Textbook Question
Book Icon
Chapter C, Problem 2.4A

The Global Sourcing Wire Harness Decision

Sheila Austin, a buyer at Autolink, a Detroit-based producer of subassemblies for the automotive market, has sent out requests for quotations for a wiring harness to four prospective suppliers. Only two of the four suppliers indicated an interest in quoting the business: Original Wire (Auburn Hills, MI) and Happy Lucky Assemblies (HLA) of Guangdong Province, China. The estimated demand for the harnesses is 5,000 units a month. Both suppliers will incur some costs to retool for this particular harness. The harnesses will be prepackaged in 24 × 12 × 6-inch cartons. Each packaged unit weighs approximately 10 pounds.

Quote 1

The first quote received is from Original Wire. Auburn Hills is about 20 miles from Autolink’s corporate headquarters, so the quote was delivered in person. When Sheila went down to the lobby, she was greeted by the sales agent and an engineering representative. After the quote was handed over, the sales agent noted that engineering would be happy to work closely with Autolink in developing the unit and would also be interested in future business that might involve finding ways to reduce costs. The sales agent also noted that they were hungry for business, as they were losing a lot of customers to companies from China. The quote included unit price, tooling, and packaging. The quoted unit price does not include shipping costs. Original Wire requires no special warehousing of inventory, and daily deliveries from its manufacturing site directly to Autolink’s assembly operations are possible.

Original Wire Quote:

  • Unit price = $30
  • Packing costs = $0.75 per unit
  • Tooling = $6,000 one-time fixed charge
  • Freight cost = $5.20 per hundred pounds

Quote 2

The second quote received is from Happy Lucky Assemblies of Guangdong Province, China. The supplier must pack the harnesses in a container and ship via inland transportation to the port of Shanghai in China, have the shipment transferred to a container ship, ship material to Seattle, and then have material transported inland to Detroit. The quoted unit price does not include international shipping costs, which the buyer will assume.

HLA Quote:

  • Unit price = $19.50
  • Shipping lead time = Eight weeks
  • Tooling = $3,000

In addition to the supplier’s quote, Sheila must consider additional costs and information before preparing a comparison of the Chinese supplier’s quotation:

  • Each monthly shipment requires three 40-foot containers.
  • Packing costs for containerization = $2 per unit.
  • Cost of inland transportation to port of export = $200 per container.
  • Freight forwarder’s fee = $100 per shipment (letter of credit, documentation, etc.).
  • Cost of ocean transport = $4,000 per container. This has risen significantly in recent years due to a shortage of ocean freight capacity.
  • Marine insurance = $0.50 per $100 of shipment.
  • U.S. port handling charges = $1,200 per container. This fee has also risen considerably this year, due to increased security. Ports have also been complaining that the charges may increase in the future.
  • Customs duty = 5% of unit cost.
  • Customs broker fees per shipment = $300.
  • Transportation from Seattle to Detroit = $18.60 per hundred pounds.
  • Need to warehouse at least four weeks of inventory in Detroit at a warehousing cost of $1.00 per cubic foot per month, to compensate for lead time uncertainty.

Sheila must also figure the costs associated with committing corporate capital for holding inventory. She has spoken to some accountants, who typically use a corporate cost of capital rate of 15%.

  • Cost of hedging currency—broker fees = $400 per shipment
  • Additional administrative time due to international shipping = 4 hours per shipment × $25 per hour (estimated)
  • At least two five-day visits per year to travel to China to meet with supplier and provide updates on performance and shipping = $20,000 per year (estimated)

The international sourcing costs must be absorbed by Sheila, as the supplier does not assume any of the additional estimated costs and invoice Sheila later, or build the costs into a revised unit price. Sheila feels that the U.S. supplier is probably less expensive, even though it quoted a higher price. Sheila also knows that this is a standard technology that is unlikely to change during the next three years, but which could be a contract that extends multiple years out. There is also a lot of “hall talk” amongst the engineers on her floor about next-generation automotive electronics, which will completely eliminate the need for wire harnesses, which will be replaced by electronic components that are smaller, lighter, and more reliable. She is unsure about how to calculate the total costs for each option, and she is even more unsure about how to factor these other variables into the decision.

Are there any other issues besides cost that Sheila should evaluate?

Blurred answer
Students have asked these similar questions
The annual demand for water bottles at Mega Stores is 500 units, with an ordering cost of Rs. 200 per order. If the annual inventory holding cost is estimated to be 20%. of unit cost, how frequently should he replenish his stocks? Further, suppose the supplier offers him a discount on bulk ordering as given below. Can the manager reduce his costs by taking advantage of either of these discounts? Recommend the best ordering policy for the store. Order size Unit cost (Rs.) 1 – 49 pcs. 20.00 50 – 149 pcs. 19.50 150 – 299 pcs. 19.00 300 pcs. or more 18.00
Help answer showing level work and formulas
I need to forecast using a 3-Period-Moving-Average-Monthly forecasting model which I did but then I need to   use my forecast numbers to generate a Master Production Schedule (MPS)  I have to Start with actual sales (my own test data numbers) for August-2022 Oct-2022 i need to create MPS to supply demand starting November-2022  April 2023  I just added numbers without applying formulas to the mps on the right side of the spreadsheet because I do not know how to do it. The second image is the example of what it should look like. Thank You.
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY