Question
Chapter 8, Problem 8.20BE
To determine
To prepare: The
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Santiago builders began construction work in 2021 for a project with contract price of P24,000,000. Santiago Builders uses percentage of completion. The financial statements for 2021 relating to the contract show the following:
Accounts receivable. P 1,500,000
Construction in progress. 4,800,000
Contract billings to date. 4,500,000
Realized gross profit in 2021. 600,000
1.Compute the total cost incurred to date
A.4,200,000. C. 5,400,000
B.4,800,000. D. 5,100,000
2.Compute the cash collection during 2021
A.3,000,000. C. 2,100,000
B.4,200,000. D. 3,900,000
GinebraCorporation recognizes construction revenue and cost using the percentage of completion method. During 2021, a single long-term project was begun which continued through 2021. Information on the project follows:
2021. 2022
Partial billing on contract 1,000,000. 4,200,000
Accounts receivable 1,000,000 3,000,000
Construction cost 1,050,000 1,920,000
Construction in progress 1,220,000 3,640,000
What is the gross profit recognized from this long-term construction contract in year 2021 and 2022, respectively?
2021 2022
A.220,000. 2,280,000
B.170,000. 500,000
C.220,000. 1,000,000
D.170,000. 1,280,000
BnD Construction Co. successfully tendered for a 3-year contract to erect some warehouse
facilities in Gros Islet. The following information has been provided.
Time left 2:20:2
Contract price - $25 000 000
2021
$ 4 000 000
Cast during year
Estimated cost to complete
Progress billings to date
Cash collected to date
Cast to date
Estimated cost to complete
Total estimated cost
Percentage complete (Round
to nearest whole number)
Total contract price
Total estimated cast
i Complete the following Workings Schedule. Do not enter negative values in the
schedule.
Estimated gross profit or loss
Revenue to recognize to date
Less Revenue previously
recognized
Revenue to recognize in year
Estimated gross profitto
recognize to date
16 000 000
4 500 000
4 200 000
Less Gross profit or lass
previously recognized
2022
2021
$8 000 000
8
050 000
11 500 000
11 000 000
2023
2022
$8 100 000
0
25 000 000
25 000 000
2023
%
Chapter 8 Solutions
Intermediate Accounting (2nd Edition)
Ch. 8 - What are the primary issues involved in revenue...Ch. 8 - What is the fundamental principle underlying the...Ch. 8 - What is the fundamental principle underlying the...Ch. 8 - Prob. 8.4QCh. 8 - Prob. 8.5QCh. 8 - How is a performance obligation defined?Ch. 8 - What are the two criteria to define a good or...Ch. 8 - Prob. 8.8QCh. 8 - What principles regarding timing and measurement...Ch. 8 - Prob. 8.10Q
Ch. 8 - What is variable consideration and what factors...Ch. 8 - Describe and contrast the two approaches used to...Ch. 8 - Prob. 8.13QCh. 8 - What factors should accountants consider to...Ch. 8 - Prob. 8.15QCh. 8 - How does a seller account for any consideration...Ch. 8 - Prob. 8.17QCh. 8 - What are the two exceptions to the general rule...Ch. 8 - What are the three criteria required to recognize...Ch. 8 - When an entity does not meet the three criteria...Ch. 8 - Prob. 8.21QCh. 8 - Prob. 8.22QCh. 8 - How does a firm estimate the degree completed...Ch. 8 - Can a firm record inventory out on consignment as...Ch. 8 - What method do agents in a transaction use to...Ch. 8 - Prob. 8.26QCh. 8 - What qualitative disclosures do the standards...Ch. 8 - All of the following are elements of a contract...Ch. 8 - Prob. 8.2MCCh. 8 - Telecom Co. enters into a two-year contract with a...Ch. 8 - The transaction price must reflect the time value...Ch. 8 - Prob. 8.5MCCh. 8 - When allocating the transaction price to separate...Ch. 8 - Which of the following indicators is not...Ch. 8 - During Yoar 1 Moriwothor Construction Company...Ch. 8 - All of the following are indicators that the...Ch. 8 - Prob. 8.10MCCh. 8 - Prob. 8.11MCCh. 8 - Identify a Contract with a Customer. Complete the...Ch. 8 - Prob. 8.2BECh. 8 - Identifying Performance Obligations. Perfect Party...Ch. 8 - Identifying Performance Obligations. Perfect Party...Ch. 8 - Estimating Variable Consideration. Gear Garage...Ch. 8 - Estimating Variable Consideration. Using the...Ch. 8 - Estimating Variable Consideration. Sellet...Ch. 8 - Estimating Variable Consideration. Seliet...Ch. 8 - Prob. 8.9BECh. 8 - Allocation of Transaction Price. Martin Software...Ch. 8 - Prob. 8.11BECh. 8 - Allocation of Transaction Price. Sycamore Sidewalk...Ch. 8 - Allocation of Transaction Price. Sycamore enters...Ch. 8 - Prob. 8.14BECh. 8 - Allocation of Transaction Price. Using the...Ch. 8 - When to Recognize Revenue. For each scenario...Ch. 8 - Prob. 8.17BECh. 8 - Prob. 8.18BECh. 8 - Percentage-of-Completion Method, Journal Entries....Ch. 8 - Prob. 8.20BECh. 8 - Sales with the Right of Return. Both incorporated...Ch. 8 - Sales with the Right of Return. Using the...Ch. 8 - Sales Returns. Historically, about 5% or the...Ch. 8 - Sales on Consignment. Hanna Lighting recertify...Ch. 8 - Determining Performance Obligations. Pagit Inc, a...Ch. 8 - Prob. 8.2ECh. 8 - Estimating Variable Consideration. King Rat Pest...Ch. 8 - Prob. 8.4ECh. 8 - Prob. 8.5ECh. 8 - Prob. 8.6ECh. 8 - Allocation of Variable Consideration. Green-Up Inc...Ch. 8 - Allocation of Variable Consideration. Green-Up Inc...Ch. 8 - Prob. 8.9ECh. 8 - Prob. 8.10ECh. 8 - Determination of When to Recognize Revenue. Far...Ch. 8 - Prob. 8.12ECh. 8 - Percentage-of-Completion Method. Gary Construction...Ch. 8 - Prob. 8.14ECh. 8 - Prob. 8.15ECh. 8 - Prob. 8.16ECh. 8 - Sales with the Right of Return. Webster Hall, Inc....Ch. 8 - Prob. 8.18ECh. 8 - Prob. 8.19ECh. 8 - Other Principal Agent Transactions, Net Revenue...Ch. 8 - Prob. 8.1PCh. 8 - Prob. 8.2PCh. 8 - Comprehensive Revenue Recognition Problem. Casale...Ch. 8 - Prob. 8.4PCh. 8 - Determining When to Recognize Revenue. Megrew...Ch. 8 - Prob. 8.6PCh. 8 - Prob. 8.7PCh. 8 - Prob. 8.8PCh. 8 - Percentage-of-Completion Method. R Wayne Computer...Ch. 8 - Prob. 8.10PCh. 8 - Prob. 8.11PCh. 8 - Sales on Consignment. Pablo Products. Ltd sells...Ch. 8 - Prob. 1JCCh. 8 - Prob. 1FSCCh. 8 - Prob. 1SSCCh. 8 - Basis for Conclusions Case 1: Control According to...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- SMDC Construction signed a contract to build a building over a period 3 years for a price of P10,000,000. Information relating to the performance of the contract is summarized as follows: 2017 2018 2019 contribution costs incurred during the year 2,500,000 2,400,000 1,800,000 estimated costs to complete 4,500,000 1,800,000 - buildings during the year 2,200,000 2,800,000 5,000,000 collections during the year 2,000,000 2,500,000 5,500,000 Prepare the entries under the percentage of completion.arrow_forwardOn January 1, 2021. Robredo Co. started the construction of a building with a fixed contract price of P10,000,000. The outcome of the construction project can be estimated reliably and the contractor decided to employ cost to cost method. The following data are provided by the accountant and project manager concerning the construction costs for the three years of construction: Year 12/31/2021 12/31/2022 12/31/2023 P 3740000 Costs incurred during the year Realized gross profit/(loss) during the year Percentage of completion as of the end of the year ? ? P750,000 (P250,000) (P800,000) 50% 37.5% ? What is the balance of Construction in Progress on December 31, 2023?arrow_forwardRecording Long-Term Construction: Recognize Revenue at a Point in Time and Over Time Watson Construction Company contracted to build a plant for $500,000. Construction started in January 2020 and was completed in November 2021. Watson uses the cost-to-cost method to measure the completion of its performance obligations. Data relating to the contract follow. 2020 2021 Costs incurred during year $290,000 $120,000 Estimated additional costs to complete 125,000 0 Billings during year 270,000 230,000 Cash collections during year 250,000 250,000 Revenue Recognized at a Point in Time Revenue Recognized Over Time a. Provide the 2020 and 2021 journal entries for Watson assuming revenue is recognized at a point in time. Provide entries for (1) construction costs incurred, (2) progress billings, (3) cash collections, and (4) revenues and expenses. Note: If a journal entry isn't required for the transaction, select "N/A" as the account names and leave the Dr. and Cr.…arrow_forward
- Provide proper solutionarrow_forwardThe total estimated cost isarrow_forwardAt the beginning of 2021, Batangas Road Construction entered into a contract to build a road for the government. Construction will take four years. The following information as of December 31, 2021 is available for the contract: Total revenue according to contract 10,000,000 Total expected cost 8,000,000 Cost incurred during 2021 1,200,000 Assume that the company estimated percentage complete based on costs incurred as a percentage of total estimated costs. Under the completed contract method, how much revenue will be reported in 2021? None 300,000 1,500,000arrow_forward
