Work Breakdown Structure
Student Name:
Institutional Affiliations:
Date of Submission:
2
Project Name: Renovation of an Apartment Kitchen
Project Description
The project is to renovate the kitchen of an apartment unit. The goal is to
create a modern and functional space for the client. The project will begin with
demolishing the existing kitchen, including removing old cabinets, appliances, and
flooring. This will be followed by the design and planning phase, including
consultation with a designer and selection of new materials. Once the materials
have been purchased, the installation process will begin, which will involve
installing new cabinets, countertops, appliances, and flooring (Fager-Pintilä, 2017).
The finishing touches will include painting the walls and ceiling, installing a
backsplash, and completing a final clean-up. The project will end with a final
inspection by the project manager and approval from the client, marking the
completion of the renovation.
Project Scope
The scope of the project is to renovate an existing apartment kitchen. This
will involve updating and improving the kitchen area's functionality, aesthetics,
and design (Keskiniva et al., 2021). The project will include the removal of old
fixtures and materials, installing new features, painting and finishing, and a final
inspection and clean-up. The goal is to transform the kitchen into a modern,
functional space that meets the owner's needs and preferences.
3
The project scope includes the following deliverables:
- A fully functioning and modern kitchen space
- New flooring, cabinetry, countertops, and plumbing and electrical fixtures
- A fresh coat of paint on walls and cabinets
- Clean and organized kitchen area
The project will require coordination with the apartment owner for design
and material selection and obtaining permits and approvals from relevant
authorities (Schneider, 2018). It will also involve hiring contractors and managing
their work to ensure quality and timely completion.
The project scope includes no significant structural changes to the apartment
or renovations outside the kitchen area. It also does not cover the cost of new
appliances (Schneider, 2018). The project team must complete the renovation
within the specified budget and timeline. Any changes or additions to the project
scope will require approval from the apartment owner.
WBS
WBS for Renovation of an Apartment Kitchen:
Level
WBS Component
Description
Identification
Code
1
Renovation of an
Apartment Kitchen
K/RK
2
Planning and
Preparation
Activities
related to
K/RK/PP
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
4
planning and
preparing for
renovation
3
Conducting Site
Survey
Surveying the
kitchen area
K/RK/PP/SS
3
Setting Budget and
Timeline
Creating a
budget and
timeline for the
project
K/RK/PP/BT
3
Obtaining Permits
and Approvals
Obtaining
necessary
permits and
approvals for
renovation
K/RK/PP/PA
2
Demolition and
Removal
Demolishing
and removing
old kitchen
fixtures and
materials
K/RK/DR
3
Removing Existing
Cabinets and
Countertops
Removing old
kitchen cabinets
and countertops
K/RK/DR/CC
3
Removing Flooring
and Wall Tiles
Removing old
flooring and
wall tiles
K/RK/DR/FT
3
Disposing of Debris
Properly
disposing of
demolished
materials
K/RK/DR/DD
2
Installation of New
Kitchen Features
Installing new
kitchen
cabinets,
countertops,
and flooring
K/RK/INF
3
Installing Cabinets
and Countertops
Installing new
kitchen cabinets
and countertops
K/RK/INF/CC
3
Installing Flooring
and Wall Tiles
Installing new
flooring and
K/RK/INF/FT
5
wall tiles
3
Installing Plumbing
and Electrical
Fixtures
Installing new
plumbing and
electrical
fixtures
K/RK/INF/PE
2
Painting and
Finishing
Painting and
finishing the
kitchen space
K/RK/PF
3
Prepping and
Priming Surfaces
Preparing and
priming walls
and cabinets for
paint
K/RK/PF/PP
3
Painting Walls and
Cabinets
Painting walls
and cabinets
with chosen
colors
K/RK/PF/PWC
3
Adding Finishing
Touches
Adding
decorative
elements such
as hardware and
backsplash
K/RK/PF/FT
2
Final Inspection and
Clean-up
Conducting a
final inspection
and cleaning up
the space
K/RK/FIC
3
Checking for
Quality and
Completeness
Ensuring the
project meets
quality
standards and is
complete
K/RK/FIC/QC
3
Cleaning and
Organizing the
Kitchen Space
Cleaning and
organizing area
for the final
reveal
K/RK/FIC/CK
Budget for Renovation of an Apartment Kitchen:
WBS Component
Estimated Cost
6
Planning and Preparation
$2,000
Demolition and Removal
$3,500
Installation of New Kitchen Features
$15,000
Painting and Finishing
$3,000
Final Inspection and Clean-up
$1,500
Total
$25,000
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
7
References
Fager-Pintilä, E. (2017). Improving productivity in pipe renovation projects by
standardized solutions.
Keskiniva, K., Saari, A., & Junnonen, J. M. (2021). Takt production monitoring
and control in apartment renovation projects.
Buildings
,
11
(3), 92.
Schneider, P. S. (2018).
The Impact of Interior-architecture on Social Well-
being
(Doctoral dissertation, Universidade de Lisboa (Portugal)).