Intermediate Accounting (2nd Edition)
2nd Edition
ISBN: 9780134730370
Author: Elizabeth A. Gordon, Jana S. Raedy, Alexander J. Sannella
Publisher: PEARSON
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 8, Problem 8.7P
a.
To determine
The percentage completed for each year.
b.
To determine
The gross profit and revenue to be recognized each year.
Given Information:
Revenue for year 2018, 2019 and 2020 is $1,200,000, $300,000 and $500,000 respectively.
Actual cost incurred for 2018, 2019 and 2020 is $900,000, $300,000 and $600,000 respectively.
c.
To determine
To prepare:
d.
To determine
To prepare: T-accounts for construction in progress, billing on construction in progress and accounts receivables.
e.
To determine
Net assets or liability for each year.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
On February 1, 2023, Sandhill Contractors agreed to construct a building at a contract price of $3,460,000. The total estimated
construction costs would be $1,890,000 and the project would be finished in 2025. Information relating to the costs and billings for
this contract is as follows:
Total costs incurred to date
Estimated costs to complete
Customer billings to date
Collections to date
2023
Gross profit/ (loss)
689,850
1,200,150
1,100,000
1,000,000
2023
2024
573050
$1,162,000 $ 2,365,000
913,000
1,890,000
1,750,000
2025
Calculate the gross profit / (loss) that should be recognized for 2023, 2024, and 2025 using the percentage completion method. (Enter
negative amounts using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45). Round percentage complete to 1 decimal
place, e.g. 15.2% and final answers to O decimal places, e.g. 5,125.)
2024
-0-
3,460,000
2,950,000
-107450
$
LA
2025
40450
In 2021, Cupid Construction Co. (CCC) began work on a two-year fixed price contract project. CCC recognizes revenue over time according to percentage of completion for this contract, and provides the following information (dollars in millions):
Accounts receivable, 12/31/2021 (from construction progress billings)
$
37.5
Actual construction costs incurred in 2021
$
135
Cash collected on project during 2021
$
105
Construction in progress, 12/31/2021
$
207
Estimated percentage of completion during 2021
60
%
How much cash remains to be collected by CCC on the project?
On February 1, 2020, Mar Contractors agreed to construct a building at a contract price of $15,400,000. Mar initially estimated total construction costs would be $12,000,000 and the project would be finished in 2023. Information relating to the costs and billings for this contract during 2020-2022 is as follows:
2020 2021 2022
Total costs incurred during the year 4,500,000 5,300,000 4,000,000
Estimated costs to complete 7,500,000 4,200,000 1,800,000
Customer billings to date 6,600,000 12,000,000 13,800,000
Collections to date 6,000,000 10,500,000 13,500,000
Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract and all the necessary journal entries for the years ended December 31, 2020, 2021, and 2022.
Using the cost-recovery method,…
Chapter 8 Solutions
Intermediate Accounting (2nd Edition)
Ch. 8 - What are the primary issues involved in revenue...Ch. 8 - What is the fundamental principle underlying the...Ch. 8 - What is the fundamental principle underlying the...Ch. 8 - Prob. 8.4QCh. 8 - Prob. 8.5QCh. 8 - How is a performance obligation defined?Ch. 8 - What are the two criteria to define a good or...Ch. 8 - Prob. 8.8QCh. 8 - What principles regarding timing and measurement...Ch. 8 - Prob. 8.10Q
Ch. 8 - What is variable consideration and what factors...Ch. 8 - Describe and contrast the two approaches used to...Ch. 8 - Prob. 8.13QCh. 8 - What factors should accountants consider to...Ch. 8 - Prob. 8.15QCh. 8 - How does a seller account for any consideration...Ch. 8 - Prob. 8.17QCh. 8 - What are the two exceptions to the general rule...Ch. 8 - What are the three criteria required to recognize...Ch. 8 - When an entity does not meet the three criteria...Ch. 8 - Prob. 8.21QCh. 8 - Prob. 8.22QCh. 8 - How does a firm estimate the degree completed...Ch. 8 - Can a firm record inventory out on consignment as...Ch. 8 - What method do agents in a transaction use to...Ch. 8 - Prob. 8.26QCh. 