Question
Chapter 8, Problem 8.16E
To determine
To prepare: The
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
ABC Co. estimates total contract costs at completion d
In 20x2. ABC incurs actual costs of P2.45M and revizes its
ABC completes the construction in 20x3 The actual total
6. In 20x1, ABC Co. enters into a contact with a customer for the
uses the cost-to-cost method in measuring its progress on the
estimate of total contract costs at completion to P4.6M.
construction of a building. The contract price is P6M. ABC Co.
me
contract.
cost of the contract is P4.5M.
How much is the profit recognized in 20x3?
a. 420,000
b. 450,000
c 500,000
d. 550,000
On January 1, 2020, San Juan Builders Inc. accepted a long-term construction project to build a bridge.
The outcome of the construction project can be estimated reliably and the contractor decided to
employ cost to cost method. The following data are provided by the accountant and project manager
concerning the contract price and construction costs for the three years of construction:
Year
12/31/2022
12/31/2020
12/31/2021
Contract price as of the end of the year
P10,000,000 P15,000,000 P20,000,000
Costs incurred during the year
Р1,000,000
P5,000,000
P8,000,000
Estimated cost to complete at the end of the
Р3,000,000
P4,000,000
P2,000,000
year
What is San Juan Builders' realized gross profit / (loss) for the year ended December 31, 2022?
The total estimated cost is
Chapter 8 Solutions
Intermediate Accounting (2nd Edition)
Ch. 8 - What are the primary issues involved in revenue...Ch. 8 - What is the fundamental principle underlying the...Ch. 8 - What is the fundamental principle underlying the...Ch. 8 - Prob. 8.4QCh. 8 - Prob. 8.5QCh. 8 - How is a performance obligation defined?Ch. 8 - What are the two criteria to define a good or...Ch. 8 - Prob. 8.8QCh. 8 - What principles regarding timing and measurement...Ch. 8 - Prob. 8.10Q
Ch. 8 - What is variable consideration and what factors...Ch. 8 - Describe and contrast the two approaches used to...Ch. 8 - Prob. 8.13QCh. 8 - What factors should accountants consider to...Ch. 8 - Prob. 8.15QCh. 8 - How does a seller account for any consideration...Ch. 8 - Prob. 8.17QCh. 8 - What are the two exceptions to the general rule...Ch. 8 - What are the three criteria required to recognize...Ch. 8 - When an entity does not meet the three criteria...Ch. 8 - Prob. 8.21QCh. 8 - Prob. 8.22QCh. 8 - How does a firm estimate the degree completed...Ch. 8 - Can a firm record inventory out on consignment as...Ch. 8 - What method do agents in a transaction use to...Ch. 8 - Prob. 8.26QCh. 8 - What qualitative disclosures do the standards...Ch. 8 - All of the following are elements of a contract...Ch. 8 - Prob. 8.2MCCh. 8 - Telecom Co. enters into a two-year contract with a...Ch. 8 - The transaction price must reflect the time value...Ch. 8 - Prob. 8.5MCCh. 8 - When allocating the transaction price to separate...Ch. 8 - Which of the following indicators is not...Ch. 8 - During Yoar 1 Moriwothor Construction Company...Ch. 8 - All of the following are indicators that the...Ch. 8 - Prob. 8.10MCCh. 8 - Prob. 8.11MCCh. 8 - Identify a Contract with a Customer. Complete the...Ch. 8 - Prob. 8.2BECh. 8 - Identifying Performance Obligations. Perfect Party...Ch. 8 - Identifying Performance Obligations. Perfect Party...Ch. 8 - Estimating Variable Consideration. Gear Garage...Ch. 8 - Estimating Variable Consideration. Using the...Ch. 8 - Estimating Variable Consideration. Sellet...Ch. 8 - Estimating Variable Consideration. Seliet...Ch. 8 - Prob. 8.9BECh. 8 - Allocation of Transaction Price. Martin Software...Ch. 8 - Prob. 8.11BECh. 8 - Allocation of Transaction Price. Sycamore Sidewalk...Ch. 8 - Allocation of Transaction Price. Sycamore enters...Ch. 8 - Prob. 8.14BECh. 8 - Allocation of Transaction Price. Using the...Ch. 8 - When to Recognize Revenue. For each scenario...Ch. 8 - Prob. 8.17BECh. 8 - Prob. 8.18BECh. 8 - Percentage-of-Completion Method, Journal Entries....Ch. 8 - Prob. 8.20BECh. 8 - Sales with the Right of Return. Both incorporated...Ch. 8 - Sales with the Right of Return. Using the...Ch. 8 - Sales Returns. Historically, about 5% or the...Ch. 8 - Sales on Consignment. Hanna Lighting recertify...Ch. 8 - Determining Performance Obligations. Pagit Inc, a...Ch. 8 - Prob. 8.2ECh. 8 - Estimating Variable Consideration. King Rat Pest...Ch. 8 - Prob. 8.4ECh. 8 - Prob. 8.5ECh. 8 - Prob. 8.6ECh. 8 - Allocation of Variable Consideration. Green-Up Inc...Ch. 8 - Allocation of Variable Consideration. Green-Up Inc...Ch. 8 - Prob. 8.9ECh. 8 - Prob. 8.10ECh. 8 - Determination of When to Recognize Revenue. Far...Ch. 8 - Prob. 8.12ECh. 8 - Percentage-of-Completion Method. Gary Construction...Ch. 8 - Prob. 8.14ECh. 8 - Prob. 8.15ECh. 8 - Prob. 8.16ECh. 8 - Sales with the Right of Return. Webster Hall, Inc....Ch. 8 - Prob. 8.18ECh. 8 - Prob. 8.19ECh. 8 - Other Principal Agent Transactions, Net Revenue...Ch. 8 - Prob. 8.1PCh. 8 - Prob. 8.2PCh. 8 - Comprehensive Revenue Recognition Problem. Casale...Ch. 8 - Prob. 8.4PCh. 8 - Determining When to Recognize Revenue. Megrew...Ch. 8 - Prob. 8.6PCh. 8 - Prob. 8.7PCh. 8 - Prob. 8.8PCh. 8 - Percentage-of-Completion Method. R Wayne Computer...Ch. 8 - Prob. 8.10PCh. 8 - Prob. 8.11PCh. 8 - Sales on Consignment. Pablo Products. Ltd sells...Ch. 8 - Prob. 1JCCh. 8 - Prob. 1FSCCh. 8 - Prob. 1SSCCh. 8 - Basis for Conclusions Case 1: Control According to...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- In 2018, the Laguna Inc entered into a contract to construct a road for 5th Avenue for $14,000,000. The road was completed in 2018. Information related to the contract is as follows: Laguna uses the percentage-of-completion method of accounting for long-term construction contracts. Required: Calculate the amount of gross profit to be recognized in each of the three years. Prepare all necessary journal entries for each of the years (credit various accounts for construction costs incurred). Prepare a partial balance sheet for 2016 and 2017 showing any items related to the contract.arrow_forwardSheridan Construction Co. uses the percentage-of-completion method. In 2024, Sheridan began work on a contract for $21300000; it was completed in 2025. The following cost data pertain to this contract: Cost incurred during the year Estimated costs to complete at the end of year Year Ended December 31 $8516000. $2990000. $3680000. $3684000. 2024 $7254000 4836000 2025 $5530000 The amount of gross profit to be recognized on the income statement for the year ended December 31, 2025 isarrow_forwardLong-term Contracts Clorad Corp. contracts with a customer to construct a building. It appropriately determines that it has one performance obligation which is satisfied over time. Using the following information for Year 1, compute Clorad's (a) total estimated costs for the contract, (b) revenue to date, and (c) gross profit recognized. Year 1 (of 4-year project): Construction costs incurred during the year $174,000 Estimated costs to complete the contract 426,000 Partial billings to customers 100,000 Collections from customers 25,000 Total contract price 1,000,000 (a) Total estimated costs for the contract $ (b) Revenue to date $ (c) Gross profit recognized $arrow_forward
