Textbook Question
Chapter B, Problem 9P
Green Vehicle Inc. manufactures electric cars and small delivery trucks. It has just opened a new factory where the C1 car and the T1 truck can both be manufactured. To make either vehicle, processing in the assembly shop and in the paint shop are required. It takes 1/40 of a day and 1/60 of a day to paint a truck of type T1 and a car of type C1 In the paint shop, respectively. It takes 1/50 of a day to assemble either type of vehicle in the assembly shop.
A T1 truck and a C1 car yield profits of $300 and $220, respectively, per vehicle sold.
- a. Define the objective function and constraint equations.
- b. Graph the feasible region.
- c. What is a maximum-profit daily production plan at the new factory?
- d. How much profit will such a plan yield, assuming whatever is produced is sold?
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
Sawing
20 min/unit
Sanding
20 min/unit
Drilling
32 min/unit
Welding
30 min/unit
Assembly
93 min/unit
Assembly
93 min/unit
Assembly
93 min/unit
A production process is shown in the figure above. The drilling operation occurs
separately from, and simultaneously with the sawing and sanding operations.
Welding starts when both drilling and sanding operations have been completed.
After welding, a product needs to go through only one of the three assembly
operations (the operations are in parallel, where parallel lines perform the exact same
operation). Considering the process times at stations, what is the process time of the
system (in min/unit)?
Suppose a final assembly is produced by assembling two components. THE The first component, A, is produced internally and goes through three process steps, which are stamping, forging and machining, with scrap estimates of 10%, 15% and 25%, respectively. For every three produced units of component A, two are used in the final assembly and one is separate to meet spare parts needs. The second component, B, which is used exclusively in final assembly, is purchased from a supplier external and inspected on arrival; 2% do not pass inspection. A unit of the component purchased is required for each final assembly. The final assembly process produces 5% of scraps. Spare parts demands for component A and final Su assembly match to 1,000 and 5,000 units, respectively. How many input units are needed for produce component A, and how many units of component B should the firm buy?
A production process at Kenneth Day Manufacturing is shown in the figure below. The drilling operation occurs separately from, and simultaneously with, the sawing
and sanding, which are independent sequential operations. A product needs to go through only one of the three assembly operations (the operations are in parallel).
6 units/hr
Sawing
2.5 units/hr
Sanding
Drilling
1.8 units/hr
Welding
7 units/hr
Assembly
0.7 units/hr
Assembly
0.7 units/hr
Assembly
0.7 units/hr
Chapter B Solutions
Operations Management
Ch. B - Prob. 1DQCh. B - Prob. 2DQCh. B - Prob. 3DQCh. B - Prob. 4DQCh. B - Prob. 5DQCh. B - Prob. 6DQCh. B - Prob. 7DQCh. B - Prob. 8DQCh. B - Prob. 9DQCh. B - Prob. 10DQ
Ch. B - Prob. 11DQCh. B - Where a constraint crosses the vertical or...Ch. B - Prob. 13DQCh. B - Prob. 1PCh. B - Prob. 2PCh. B - Prob. 3PCh. B - B.4. Consider the following linear programming...Ch. B - Prob. 5PCh. B - Prob. 6PCh. B - Prob. 7PCh. B - Prob. 8PCh. B - Green Vehicle Inc. manufactures electric cars and...Ch. B - Prob. 10PCh. B - Prob. 11PCh. B - Prob. 12PCh. B - The LP relationships that follow were formulated...Ch. B - Prob. 14PCh. B - Prob. 15PCh. B - Prob. 16PCh. B - Prob. 17PCh. B - Prob. 18PCh. B - Prob. 19PCh. B - Prob. 20PCh. B - Prob. 21PCh. B - Prob. 22PCh. B - Prob. 23PCh. B - How many corner points are there in the feasible...Ch. B - Prob. 25PCh. B - Prob. 26PCh. B - A fertilizer manufacturer has to fulfill supply...Ch. B - Prob. 28PCh. B - Bowman Builders manufactures steel storage sheds...Ch. B - Prob. 30PCh. B - Quain Lawn and Garden, Inc Bill and Jeanne Quain...Ch. B - Quain Lawn and Garden, Inc Bill and Jeanne Quain...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- A production process at Kenneth Day Manufacturing is shown in the figure below. The drilling operation occurs separately from, and simultaneously with, the sawing and sanding, which are independent sequential operations. A product needs to go through only one of the three assembly operations (the operations are in parallel). 7 units/hr 5 units/hr Assembly 0.8 units/hr Sawing Sanding Welding Assembly 2.1 units/hr 0.8 units/hr Drilling 2.5 units/hr Assembly 0.8 units/hr a) is the bottleneck. b) The bottleneck time is minutes per unit (round your response to two decimal places). c) The throughput time of the overall system is minutes (round your response to two decimal places).arrow_forwardIn a sandwich production factory, making each ham and cheese sandwich consists of a number of activities which totally take 7 minutes. The production line for ham and cheese sandwich has five workers who work 12 hours a day. What is the maximum number of ham and cheese sandwiches they canmake in this production line?a) 465 b) 425c) 612 d) 514e) 102arrow_forwardA production process at Brianna Bryant Manufacturing is shown in the figure below. The drilling operation occurs separately from, and simultaneously with, the sawing and sanding, which are independent sequential operations. A product needs to go through only one of the three assembly operations (the operations are in parallel). 6 units/hr 2.5 units/hr Sawing Sanding Q Assembly 0.8 units/hr Welding 5 units/hr Assembly 0.8 units/hr Drilling 2.1 units/hr a) is the bottleneck. b) The bottleneck time is minutes per unit (round your response to two decimal places). c) The throughput time of the overall system is minutes (round your response to two decimal places). Assembly 0.8 units/hr d) If the firm operates 11 hours per day, 20 days per month, the monthly capacity of the manufacturing process is units (enter your response as a whole number).arrow_forward
- These four steps make up what is called a machine cycle but is more often known as a process loop. When it comes to machine cycles, what factors do most people prioritise? Should I be concerned that I may have to replace machine cycle parts when they wear out? Is it feasible that doubling the number of modules available would make toggling between them easier?arrow_forwardThese four elements make up a machine cycle, often known as a process loop. Which parts of machine cycles do people value the most? Do you have to worry about the various parts of a machine cycle needing replacement? Is there a way to solve the problem of switching between modules by adding another one?arrow_forwardA Company produces a component for use in the aerospace industry. The component consists of three parts (A, B and C), which are purchased externally and cost 50c, 60c and 70c per piece respectively. Parts A and B are assembled first on assembly line 1, which produces 150 components per hour. Part C undergoes a drilling operation before being finally assembled with the output from assembly line 1. There are six drilling machines in total, but only three are currently operational. Each drilling machine drills part C at a rate of 30 parts per hour. The final assembly line has a production capacity of 100 components per hour. At present, components are produced eight hours a day, five days a week. If the need arises, management can add a second shift of eight hours for the assembly lines only. The cost of assembly labour is 40c per assembly operation for each assembly line; the cost of drilling labour is 20c per part. For drilling, the cost of electricity is 10c per part. The overhead cost…arrow_forward
- A manufacturing process has a fixed cost of $150,000 per month. Each unit of product being produced contains $25 worth of material and takes $45 of labor. How many units are needed to break even if each completed unit has a value of $90? (Answer in Appendix D)arrow_forwardLead Time Gourmet Helper Appliance Company manufactures home kitchen appliances. The manufacturing process includes stamping, final assembly, testing and shipping. In the stamping operation, a number of individuals are responsible for stamping the steel outer surface of the appliance. The stamping operation is set up prior to each run. A run of 75 stamping is completed after each setup. A setup requires 40 minutes the parts wait for the setup to be completed before stamping begins. Each stamping requires 5 minutes of operating time. After each batch is completed, the operator moves stamp the stamped covers to the final assembly area. This move takes 10 minutes to complete. The final assembly for each appliance unit requires 18 minutes and is also done in batches of 75 appliance units. The batch of 75 appliance units is moved into the test building, which is crossed street. The move takes 25 minutes. In the final test, the 75 unit batch is tested one at a time. Each test…arrow_forwardThose four elements make up what is sometimes known as a machine cycle but is more often referred to as a process loop. To what extent do the most important features of machine cycles include? Do you have to worry about the various parts of a machine cycle needing replacement? Is there a way to solve the problem of switching modules by adding another one?arrow_forward
- Please ignore the answers and help me solve this questionarrow_forwardThe Goodparts Company produces a component that is subsequently used in the aerospace industry. The component consists of three parts (A, B, and C) that are purchased from outside and cost 35, 30, and 10 cents per piece, respectively. Parts A and B are assembled first on assembly line 1, which produces 185 components per hour. Part C undergoes a drilling operation before being finally assembled with the output from assembly line 1. There are, in total, six drilling machines, but at present only three of them are operational. Each drilling machine drills part C at a rate of 80 parts per hour. In the final assembly, the output from assembly line 1 is assembled with the drilled part C. The final assembly line produces at a rate of 205 components per hour. At present, components are produced eight hours a day and five days a week. Management believes that if the need arises, it can add a second shift of eight hours for the assembly lines. The cost of assembly labor is 30 cents per part for…arrow_forwardSolvo produces three types of trucks on one assembly line: the long-haul (L), the short-haul (S), and the vocational truck (V). Next month the company has orders for 1,100 long-haul trucks, 1650 short-haul trucks, and 550 vocational trucks. Chris Riggs, the production manager for Solvo, wants to try uniform production and mixed-model sequencing. Assuming 30 working days per month, what assembly sequence would you recommend, and how many times per day should the sequence be repeated. (Round answer to 0 decimal places) Assembly sequence? (pick one) a.vocational,vocational, vocational, long-haul, long-haul, short-haul b.short-haul, long-haul, short-haul, vocational, short-haul, long-haul c.short-haul, short-haul, long-haul, long-haul, vocational, vocational How many times should sequence be repeated?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY