The Action Toy Company has decided to manufacture a new train set the production of which is broken into six steps. The demand for the train is 4,800 units per 40-hour workweek:

Chapter 9, Problem 15P, The Action Toy Company has decided to manufacture a new train set the production of which is broken

a) Draw a precedence diagram of this operation.

b) Given the demand, what is the cycle time for this operation?

c) What is the theoretical minimum number of workstations?

d) Assign tasks to workstations.

e) How much total idle time a present each cycle?

f) What is the efficiency of the assembly line with five stations? With six stations?

a)

Expert Solution
Check Mark
Summary Introduction

To draw: The precedence diagram.

Answer to Problem 15P

EBK PRINCIPLES OF OPERATIONS MANAGEMENT, Chapter 9, Problem 15P , additional homework tip  1

Explanation of Solution

Given information:

Task Time (seconds) Immediate predecessors
A 20 -
B 30 A
C 15 A
D 15 A
E 10 B, C
F 30 D, E
Total 120  
  • Weekly demand is 4,800 units / 40 hours workweek.

Precedence diagram:

EBK PRINCIPLES OF OPERATIONS MANAGEMENT, Chapter 9, Problem 15P , additional homework tip  2

b)

Expert Solution
Check Mark
Summary Introduction

To determine: The cycle time.

Introduction:

Cycle time:

Cycle time is the total time taken to complete an unit of work from the beginning of the process to the end of the process.

Answer to Problem 15P

The  cycle time is 30 seconds / unit.

Explanation of Solution

Given information:

Task Time (seconds) Immediate predecessors
A 20 -
B 30 A
C 15 A
D 15 A
E 10 B, C
F 30 D, E
Total 120  
  • Weekly demand is 4,800 units / 40 hours workweek.

Formula to calculate cycle time:

Cycle time=Output / day×60 minutes / hour×60 seconds / minutes

Calculation of cycle time:

Cycle time=404,800×60×60=2408=30seconds / unit

The  cycle time is 30 seconds / unit.

c)

Expert Solution
Check Mark
Summary Introduction

To determine: The theoretical minimum number of workstations.

Answer to Problem 15P

The theoretical minimum number of workstations is 4 workstations.

Explanation of Solution

Given information:

Task Time (seconds) Immediate predecessors
A 20 -
B 30 A
C 15 A
D 15 A
E 10 B, C
F 30 D, E
Total 120  
  • Weekly demand is 4,800 units / 40 hours workweek.
  • Average daily demand is 50 chairs.

Formula to calculate theoretical minimum number of workstations:

Workstations=Total task timeCycle time

Calculation of theoretical minimum number of workstations:

Workstations=12030=4 workstations

The theoretical minimum number of workstations is 4 workstations.

d)

Expert Solution
Check Mark
Summary Introduction

To assign: The different tasks to different workstations.

Explanation of Solution

Assignment of different tasks to different workstations:

Workstation Elligible tasks Selected tasks Task time (seconds) Available cycle time (seconds) Remarks
1 30
A A 20 10 Task A is the only elligible ask
10 (Idle Time) No other elligible task is available
2 30
B, C, D B 30 0 Task B has the highest task time
3 30
C, D C 15 15 Task C is assigned
D D 15 0 Task D is assigned
4 30
E E 10 20 Task E is the only elligible task available
20 (Idle time) The available cycle time is less than the task time
5 F F 30 0 Task F is assigned
Workstation Task assigned Idle time
1 A 10
2 B 0
3 C, D 0
4 E 20
5 F 0
Total 30

e)

Expert Solution
Check Mark
Summary Introduction

To determine: The idle time per cycle.

Answer to Problem 15P

The  idle time is 30 seconds / cycle.

Explanation of Solution

Given information:

Task Time (seconds) Immediate predecessors
A 20 -
B 30 A
C 15 A
D 15 A
E 10 B, C
F 30 D, E
Total 120  
  • Weekly demand is 4,800 units / 40 hours workweek.
  • Average daily demand is 50 chairs.

Calculation of idle time per cycle:

Idle time=10+20=30seconds / cycle

The  idle time is 30 seconds / cycle.

f)

Expert Solution
Check Mark
Summary Introduction

To determine: The efficiency.

Introduction:

Efficiency:

Efficiency is the measure of  what is actually produced as opposed to what can be theoretically produced with the same amount of resources.

Answer to Problem 15P

The efficiency with five and six workstations is 80% and 66.6% respectively.

Explanation of Solution

Given information:

Task Time (seconds) Immediate predecessors
A 20 -
B 30 A
C 15 A
D 15 A
E 10 B, C
F 30 D, E
Total 120  
  • Weekly demand is 4,800 units / 40 hours workweek.
  • Average daily demand is 50 chairs.

Formula to calculate efficiency:

Efficiency=Total task timeNumber of workstations×Cycle time×100

Calculation of efficiency for five workstations:

Efficiency=1205×30×100=12,000150×100=80%

Calculation of efficiency for six workstations:

Efficiency=1206×30×100=12,000180×100=66.6%

The efficiency with five and six workstations is 80% and 66.6% respectively.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
CASE STUDY 9-1 Was Robert Eaton a Good Performance Management Leader? R obert Eaton was CEO and chairman of Chrys- ler from 1993 to 1998, replacing Lee Iacocca, who retired after serving in this capacity since 1978. Eaton then served as cochairman of the newly merged DaimlerChrysler organization from 1998 to 2000. In fact, Eaton was responsible for the sale of Chrysler Corporation to Daimler-Benz, thereby creating DaimlerChrysler. With 362,100 employees, DaimlerChrysler had achieved revenues of €136.4 billion in 2003. DaimlerChrysler's passenger car brands included Maybach, Mercedes-Benz, Chrysler, Jeep, Dodge, and Smart. Commercial vehicle brands included Mercedes-Benz, Freightliner, Sterling, Western Star, and Setra. From the beginning of his tenure as CEO, Eaton communicated with the people under him. He immediately shared his plans for the future with his top four executives, and upon the advice of his colleague, Bob Lutz, decided to look around the company before making any hasty…
Critically assess Martin’s coaching style.
Compare Robert Eaton’s performance management leadership presented in the case against the performance management leadership principles, functions, and behaviors.  What recommendations can be made about what he might do more effectively?  Explain and defend your answer.
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY