5AD4BE1BF7B, CG3D, EH2FI3FJ6G, H, I
Q: Draw the network diagram for the whole project (with AoN Activity on Node)
A: Activity-on-node could be a project management term that refers to a precedence schematization…
Q: Draw a project network diagram (AON), given the following information. Complete the forward and…
A: A network diagram representing the activity relationship in a project by visualizing nodes and…
Q: Given the network shown above, what is the earliest start time for activity F? Given the…
A: The earliest start time for activity F, based on the network diagram provided, is at the end of the…
Q: he table below show a set of activities of an IS project,its expected completion time (ET) and…
A: Network Diagram : Critical Path = A-B-C-D-G-H Project Completion time = 7+9+5+17+10+7 = 55
Q: Draw the Project Network
A: A network diagram is a visual picture of a project which helps to identify the activity relationship…
Q: Please answer all parts Activity Preceding activity Activity duration A - 6 B - 3 C - 1…
A: Note: - Since we can answer only up to three subparts we will answer the first three subparts…
Q: (i) Identify the critical activities and total duration for the project. (ii) Draw a network…
A:
Q: What is the earliest start time for Activity F? Multiple Choice
A: The Critical Path Method (CPM) is a project management process used to determine the most critical…
Q: Use this table as inputs to answer the questions below: Activity Total Budgeted Duration (months)…
A: Possible paths and duration: A-G = 4 B-E-F = 9 A-D = 5 C = 2 The critical path would be B-E-F with 9…
Q: Choose the correct network to represent this situation. DA Which activities are on the critical…
A: A network diagram shows the link between each task and the duration taken by each activity with…
Q: Use the following network with activities and times estimated in days to answer the questions. Start…
A: A network diagram is a graphical representation of project that helps to identify the activity…
Q: Normal Time Problem 1 You are the manager of a project to improve a billing process at your firm.…
A: Finding the Optimum Project Duration with Crashing and Penalty Costs: A Step-by-Step GuideIn project…
Q: Problem #2-Freeze Inc. is planning the implementation of a new sales offices in the Tampa - FL area…
A: ES = maximum (EF of all immediate predecessor) EF = ES + duration Minimum project duration = largest…
Q: Development of Version 2.0 of a particular accounting software product is being considered by Jose…
A: A network diagram is a graphical representation of project that helps to identify the activity…
Q: Draw the arrow diagram, using the helpful numbering of the activities, which suggests the following…
A: D(duration)=given in the question as normal time ES (Early start)= The first activity from where the…
Q: c. What is the total time of the minimum-cost schedule? (Enter your responses as whole numbers.) The…
A: We have arranged the activities according to normal time and calculated the critical path…
Q: Consider the following diagram, why is it used and explain what information does it provide to the…
A: The diagram is called the risk impact/probability chart. This diagram uses two dimensions;…
Q: Solve the following project by hand and submit your notes: Activity Normal Time (weeks) Crash…
A: NOTE: AS PER GUIDELINES, WE ARE ONLY ALLOWED TO DO THREE SUB-PARTS AT A TIME. PLEASE POST THE REST…
Q: Design a Gantt chart using the following data, removing blank spaces on the chart. TASK ASSIGN…
A: Gantt charts can be created manually using pen and paper, but they are most commonly created using…
Q: For the construction project represented by the activity network as 16 points shown below. Find one…
A:
Q: Company A has a project that will scheduled on March 15, 2021, so the Operation department prepared…
A: Project management schedule contains a list of project-related activities and deliverables, usually…
Q: 1 A = 1 B=2 C = 3 2 Figure 5-1: Network Diagram Example Click for accessible description 3 4…
A: A network diagram can be formed to schematically illustrate the sequence of the projects. In network…
Q: a) Provide FOUR (4) key decisions invalidating priority rankings in Project Portfolio Management.…
A: Project management is the aspect of management that is concerned with managing, allocating, and…
Q: Nikos Anastopoulos of EMPROSS Strategic IT Consultants, leads the development of a new football…
A: to find:the duration of the projectthe critical pathgiven:the activities with precedence…
Q: 3 LL 4 H 6
A: Given data: Activity Duration A 2 B 4 D 1 E 5 F 4 G 1 H 3
Q: How can I draw the network diagrams? How can I list the network paths? How can I determine the…
A: A network diagram shows the link of each task with the duration taken by each activity with respect…
Q: What is the critical path of the network?