- At the beginning of 2021, Batangas Road Construction entered into a contract to build a road for the government. Construction will take four years. The following information as of December 31, 2021 is available for the contract: Total revenue according to contract 10,000,000 Total expected cost 8,000,000 Cost incurred during 2021 1,200,000 Assume that the company estimated percentage complete based on costs incurred as a percentage of total estimated costs. Under the completed contract method, how much revenue will be reported in 2021? None 300,000 1,500,000arrow_forwardOn July 1, 20x1, ABC Construction Co. enters into contract with a customers for the construction of a building. The contract prices is P6M, which is to be billed to the customers periodically based on ABC's progress on the construction . The estimated total contract cost is P4M. The actual costs incurred in 20x1 amounts to P1.2M. 1. The revenue to be recognized in 20x1arrow_forwardConstruction Contract: Graded Question #1: George Co. enters into a contract to build an apartment for Jungle Co. for a fixed fee of P20,000,000. At contract inception, George Co. assesses its performance obligations in the contract and concludes that it has a single performance obligation that is satisfied over time. George Co. determines that the measure of progress best depicts its performance in the contract is input method based on costs incurred. George estimates that the total contract costs would amount to P16,000,000 over the construction period. George incurs contract costs of P2,000,000 during the year. How much revenue is recognized for the year?arrow_forward
- 1. Prepare a schedule showing the revenue, cost and gross profit earned each year using thepercentage of completion method, using the engineer’s estimate as a measure ofcompletion.2. Prepare all journal entries required to reflect the contract3. Prepare journal entries for 2020 assuming zero profit method is used.arrow_forwardThe choices are the percentagearrow_forwardLetter C is the correct answer, please provide complete solution.arrow_forward
- In 2018, the Laguna Inc entered into a contract to construct a road for 5th Avenue for $14,000,000. The road was completed in 2018. Information related to the contract is as follows: 1. Calculate the amount of gross profit to be recognized in each of the three years under percentage-of-completion method of accounting for long-term construction contracts. 2. Calculate the amount of gross profit to be recognized in each of the three years under completed contract method of accounting for long-term construction contracts.arrow_forwardA Construction Co. entered into a P80M fixed price contract for the construction of a private road. The performance obligation on the contract is satisfied over time. Contractor measures its progress on the contract using the “cost-to-cost” method. The estimated total contract cost is P40M. The following were the actual costs incurred during the first year of the construction: Costs of negotiating the contract (charged immediately as expense) 400,000 Costs of materials used in construction 12,000,000 Costs of materials purchased but not yet used in construction 2,000,000 Site labor costs 4,000,000 Site supervision costs 800,000 Depreciation of equipment used in construction 480,000 Depreciation of idle construction equipment 240,000 Costs of moving plant, equipment, and materials to and from the contract site 160,000 Costs of hiring plant and equipment 560,000 Advance payments to subcontractors (subcontracted work is not yet started) 80,000 What is the percentage of completion…arrow_forwardanswer must be in table format or i will give down votearrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Intermediate Accounting: Reporting And AnalysisAccountingISBN:9781337788281Author:James M. Wahlen, Jefferson P. Jones, Donald PagachPublisher:Cengage Learning
- Individual Income TaxesAccountingISBN:9780357109731Author:HoffmanPublisher:CENGAGE LEARNING - CONSIGNMENT
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:9781337788281
Author:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:Cengage Learning
Individual Income Taxes
Accounting
ISBN:9780357109731
Author:Hoffman
Publisher:CENGAGE LEARNING - CONSIGNMENT