1) Using the table below, calculate the expected time for all the activities (20 points). Expected time = (o+4r+p)/6 2. a. Using above data, manually draw a network diagram for the above activities. (10 points).
b. Calculate the earliest completion times for each of the activities listed above (15 points). Earliest completion times: A = 6 B =6+7 = 13 C = 6+6= 12 D = 6+5 = 11 E = 11+8 = 19 F = 19+7 = 26 G = 19+5 = 24 H = 19+4 = 23 I = 26+4 = 30 J = 30+8= 38 c. Calculate latest completion times for each of the activities listed above A =11-5 = 6 B =30-13 = 17 C =19-12 =7 D = 19-8 = 11 E = 26-7 = 19 F = 30-4= 26 G = 30-4 = 26 H = 30-8 = 30 I = 38 -8 = 30 J = 38 d. Calculate slack times for each of the activities listed above A =6-6 =0 B =38-8 = 30 C =26-7= 19 D = 11-11=0 E = 19-19=0
F = 26-26 =0 G = 26-24 =2 H = 30-23= 7 J = 30-30=0 I = 38-38=0 e. Indicate the activities that is/are in the critical path A – D- E- F- I = J f. Using project management software, draw a Gantt chart for these activities g. Using project management software, draw network diagram for these activities
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help
h. Compare your hand-drawn network diagram with the one generated using project management software A hand-drawn network diagram makes it easier to see what activity must be completed before starting a new activity. It looks more ‘3D’. It looks more ‘busy’ with all the calculations, but it provides a good context of the order of activities. The diagram generated with project management software looks more ‘flat’ and clean. It is a bit harder to identify what activities must be completed first before moving to the next one. This diagram shows critical paths in different colors, and it makes it stand out.