Question
Book Icon
Chapter 9, Problem 23P

a)

Summary Introduction

To determine: The theoretical minimum number of workstations.

a)

Expert Solution
Check Mark

Answer to Problem 23P

The theoretical minimum number of workstations is 5 workstations.

Explanation of Solution

Given information:

Task Time (seconds) Immediate predecessors
A 40 -
B 30 A
C 50 A
D 40 B
E 6 B
F 25 C
G 15 C
H 20 D, E
I 18 F, G
J 30 H, I
Total 274  
  • Output is 60 iStars / hour

Calculation of cycle time:

The requirement is to produce 60 iStars / hour. Hence, the cycle time for one iStar will be:

Cycle time=60 iStars / hour60minutes / hour×60 seconds=1×60 seconds=60 seconds / iStar

Formula to calculate theoretical minimum number of workstations:

Workstations=Total task timeCycle time

Calculation of theoretical minimum number of workstations:

Workstations=27460=4.57=5 workstations

The theoretical minimum number of workstations is 5 workstations.

b)

Summary Introduction

To balance: The assembly line.

b)

Expert Solution
Check Mark

Explanation of Solution

Precedence diagram:

EBK PRINCIPLES OF OPERATIONS MANAGEMENT, Chapter 9, Problem 23P

List of most following tasks:

Tasks Following tasks
A 9
B 4
C 4
D 2
E 2
F 2
G 2
H 1
I 1
J 0

Assignment of different tasks to different workstations:

Workstation Elligible tasks Selected tasks Task time (seconds) Available cycle time (seconds) Remarks
1 60
A A 40 20
B,C 20 (Idle time) Cycle time is less than task time
2 60
B, C C 7 50 Tie broken randomnly
B, F, G 10 (Idle time) Cycle time is less than task time
3 60
B, F, G B 30 30 Task B has most following tasks.
D, E, F, G F 25 24 Tie broken randomnly
D, E, G 1 (Idle time) Cycle time is less than task time
4 60
D, E, G D 40 20 Tie broken randomnly
E, G G 15 5 Tie broken randomnly
E,I 5 (Idle time) Cycle time is less than task time
5 60
E, I E 6 54 Task E has most following tasks.
I, H H 20 34 Tie broken randomnly
I I 18 2 Task I is only elligible task
2 (Idle time)
6 60
J J 30 30 Task J is the remaining task
30 (Idle time)
Workstation Task assigned Idle time
1 A 20
2 C 10
3 B, F 1
4 D, G 5
5 E, H, I 2
6 J 30
Total 68

c)

Summary Introduction

To determine: The actual number of workstations.

c)

Expert Solution
Check Mark

Answer to Problem 23P

The actual number of workstations is 6.

Explanation of Solution

Workstation Task assigned Idle time
1 A 20
2 C 10
3 B, F 1
4 D, G 5
5 E, H, I 2
6 J 30
Total 68

The actual number of workstations is 6.

d)

Summary Introduction

To determine: The efficiency.

Introduction:

Efficiency:

Efficiency is the measure of  what is actually produced as opposed to what can be theoretically produced with the same amount of resources.

d)

Expert Solution
Check Mark

Answer to Problem 23P

The efficiency is 76.11%.

Explanation of Solution

Formula to calculate efficiency:

Efficiency=Total task timeNumber of workstations×Cycle time×100

Calculation of efficiency:

Efficiency=2746×60×100=274,00360=76.11%

The efficiency is 76.11%.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
CASE STUDY 9-1 Was Robert Eaton a Good Performance Management Leader? R obert Eaton was CEO and chairman of Chrys- ler from 1993 to 1998, replacing Lee Iacocca, who retired after serving in this capacity since 1978. Eaton then served as cochairman of the newly merged DaimlerChrysler organization from 1998 to 2000. In fact, Eaton was responsible for the sale of Chrysler Corporation to Daimler-Benz, thereby creating DaimlerChrysler. With 362,100 employees, DaimlerChrysler had achieved revenues of €136.4 billion in 2003. DaimlerChrysler's passenger car brands included Maybach, Mercedes-Benz, Chrysler, Jeep, Dodge, and Smart. Commercial vehicle brands included Mercedes-Benz, Freightliner, Sterling, Western Star, and Setra. From the beginning of his tenure as CEO, Eaton communicated with the people under him. He immediately shared his plans for the future with his top four executives, and upon the advice of his colleague, Bob Lutz, decided to look around the company before making any hasty…
Critically assess Martin’s coaching style.
Compare Robert Eaton’s performance management leadership presented in the case against the performance management leadership principles, functions, and behaviors.  What recommendations can be made about what he might do more effectively?  Explain and defend your answer.
Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.