4/27/23, 10:20 PM
Mini PMP - Ch 13 - Project Closure and Benefits Realization : MGMT641102-Global Project Management
https://njit.instructure.com/courses/27956/quizzes/88095?module_item_id=1002795
1/19
Mini PMP - Ch 13 - Project Closure and Benefits
Realization Due
Apr 22 at 11:59pm
Points
45
Questions
45
Available
until Apr 22 at 11:59pm
Time Limit
90 Minutes
This quiz was locked Apr 22 at 11:59pm.
Attempt History
Attempt
Time
Score
LATEST
Attempt 1
89 minutes
37 out of 45
Score for this quiz: 37
out of 45
Submitted Apr 22 at 1:52pm
This attempt took 89 minutes.
1 / 1 pts
Question 1
Following is a list of a few of the more important aspects of the transition
from project to integrated operation that must be considered when the
project functions are distributed. Which one matches the following
description? Are all the functional areas aware of the change? Has each
made sure that the transition from project to standard operation has been
accomplished within standard organizational guidelines?
Purchasing, distribution, legal, and so on Correct!
Correct!
Marketing Information systems/software Risk identification and management
4/27/23, 10:20 PM
Mini PMP - Ch 13 - Project Closure and Benefits Realization : MGMT641102-Global Project Management
https://njit.instructure.com/courses/27956/quizzes/88095?module_item_id=1002795
2/19
1 / 1 pts
Question 2
The primary criterion for project continuance or closure is whether or not
the organization is willing to invest the estimated time and cost required to
complete the project, given the projectÍs current status and current
expected outcome.
True Correct!
Correct!
False 0 / 1 pts
Question 3
Closures that are typically the result of conflict between senior managers,
one of whom may be terminated along with the project, are known as
what?
Political closures orrect Answer
orrect Answer
Closure by addition Conflict closures ou Answered
ou Answered
Closure by integration 1 / 1 pts
Question 4
Listed below are four critical success factors for projects. Which one
matches the following description? Availability of the required technology
and expertise to accomplish the specific technical action steps.
4/27/23, 10:20 PM
Mini PMP - Ch 13 - Project Closure and Benefits Realization : MGMT641102-Global Project Management
https://njit.instructure.com/courses/27956/quizzes/88095?module_item_id=1002795
3/19
Monitoring and feedback Communication Trouble-shooting Technical tasks Correct!
Correct!
1 / 1 pts
Question 5
The special case of closure by extinction wherein the project experiences
a sudden demise even though it was lacking obvious signals that death
was imminent is known as what?
Closure by addition Closure by integration Closure by starvation Termination by murder Correct!
Correct!
1 / 1 pts
Question 6
A special case of closure by extinction is termination by _____.
murder
Correct!
Correct!
orrect Answers
orrect Answers
murder
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
4/27/23, 10:20 PM
Mini PMP - Ch 13 - Project Closure and Benefits Realization : MGMT641102-Global Project Management
https://njit.instructure.com/courses/27956/quizzes/88095?module_item_id=1002795
4/19
1 / 1 pts
Question 7
What section of the final project report is a comparison of what the project
achieved with what the project tried to achieve?
Administrative performance Personnel suggestions Project performance Correct!
Correct!
Organizational structure 1 / 1 pts
Question 8
The primary criterion for this is whether or not the organization is willing to
invest the estimated time and cost required to complete the project, given
the projectÍs current status and current expected outcome.
Continuance Closure Continuance or closure Correct!
Correct!
Extinction 1 / 1 pts
Question 9
This is an administrator responsible for wrapping up the administrative
details of a project.
4/27/23, 10:20 PM
Mini PMP - Ch 13 - Project Closure and Benefits Realization : MGMT641102-Global Project Management
https://njit.instructure.com/courses/27956/quizzes/88095?module_item_id=1002795
5/19
Project manager Closure manager Correct!
Correct!