A:
Q: The information in the table below is available for a large fund-raising project. Activity…
A: 1. During forward pass in case of more than two preceding activities the early start will be…
Q: A5 What is the late start time for activity A3 ? Late start time 4 days
A: 1. Take the ES of the initial activity as 0. 2. Add duration to this to get EF. 3. This EF will…
Q: In the cpm network diagram given below: a-Find the critical path and show it on the diagram.…
A: Find the Given details below:
Q: Based on the data presented in the table, draw a network diagram
A: ActivityPredecessor ActivityTimeA-3BA9CA11DB13EC9FC5GD,F15HE11IG,H8
Q: What is the earliest start time (EST) and latest: completion time (LCT) of activity B? OEST-9 and…
A: 1. Take the ES of the first activity as 0. 2. Add duration to this ES to get EF. 3. This EF will…
Q: Use the network below to answer the following questions 16 to 23. Note that projects start on Day 0.…
A: The critical path is the path that shows the longest path in the project network diagram. The…
Q: a) Based on the given information regarding the activities for the project, the project length =…
A: A network diagram related to the project shows the sequence of the task that is performed to…
Q: The table below contains data for the installation of new equipment in a manufacturing process for a…
A: Since you have submitted a question with multiple subparts, as per guidelines, we have answered the…
Q: Draw the network diagram and determine the minimum total time (in weeks) using the concept of…
A: Project crashing is a process which helps to reduce the total project completion time using…
Q: Develop an AON network for this problem. b) What is the critical path? c) What is the total project…
A: Given the data shown below, For this dataset, I would prepare the AON network diagram, this…
Q: Development of Version 2.0 of a particular accounting software product is being considered by Jose…
A: Find the Given details below: Activity Normal Time (NT) (Weeks) Normal cost (NC) ($) Crash Time…
Q: Make a list of the tasks that is necessary for Management Trainee Officer job in private banks.…
A: Below is the solution:-
Q: STADIO's top management asks you to manage the construction project of a new campus in Limpopo. Draw…
A: A work breakdown structure (WBS) is a hierarchical breakdown of the project deliverables into…
Q: Create the the network if it is accelerated according to the schedule above b.Find the cost and the…
A: The critical path is the path that has the longest duration among all other paths of a project to be…
Q: A large Southeast city is requesting federal funding for a park-and-ride project. One of the…
A: Find the Given details below:
Q: Kelle Carpet and Trim installs carpet in commercial offices. Peter Kelle has been very concerned…
A: The Critical Path Method provides project managers with a systematic approach to analyzing and…
Step by step
Solved in 3 steps
- The accompanying table shows the activities, times, and sequences required: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 3 B 2 C 4 4 6 6 DEFGHH I ✔A-C-F-G- ? A-B-E-I b. What is the critical path? (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer.) ? A-D-H- ? A-D-F-G- B ✓C c. Suppose you want to shorten the completion time as much as possible, and you have the option of shortening any or all of B. C, D. and G each one week. Which would you shorten? (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer.) ✔A-D-H- A A A B ? A-B-E-I C, D D, F D E, G, H d-1. What is the new critical path? (You may select more than one answer. Single click the box with the question mark to…b) – Draw the Activity-on-Node (AON) diagram using the following representation for every node: Activity Description Expected Time ES EF LS LF Slack C.) Complete the following table, determine the expected time of completion assuming that the project starts at week 0 (zero) and identify the critical path for this project. Demonstrate all your calculations. On Critical Path? Activity Activity Description ES EF LS LF Slack Yes or No Locate new facilities 2 Order furniture Interview prospective staff Hire and train staff 3 4. Remodel facilities Receive and set up furniture Move in and start up 6 7 a) Complete the following table, calculate the project variance and project standard deviation. Demonstrate all your calculations.Q1: Given the information below, draw the network (AOA) and find the probability of finishing the job in (40) weeks? Solve using PERT. Activity notation Weeks 1-2 2-3 2-4 2-5 3-6 4-7| 5-7 6-8 7-8 8-9 2,7,8 5,6,9 3,7,8 4,5,6 6,9,10 6,8,11 4,6,7 5,7,10 4,8,9 4,7,9 [50%]
- The table below contains information about an environmental clean-up project in the township of Hiles. Shorten the project threethree weeks by finding the minimum-cost schedule. Assume that project indirect costs and penalty costs are negligible. Identify activities to crash while minimizing the additional crash costs. Activity Normal Time (weekweeks) Crash Time (weekweeks) Cost to Crash ($ per weekweek) Immediate Predecessor(s) A 55 44 300300 None B 77 44 5050 None C 77 66 300300 A D 77 66 250250 A E 11 11 long dash— B F 33 33 long dash— C, D G 55 44 200200 D, E H 44 22 200200 F I 22 22 long dash— G Part 2 Fill in the table below with the activity times after crashing to show the resulting schedule. (Enter your responses as…Can anybody draw a network analysis diagram of this problem?Table 3 gives time estimates in weeks for each activity (Durations are Time Expected obtained using PERT) Activity Preceded 1 Order review 2 Order vendor parts 3 Produce standard parts 4 Design custom parts Software development 5 6 Manufacture custom parts 7 Assemble 8 Test Duration 5 15 20 13 18 10 10 5 1 1 1 4 2,3,6 2,5 Resources Ryan Carly Ryan Lauren Connor Ryan Dawn Test Assuming that you have been engaged to programme the project activities indicated in Table 3 and Figure A8.1B (Air Control Project: Time Plan without Resources), USE CCPM (Critical Chain Project Management) to ESTIMATE the project duration by showing each and every stage of your programming process (indicate technical dependency with resources imposed).
- Draw an activity network described in this precedence table, using as few dummies as possible. Activity A B C D E G H I J K L Must be preceded by: A с с B. D. E, F B.D.E. F F.D G, H, I F.D KQUESTION 16 Refer to the project addressed in questions 21-30 of your Quiz 1 and associated worked solutions used in our review session. The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for the project. Activity A B D E Table 1 Reference: Ref 1 optimistic most likely time time 3 4 2 6 5 5 8 3 9 9 pessimistic time 7 10 5 12 15 Activity Predecessor A A B, C D Using Table 1, which of the following statements are correct? O A. The latest finish time of activity B is the same as its earliest finish time O B. Activity A is critical because it is the starting activity in the project O C. Activity D must be critical because it is the only predecessor of activity E O D. Answers A and B are correct O E. Answers A and C are correctB/U pe Activity A B D 11. A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of $4,000 per week for every week the project exceeds 37 weeks. What is the lowest total cost for completing this project? Predecessor Time 18 11 A A B C E D Normal A H 12 15 3 19 Asbe de ABC' AMBBC RACE AB 7 8 12 6 Normal Cost Crash Time Crash Cost $22,000 $32,000 $62,000 $18,000 $35,000 $8,000 $23,000 $32,000 $56,000 $12,000 5 $18,000 19 $22,000 $9,000 $15,000 $5,000 $13,000 $20,000 $45,000 2 5 4