1 Work Breakdown Structure Student Name: Institutional Affiliations: Date of Submission:
2 Project Name: Renovation of an Apartment Kitchen Project Description The project is to renovate the kitchen of an apartment unit. The goal is to create a modern and functional space for the client. The project will begin with demolishing the existing kitchen, including removing old cabinets, appliances, and flooring. This will be followed by the design and planning phase, including consultation with a designer and selection of new materials. Once the materials have been purchased, the installation process will begin, which will involve installing new cabinets, countertops, appliances, and flooring (Fager-Pintilä, 2017). The finishing touches will include painting the walls and ceiling, installing a backsplash, and completing a final clean-up. The project will end with a final inspection by the project manager and approval from the client, marking the completion of the renovation. Project Scope The scope of the project is to renovate an existing apartment kitchen. This will involve updating and improving the kitchen area's functionality, aesthetics, and design (Keskiniva et al., 2021). The project will include the removal of old fixtures and materials, installing new features, painting and finishing, and a final inspection and clean-up. The goal is to transform the kitchen into a modern, functional space that meets the owner's needs and preferences.
3 The project scope includes the following deliverables: - A fully functioning and modern kitchen space - New flooring, cabinetry, countertops, and plumbing and electrical fixtures - A fresh coat of paint on walls and cabinets - Clean and organized kitchen area The project will require coordination with the apartment owner for design and material selection and obtaining permits and approvals from relevant authorities (Schneider, 2018). It will also involve hiring contractors and managing their work to ensure quality and timely completion. The project scope includes no significant structural changes to the apartment or renovations outside the kitchen area. It also does not cover the cost of new appliances (Schneider, 2018). The project team must complete the renovation within the specified budget and timeline. Any changes or additions to the project scope will require approval from the apartment owner. WBS WBS for Renovation of an Apartment Kitchen: Level WBS Component Description Identification Code 1 Renovation of an Apartment Kitchen K/RK 2 Planning and Preparation Activities related to K/RK/PP
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help
4 planning and preparing for renovation 3 Conducting Site Survey Surveying the kitchen area K/RK/PP/SS 3 Setting Budget and Timeline Creating a budget and timeline for the project K/RK/PP/BT 3 Obtaining Permits and Approvals Obtaining necessary permits and approvals for renovation K/RK/PP/PA 2 Demolition and Removal Demolishing and removing old kitchen fixtures and materials K/RK/DR 3 Removing Existing Cabinets and Countertops Removing old kitchen cabinets and countertops K/RK/DR/CC 3 Removing Flooring and Wall Tiles Removing old flooring and wall tiles K/RK/DR/FT 3 Disposing of Debris Properly disposing of demolished materials K/RK/DR/DD 2 Installation of New Kitchen Features Installing new kitchen cabinets, countertops, and flooring K/RK/INF 3 Installing Cabinets and Countertops Installing new kitchen cabinets and countertops K/RK/INF/CC 3 Installing Flooring and Wall Tiles Installing new flooring and K/RK/INF/FT
5 wall tiles 3 Installing Plumbing and Electrical Fixtures Installing new plumbing and electrical fixtures K/RK/INF/PE 2 Painting and Finishing Painting and finishing the kitchen space K/RK/PF 3 Prepping and Priming Surfaces Preparing and priming walls and cabinets for paint K/RK/PF/PP 3 Painting Walls and Cabinets Painting walls and cabinets with chosen colors K/RK/PF/PWC 3 Adding Finishing Touches Adding decorative elements such as hardware and backsplash K/RK/PF/FT 2 Final Inspection and Clean-up Conducting a final inspection and cleaning up the space K/RK/FIC 3 Checking for Quality and Completeness Ensuring the project meets quality standards and is complete K/RK/FIC/QC 3 Cleaning and Organizing the Kitchen Space Cleaning and organizing area for the final reveal K/RK/FIC/CK Budget for Renovation of an Apartment Kitchen: WBS Component Estimated Cost
6 Planning and Preparation $2,000 Demolition and Removal $3,500 Installation of New Kitchen Features $15,000 Painting and Finishing $3,000 Final Inspection and Clean-up $1,500 Total $25,000
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help
7 References Fager-Pintilä, E. (2017). Improving productivity in pipe renovation projects by standardized solutions. Keskiniva, K., Saari, A., & Junnonen, J. M. (2021). Takt production monitoring and control in apartment renovation projects. Buildings , 11 (3), 92. Schneider, P. S. (2018). The Impact of Interior-architecture on Social Well- being (Doctoral dissertation, Universidade de Lisboa (Portugal)).