Stakeholder Program administrator 1 / 1 pts
Question 10
Following is a list of a few of the more important aspects of the transition
from project to integrated operation that must be considered when the
project functions are distributed. Which does the following describe? Are
all drawings complete and on file? Are operating manuals and change
procedures understood?
Engineering Correct!
Correct!
Manufacturing Accounting/finance Personnel 1 / 1 pts
Question 11
The process of closure is all of the following except which one?
Straight-forward Correct!
Correct!
Always complicated Almost always inevitable
4/27/23, 10:20 PM
Mini PMP - Ch 13 - Project Closure and Benefits Realization : MGMT641102-Global Project Management
https://njit.instructure.com/courses/27956/quizzes/88095?module_item_id=1002795
6/19
Never easy 1 / 1 pts
Question 12
When an in-house project is a major success and it is terminated by
institutionalizing it as a formal part of the parent organization; this is
closure by what?
Extinction Starvation Integration Addition Correct!
Correct!
1 / 1 pts
Question 13
Bringing the project into the organization as a separate, ongoing entity is
called what?
Closure by extinction Closure by integration Closure by addition Correct!
Correct!
Closure by starvation 1 / 1 pts
Question 14
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
4/27/23, 10:20 PM
Mini PMP - Ch 13 - Project Closure and Benefits Realization : MGMT641102-Global Project Management
https://njit.instructure.com/courses/27956/quizzes/88095?module_item_id=1002795
7/19
Closure comes to every project.
True Correct!
Correct!
False 0 / 1 pts
Question 15
Special _____ managers are sometimes useful in completing the long and
involved process of shutting down the project.
Temination
ou Answered
ou Answered
orrect Answers
orrect Answers
closure 1 / 1 pts
Question 16
The end of all activity on a project without extending it in some form is
referred to as what?
Integration Extinction Correct!
Correct!
Starvation Addition
4/27/23, 10:20 PM
Mini PMP - Ch 13 - Project Closure and Benefits Realization : MGMT641102-Global Project Management
https://njit.instructure.com/courses/27956/quizzes/88095?module_item_id=1002795
8/19
1 / 1 pts
Question 17
With closure by _____, the project is closed, but the project still exists as
a legal entity complete with sufficient staff to maintain some sort of
presence such as an administrative assistant who issues a project ñno-
progressî report each year.
Starvation
Correct!
Correct!
orrect Answers
orrect Answers
starvation 1 / 1 pts
Question 18
Listed below are four critical success factors for projects. Which one
matches the following description? Communication, consultation, and
active listening to all impacted parties.
Personnel Project schedule/plan Project mission Client consultation Correct!
Correct!
0 / 1 pts
Question 19
Termination by murder usually happens slowly.
True ou Answered
ou Answered
4/27/23, 10:20 PM
Mini PMP - Ch 13 - Project Closure and Benefits Realization : MGMT641102-Global Project Management
https://njit.instructure.com/courses/27956/quizzes/88095?module_item_id=1002795
9/19
False orrect Answer
orrect Answer
1 / 1 pts
Question 20
Closure by extinction always means the project failed.
True False Correct!
Correct!
1 / 1 pts
Question 21
In closure by integration, project assets are what?
Reassigned to another project Liquidated Transferred from the dying project to the newly born division Distributed among the existing elements of the parent organization Correct!
Correct!
1 / 1 pts
Question 22
The fundamental purpose of the final project report is to do what?
Devote more resources to the project Document the errors in the project
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
4/27/23, 10:20 PM
Mini PMP - Ch 13 - Project Closure and Benefits Realization : MGMT641102-Global Project Management
https://njit.instructure.com/courses/27956/quizzes/88095?module_item_id=1002795
10/19
Finish the work so that payment can be collected Improve future projects Correct!
Correct!
1 / 1 pts
Question 23
Agile projects may conclude with a special sprint referred to as the _____
sprint.
release
Correct!
Correct!
orrect Answers
orrect Answers
release 1 / 1 pts
Question 24
Listed below are four critical success factors for projects. Which one
matches the following description? Recruitment, selection, and training of
the necessary personnel for the project team.
Client consultation Project schedule/plan Personnel Correct!
Correct!
Project mission 0 / 1 pts
Question 25
4/27/23, 10:20 PM
Mini PMP - Ch 13 - Project Closure and Benefits Realization : MGMT641102-Global Project Management
https://njit.instructure.com/courses/27956/quizzes/88095?module_item_id=1002795
11/19
Most projects are carried out for other organizations, like a construction
company building a new office building for a client.
True ou Answered
ou Answered
False orrect Answer
orrect Answer
1 / 1 pts
Question 26
In general, the problems of integration are related to the level of
experience that the parent organization has had with the technology being
integrated and to the successful integration of other projects, regardless
of technology, how?
Directly proportional Not proportional Inversely proportional Correct!
Correct!
Unrelated 1 / 1 pts
Question 27
There is no stigma associated with closing a project early in Agile.
True Correct!
Correct!
False
4/27/23, 10:20 PM
Mini PMP - Ch 13 - Project Closure and Benefits Realization : MGMT641102-Global Project Management
https://njit.instructure.com/courses/27956/quizzes/88095?module_item_id=1002795
12/19
1 / 1 pts
Question 28
During the implementation of project closure, if personnel performance
evaluations are required, they should be prepared by who?
Closure manager Project management office Senior manager Project manager or immediate supervisor of the team member Correct!
Correct!
0 / 1 pts
Question 29
A common mistake in project management is to appoint as project
manager an individual with excellent _____ skills but weak _____skills.
Technical , Managerial
ou Answered
ou Answered
orrect Answers
orrect Answers
managerial technical 1 / 1 pts
Question 30
What section of the final project report contains comments regarding how
the organizational structure aided or impeded the progress of the project?
Administrative performance Organizational structure Correct!
Correct!
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
4/27/23, 10:20 PM
Mini PMP - Ch 13 - Project Closure and Benefits Realization : MGMT641102-Global Project Management
https://njit.instructure.com/courses/27956/quizzes/88095?module_item_id=1002795
13/19
Personnel suggestions Project performance 1 / 1 pts
Question 31
Closure by _____ is the most common way of dealing with successful
projects, and the most complex.
Integration
Correct!
Correct!
orrect Answers
orrect Answers
integration 1 / 1 pts
Question 32
Following is a list of a few of the more important aspects of the transition
from project to integrated operation that must be considered when the
project functions are distributed. Which does the following describe? Have
the project accounts been closed and audited? Do the new department
budgets include the additional work needed by the project?
Personnel Manufacturing Accounting/finance Correct!
Correct!
Engineering 1 / 1 pts
Question 33
4/27/23, 10:20 PM
Mini PMP - Ch 13 - Project Closure and Benefits Realization : MGMT641102-Global Project Management
https://njit.instructure.com/courses/27956/quizzes/88095?module_item_id=1002795
14/19
Bringing the project activities into the organization and distributing them
among existing functions is referred to as what?
Closure by addition Termination by murder Closure by extinction Closure by integration Correct!
Correct!
0 / 1 pts
Question 34
For projects organized as weak matrices, most of the individuals on the
project ñbelongî to the project.
True ou Answered
ou Answered
False orrect Answer
orrect Answer
1 / 1 pts
Question 35
Most studies have shown that the factors associated with project success
or failure are what?
Different across different industries but similar for the various types of
projects
Different across different industries and the various types of projects Correct!
Correct!
4/27/23, 10:20 PM
Mini PMP - Ch 13 - Project Closure and Benefits Realization : MGMT641102-Global Project Management
https://njit.instructure.com/courses/27956/quizzes/88095?module_item_id=1002795
15/19
Similar across different industries but different for the various types of
projects
Similar across different industries and the various types of projects 1 / 1 pts
Question 36
Following is a list of a few of the more important aspects of the transition
from project to integrated operation that must be considered when the
project functions are distributed. Which one matches the following
description? Is the sales department aware of the change?
Marketing Correct!
Correct!
Purchasing, distribution, legal, and so on Information systems/software Risk identification and management 1 / 1 pts
Question 37
Following is a list of a few of the more important aspects of the transition
from project to integrated operation that must be considered when the
project functions are distributed. Which one matches the following
description? Have all possible threats to the project been faced, subjected
to analysis, and dealt with accordingly?
Purchasing, distribution, legal, and so on Marketing
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
4/27/23, 10:20 PM
Mini PMP - Ch 13 - Project Closure and Benefits Realization : MGMT641102-Global Project Management
https://njit.instructure.com/courses/27956/quizzes/88095?module_item_id=1002795
16/19
Information systems/software Risk identification and management Correct!
Correct!
1 / 1 pts
Question 38
It is important to select a project manager who has strong what?
Monitoring skills Managerial skills Correct!
Correct!
Technical skills Trouble-shooting skills 0 / 1 pts
Question 39
When project success results in closure by _____, project personnel,
property, and equipment are often simply transferred from the dying
project to the newly born division.
integration
ou Answered
ou Answered
orrect Answers
orrect Answers
addition 1 / 1 pts
Question 40
4/27/23, 10:20 PM
Mini PMP - Ch 13 - Project Closure and Benefits Realization : MGMT641102-Global Project Management
https://njit.instructure.com/courses/27956/quizzes/88095?module_item_id=1002795
17/19
When a decision is made to close a project by extinction, all activity on the
substance of the project ceases. A great deal of _____ activity, however,
remains to be done.
organizational
Correct!
Correct!
orrect Answers
orrect Answers
organizational 0 / 1 pts
Question 41
The techniques of project management section of the final report does
what?
Analyzes the impact of organizational structure on the project Reviews the administrative practices used during the project ou Answered
ou Answered
Offers solutions to technical problems that may have occurred Compares what the project achieved with what it aimed for orrect Answer
orrect Answer
1 / 1 pts
Question 42
Cutting a project's budget sufficiently to stop progress without actually
killing the project is referred to as what?
Closure by starvation Correct!
Correct!
Closure by subtraction Closure by extinction
4/27/23, 10:20 PM
Mini PMP - Ch 13 - Project Closure and Benefits Realization : MGMT641102-Global Project Management
https://njit.instructure.com/courses/27956/quizzes/88095?module_item_id=1002795
18/19
Closure by addition 1 / 1 pts
Question 43
What section of the final project report contains a review of administrative
practices?
Project performance Organizational structure Personnel suggestions Administrative performance Correct!
Correct!
1 / 1 pts
Question 44
Sunk costs are not relevant to current investment decisions.
True Correct!
Correct!
False 1 / 1 pts
Question 45
The project performance section of the final report does what?
Analyzes the impact of organizational structure on the project
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
4/27/23, 10:20 PM
Mini PMP - Ch 13 - Project Closure and Benefits Realization : MGMT641102-Global Project Management
https://njit.instructure.com/courses/27956/quizzes/88095?module_item_id=1002795
19/19
Reviews the administrative practices used during the project Compares what the project achieved with what it aimed for Correct!
Correct!
Offers solutions to technical problems that may have occurred Quiz Score: 37
out of 45
Related Documents
Recommended textbooks for you
Marketing
Marketing
ISBN:9780357033791
Author:Pride, William M
Publisher:South Western Educational Publishing

Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning

Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Recommended textbooks for you
- MarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational PublishingPurchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningPractical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Marketing
Marketing
ISBN:9780357033791
Author:Pride, William M
Publisher:South Western Educational Publishing

Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning

Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,