a)
To determine: The theoretical minimum number of workstations.
a)
Answer to Problem 23P
The theoretical minimum number of workstations is 5 workstations.
Explanation of Solution
Given information:
Task | Time (seconds) | Immediate predecessors |
A | 40 | - |
B | 30 | A |
C | 50 | A |
D | 40 | B |
E | 6 | B |
F | 25 | C |
G | 15 | C |
H | 20 | D, E |
I | 18 | F, G |
J | 30 | H, I |
Total | 274 |
- Output is 60 iStars / hour
Calculation of cycle time:
The requirement is to produce 60 iStars / hour. Hence, the cycle time for one iStar will be:
Formula to calculate theoretical minimum number of workstations:
Calculation of theoretical minimum number of workstations:
The theoretical minimum number of workstations is 5 workstations.
b)
To balance: The assembly line.
b)
Explanation of Solution
Precedence diagram:
List of most following tasks:
Tasks | Following tasks |
A | 9 |
B | 4 |
C | 4 |
D | 2 |
E | 2 |
F | 2 |
G | 2 |
H | 1 |
I | 1 |
J | 0 |
Assignment of different tasks to different workstations:
Workstation | Elligible tasks | Selected tasks | Task time (seconds) | Available cycle time (seconds) | Remarks |
1 | 60 | ||||
A | A | 40 | 20 | ||
B,C | 20 (Idle time) | Cycle time is less than task time | |||
2 | 60 | ||||
B, C | C | 7 | 50 | Tie broken randomnly | |
B, F, G | 10 (Idle time) | Cycle time is less than task time | |||
3 | 60 | ||||
B, F, G | B | 30 | 30 | Task B has most following tasks. | |
D, E, F, G | F | 25 | 24 | Tie broken randomnly | |
D, E, G | 1 (Idle time) | Cycle time is less than task time | |||
4 | 60 | ||||
D, E, G | D | 40 | 20 | Tie broken randomnly | |
E, G | G | 15 | 5 | Tie broken randomnly | |
E,I | 5 (Idle time) | Cycle time is less than task time | |||
5 | 60 | ||||
E, I | E | 6 | 54 | Task E has most following tasks. | |
I, H | H | 20 | 34 | Tie broken randomnly | |
I | I | 18 | 2 | Task I is only elligible task | |
2 (Idle time) | |||||
6 | 60 | ||||
J | J | 30 | 30 | Task J is the remaining task | |
30 (Idle time) |
Workstation | Task assigned | Idle time |
1 | A | 20 |
2 | C | 10 |
3 | B, F | 1 |
4 | D, G | 5 |
5 | E, H, I | 2 |
6 | J | 30 |
Total | 68 |
c)
To determine: The actual number of workstations.
c)
Answer to Problem 23P
The actual number of workstations is 6.
Explanation of Solution
Workstation | Task assigned | Idle time |
1 | A | 20 |
2 | C | 10 |
3 | B, F | 1 |
4 | D, G | 5 |
5 | E, H, I | 2 |
6 | J | 30 |
Total | 68 |
The actual number of workstations is 6.
d)
To determine: The efficiency.
Introduction:
Efficiency:
Efficiency is the measure of what is actually produced as opposed to what can be theoretically produced with the same amount of resources.
d)
Answer to Problem 23P
The efficiency is 76.11%.
Explanation of Solution
Formula to calculate efficiency:
Calculation of efficiency:
The efficiency is 76.11%.
Want to see more full solutions like this?
Chapter 9 Solutions
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
- Gibson Appliances wants to establish an assembly line to manufacture its new product, the Micro Popcorn Popper. The goal is to produce five poppers per hour. The tasks, task times, immediate predecessors, and precedence diagram for producing one Micro Popcorn Popper are as follows Task A B C D E F Time (min) 10 12 8 10 7 5 Immediate Predecessors A AB B,C С D.E a) The theoretical minimum number of workstations (Round your response up to the next whole number)arrow_forwardThe desired daily output for an assembly line is 480 units. This assembly line will operate 760 minutes per day. The following table contains information on this product's task times and precedence relationships: TASK А ABCDEFGH 58 48 28 25 38 78 58 18 TASK TIME (SECONDS) Work Station I II III 50 IV 40 20 Efficiency 30 50 10 b. What is the workstation cycle time? Workstation cycle time 95 seconds per unit IMMEDIATE PREDECESSOR c. Balance this line using the largest number of following tasks. Use the longest task time as a secondary criterion. (Leave no cells blank - be certain to enter "0" wherever required.) Task IAAUI A-C-D E-G B-D F А А 77.6 % B с D-F E-G Idle Time d. What is the efficiency of your line balance? (Round your answer to 1 decimal place.) 5 5 55 20arrow_forwardStanford Rosenberg Computing wants to establish anassembly line for producing a new product, the Personal DigitalAssistant (PDA). The tasks, task times, and immediate predecessorsfor the tasks are as follows: Rosenberg's goal is to produce 180 PDAs per hour.a) What is the cycle time?b) What is the theoretical minimum for the number of workstations that Rosenberg can achieve in this assembly line?c) Can the theoretical minimum actually be reached when workstations are assigned?arrow_forward
- Smart Manufacturing's production engineers are reviewing the layout of their assembly line for their leading product. The line will operate eight hours a day with a desired output of 240 units per day. The following table contains information about this product's task times and precedence relationships: TASK Task Time (seconds) Immediate Precedent A 60 -- B 80 A C 20 A D 50 A E 90 B,C F 30 C,D G 30 E, F H 60 G Determine: a) Network of activities (precedence diagram) b) Cycle time c) The required number of workstations d) Evaluate the solution by the appropriate line balance heuristicarrow_forwardA company needs to rebalance a product layout for producing new plastic license plates. They plan to use the assembly line six hours in order to meet projected demand of 2,160 license plates each day. The following table describes the tasks involved in the production of this product: Without regard to projected demand, what is the maximum possible cycle time for this assembly line? Task Time (secs) Immediate Predecessor a 3 none b 4 none c 5 a,b d 7 none e 9 c,darrow_forwardDefine layout planning and explain its importance.arrow_forward
- An assembly line is to operate eight hours per day with a desired output of 240 units perday. The following table contains information on this product’s task times and precedencerelationships: Task Task Time (Seconds) Immediate Predecessor A 60 — B 80 A C 20 A D 50 A E 90…arrow_forwardThe desired daily output for an assembly line is 240 units. This assembly line will operate 8 hours per day. The following table contains information on the product's task times and precedence relationships: Task 1 2 345678 Time (s) 60 80 20 50 90 30 30 60 a. Draw the precedence diagram. b. What is the workstation cycle time? c. Balance this line using the longest task time. d. What is the efficiency of your balanced line? Predecessor 1 1 1 2,3 3,4 5,6 7arrow_forwardAssembly Line Problem A shop works a 400-minute day. The manager of the shop wants an output of 200 units per day for the assembly line that has the elemental tasks shown in the following table. Task Immediate Predecessor Task(s) Task Time (minutes) a --- 0.5 b a 1.4 c a 1.2 d a 0.7 e b,c 0.5 f d g e 0.4 h g 0.3 i F 0.5 j e, I 0.8 k h, j 0.9 l k 0.3 d)Compute the efficiency of the assembly linearrow_forward
- The desired daily ouput for an assembly line is 420 units. This assembly line will operate 595 minutes per day. The following table contains information on the products task times and precedence relationships Task. Task time-seconds Immediate predecessor A. 35 - B. 40 A C 30 A D 40 B E 20 C F 70 C G 45 E-F H 30 D-G The required workstation cycle time to meet the desired output time is 85 seconds Balance this line using the largest number of following tasks. Use the longest task time as a secondary criterion The answer gives only 4 workstations as option Have to fill out following Workstation. Task Idle time 1 ?? ?? 2 ?? ?? 3…arrow_forwardWhat is DESIGNING PROCESS LAYOUTS?arrow_forwardP.nilesharrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.