- Required: Calculate the following: a. estimated total cost of completion, b. estimated profit on completion, c. estimated profit to date. Lim Construction is building Univ tower Near Unicity, Sibu. The date of commencement of construction is 1 January 2021 and the date of completion is on 31 December 2026. During the year ending 31 December 2021, the following information reported: RM Contract price Plant sent to site Purchasing of materials Wages paid Direct expenses Overhead incurred 13,000,000.00 2,000,000.00 3,000,000.00 1,500,000.00 1,000,000.00 500,000.00 At the end of December 2021, the following available: 1. Material unused on site amounted RM1,000,000.00 2. Wages owing RM500,000.00 3. Value of work certified RM6,000,000.00 4. Cost of work done but not yet certified amounted to RM500,000.00 5. Plant at site RM1,500,000.00arrow_forwardInformation on Red Hot Co.’s construction contracts with customers which commenced during 20x1 is shown below: Contract 1 Contract price 420,000; Costs incurred during the year 240,000; Estimated costs to complete 120,000; Progress billings 150,000 Collections 90,000 Contract 2: Contract price P300,000; Costs incurred during the year 280,000; Estimated costs to complete 40,000; Progress billings 270,000; Collections 250,000. At contract inception, Red Hot Co. assessed that its performance obligation in each of Contract 1 and Contract 2 is satisfied over time. Red Hot Co. uses the ‘cost-to-cost’ method in measuring its progress on the contract. How much total profit (loss) is recognized from the two contracts in 20x1?\\n*\\n4 points\\n40,000\\n20,000\\n(20,000)\\n0arrow_forwardplease answer and explain with work and steps thanksarrow_forward
- On January 1, 2021, Ka Leody Inc. entered into a long-term construction contract with fixed contract price of P 5,000,000. Ka Leody billed its client as follows: 30% during 2021, 40% during 2022 and the remainder at the end of project completion. The following data were provided by the cost accountant of the Ka Leody Inc: 2020 2021 2022 Cumulative cost incurred as of the end of the year P 2,200,000 P 3,600,000 P 4,800,000 Estimated remaining cost to complete at the end of the year P 3,300,000 P 900,000 What is the revenue to be recognized on December 31, 2021 under percentage of completion method ?arrow_forwardOn February 1, 2023, Sandhill Contractors agreed to construct a building at a contract price of $3,460,000. The total estimated construction costs would be $1,890,000 and the project would be finished in 2025. Information relating to the costs and billings for this contract is as follows: Total costs incurred to date Estimated costs to complete Customer billings to date Collections to date 2023 Gross profit/ (loss) 689,850 1,200,150 1,100,000 1,000,000 2023 2024 573050 $1,162,000 $ 2,365,000 913,000 1,890,000 1,750,000 2025 Calculate the gross profit / (loss) that should be recognized for 2023, 2024, and 2025 using the percentage completion method. (Enter negative amounts using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45). Round percentage complete to 1 decimal place, e.g. 15.2% and final answers to O decimal places, e.g. 5,125.) 2024 -0- 3,460,000 2,950,000 -107450 $ LA 2025 40450arrow_forwardQuestion Three: $960,000. The job was completed in 2022. The following information is available: During 2020 Nass Company started a construction job with a contract price of Costs to date Estimated costs to complete Billings to date Collections to date 2020 $240,000 360,000 180,000 162,000 (a) Percentage-of-completion Date 2021 2021 $495,000 165,000 540,000 486.000 Required: a) Preparing all the journal entries for 2021 Assuming Nass uses the percentage-of-completion method. Account b) Assume that Nass uses the cost-recovery method, record the revenue, and gross profit if any, recognized in 2021 and 2022. c) Show the presentation of construction-in-process and billings in construction-in-process accounts in the statement of financial position in 2020 under both the percentage-of-completion and the cost-recovery method. 2022 $642,000 0 960,000 855,000 Debit Credit ASI -991E ATUarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Intermediate Accounting: Reporting And AnalysisAccountingISBN:9781337788281Author:James M. Wahlen, Jefferson P. Jones, Donald PagachPublisher:Cengage Learning
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:9781337788281
Author:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:Cengage Learning