OIE-501 Simulation Balancing Process Capacity

docx

School

Worcester Polytechnic Institute *

*We aren’t endorsed by this school

Course

500

Subject

Industrial Engineering

Date

Feb 20, 2024

Type

docx

Pages

2

Uploaded by SuperMetal13209

Report
Introduction As a car operations manager, I am given a budget of $3 million dollars, and I must decide on how to allocate it. I have to allocate the $3 million between vacuum, machine wash, and hand dry stations, to maximize efficiency and improve profitability. It costs $675 per day to run the car wash, at the beginning of every day the profit is -$675, each car wash yields revenue of $10 with it costing $5 per car. There are two challenges in this simulation: 1] No Variation 2] Variation 1] Challenge 1: No Variation In this type of challenge, the capacity of each station remains constant. To, achieve maximum efficiency and profitability, the capacity of each station should be the same. Let x cars/hr be the capacity of each station. Initially, we know that: Machine Initial Capacity Time required for each car Vacuum and Trash Control 36 cars/hr 1.67 minutes Machine Wash 30 cars/hr 2 minutes Hand dry 24 cars/hr 2.5 minutes The $3 million would be used to increase the capacity of each station to x. Change in capacity for vacuum and trash control = (x-36) cars/hr Change in capacity for Machine Wash = (x-30)/hr Change in capacity for Hand dry = (x-24)/hr In the simulation we are given information about the cost of the station operation for the number of cars. Vacuum Station - $1 million for 1.5 cars/hr Hence, cost for (x-36) cars/hr = (x-36)/1.5 million Machine Wash - $1 million for 15 cars/hr Hence, cost for (x-30) cars/hr = (x-30)/15 million Hand dry - $1 million for 9 cars/hr Hence, cost for (x-24) cars/hr = (x-24)/9 million The total cost for the upgrade is $3 million. (x-36)/1.5 + (x-30)/15 + (x-24)/9 = 3 Solving, for the value of x, we get x=37.5 When x=37.5, (x-36)/1.5 = (37.5-36)/1.5 = 1.5/1.5 = $1 million When x=37.5, (x-30)/15 = (37.5-30)/15 = 7.5/15 = $0.5 million When x=37.5, (x-24)/9 = (37.5-24)/9 = 13.5/9 = $1.5 million Hence, the optimal solution is, Vacuum Station - $1 million, Machine wash = $0.5 million, Hand dry - $1.5 million. Putting the above values in the simulator, we get the profit as $825. Simulation results:
Challenge 2: For Challenge 2, I started with substituting values obtained from Challenge 1. Profit obtained was $655 but the hand dry capacity was not utilized completely. After multiple trials I realized that the capacity of each station varies. Through several trials I saw that the fluctuations lead to longer cycle time than the one in Challenge 1. The variables create differences in process performance and in turn affect the overall profits. Hence, if the processes are longer the profitability will decrease. In Challenge one, I had a profit of $825 a day, $103.13 an hour, and 300 cars serviced, while in challenge 2, the most I was able to achieve was $685, $85.63 an hour, and 272 cars serviced. Below values give us the profit of $685. Vacuum and Trash removal - $1.3 million Machine wash - $0.6 million Hand Dry and Windows - $1.1 million Conclusion In conclusion the key takeaways from this simulation are capacity, washing station allocation and utilization. In both challenges we learned that the more capacity we used the greater profit we gained overall. We also learned that decreasing the allocation of the was station and having it the least funded station in both challenges is what yielded the best results and highest profits. Lastly, we saw that the higher our utilization rate for each station, the higher our capacity could be and overall, we would be able to maximize our profits for the day.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help