Table 3 gives time estimates in weeks for each activity (Durations are Time Expected obtained using PERT) Activity Preceded Duration Resources 1 Order review 2 Order vendor parts 3 Produce standard parts 4 Design custom parts 5 Software development 6 Manufacture custom parts 7 Assemble 8 Test 5 15 20 13 18 10 10 5 1 1 1 1 4 23,6 2,5 Ryan Carly Ryan Lauren Connor Ryan Dawn Test Assuming that you have been engaged to programme the project activities indicated in Table 3 and Figure A8.1B (Air Control Project: Time Plan without Resources), USE CCPM (Critical Chain Project Management) to ESTIMATE the project duration by showing each and every stage of your programming process (indicate technical dependency with resources imposed).
Table 3 gives time estimates in weeks for each activity (Durations are Time Expected obtained using PERT) Activity Preceded Duration Resources 1 Order review 2 Order vendor parts 3 Produce standard parts 4 Design custom parts 5 Software development 6 Manufacture custom parts 7 Assemble 8 Test 5 15 20 13 18 10 10 5 1 1 1 1 4 23,6 2,5 Ryan Carly Ryan Lauren Connor Ryan Dawn Test Assuming that you have been engaged to programme the project activities indicated in Table 3 and Figure A8.1B (Air Control Project: Time Plan without Resources), USE CCPM (Critical Chain Project Management) to ESTIMATE the project duration by showing each and every stage of your programming process (indicate technical dependency with resources imposed).
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question

Transcribed Image Text:Table 3 gives time estimates in weeks for each activity (Durations are Time Expected obtained using PERT)
Activity
Preceded
1
Order review
2
Order vendor parts
3 Produce standard
parts
4 Design custom parts
Software development
5
6 Manufacture custom
parts
7 Assemble
8
Test
Duration
5
15
20
13
18
10
10
5
1
1
1
4
2,3,6
2,5
Resources
Ryan
Carly
Ryan
Lauren
Connor
Ryan
Dawn
Test
Assuming that you have been engaged to programme the project activities indicated in Table 3 and Figure A8.1B (Air
Control Project: Time Plan without Resources),
USE CCPM (Critical Chain Project Management) to ESTIMATE the project duration by showing each and every stage of
your programming process (indicate technical dependency with resources imposed).
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 4 steps with 3 images

Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education


Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning

Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.