8 - What qualitative disclosures do the standards...Ch. 8 - All of the following are elements of a contract...Ch. 8 - Prob. 8.2MCCh. 8 - Telecom Co. enters into a two-year contract with a...Ch. 8 - The transaction price must reflect the time value...Ch. 8 - Prob. 8.5MCCh. 8 - When allocating the transaction price to separate...Ch. 8 - Which of the following indicators is not...Ch. 8 - During Yoar 1 Moriwothor Construction Company...Ch. 8 - All of the following are indicators that the...Ch. 8 - Prob. 8.10MCCh. 8 - Prob. 8.11MCCh. 8 - Identify a Contract with a Customer. Complete the...Ch. 8 - Prob. 8.2BECh. 8 - Identifying Performance Obligations. Perfect Party...Ch. 8 - Identifying Performance Obligations. Perfect Party...Ch. 8 - Estimating Variable Consideration. Gear Garage...Ch. 8 - Estimating Variable Consideration. Using the...Ch. 8 - Estimating Variable Consideration. Sellet...Ch. 8 - Estimating Variable Consideration. Seliet...Ch. 8 - Prob. 8.9BECh. 8 - Allocation of Transaction Price. Martin Software...Ch. 8 - Prob. 8.11BECh. 8 - Allocation of Transaction Price. Sycamore Sidewalk...Ch. 8 - Allocation of Transaction Price. Sycamore enters...Ch. 8 - Prob. 8.14BECh. 8 - Allocation of Transaction Price. Using the...Ch. 8 - When to Recognize Revenue. For each scenario...Ch. 8 - Prob. 8.17BECh. 8 - Prob. 8.18BECh. 8 - Percentage-of-Completion Method, Journal Entries....Ch. 8 - Prob. 8.20BECh. 8 - Sales with the Right of Return. Both incorporated...Ch. 8 - Sales with the Right of Return. Using the...Ch. 8 - Sales Returns. Historically, about 5% or the...Ch. 8 - Sales on Consignment. Hanna Lighting recertify...Ch. 8 - Determining Performance Obligations. Pagit Inc, a...Ch. 8 - Prob. 8.2ECh. 8 - Estimating Variable Consideration. King Rat Pest...Ch. 8 - Prob. 8.4ECh. 8 - Prob. 8.5ECh. 8 - Prob. 8.6ECh. 8 - Allocation of Variable Consideration. Green-Up Inc...Ch. 8 - Allocation of Variable Consideration. Green-Up Inc...Ch. 8 - Prob. 8.9ECh. 8 - Prob. 8.10ECh. 8 - Determination of When to Recognize Revenue. Far...Ch. 8 - Prob. 8.12ECh. 8 - Percentage-of-Completion Method. Gary Construction...Ch. 8 - Prob. 8.14ECh. 8 - Prob. 8.15ECh. 8 - Prob. 8.16ECh. 8 - Sales with the Right of Return. Webster Hall, Inc....Ch. 8 - Prob. 8.18ECh. 8 - Prob. 8.19ECh. 8 - Other Principal Agent Transactions, Net Revenue...Ch. 8 - Prob. 8.1PCh. 8 - Prob. 8.2PCh. 8 - Comprehensive Revenue Recognition Problem. Casale...Ch. 8 - Prob. 8.4PCh. 8 - Determining When to Recognize Revenue. Megrew...Ch. 8 - Prob. 8.6PCh. 8 - Prob. 8.7PCh. 8 - Prob. 8.8PCh. 8 - Percentage-of-Completion Method. R Wayne Computer...Ch. 8 - Prob. 8.10PCh. 8 - Prob. 8.11PCh. 8 - Sales on Consignment. Pablo Products. Ltd sells...Ch. 8 - Prob. 1JCCh. 8 - Prob. 1FSCCh. 8 - Prob. 1SSCCh. 8 - Basis for Conclusions Case 1: Control According to...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- On March 1, 2019, Elkhart enters into a new contract to build a specialized warehouse for 7 million. The promise to transfer the warehouse is determined to be a performance obligation. The contract states that if the warehouse is usable by November 30, 2019, Elkhart will receive a bonus of 600,000. For every week after November 30 that the warehouse is not usable, the bonus will decrease by 150,000. Elkhart provides the following completion schedule: Required: 1. Assume that Elkhart uses the expected value approach. What amount should Elkhart use for the transaction price? 2. Assume that Elkhart uses the most likely amount approach. What amount should Elkhart use for the transaction price? 3. Next Level What is the purpose of assessing whether a constraint on the variable consideration exists?arrow_forwardAt the beginning of 2021, Batangas Road Construction entered into a contract to build a road for the government. Construction will take four years. The following information as of December 31, 2021 is available for the contract: Total revenue according to contract 10,000,000 Total expected cost 8,000,000 Cost incurred during 2021 1,200,000 Assume that the company estimated percentage complete based on costs incurred as a percentage of total estimated costs. Under the completed contract method, how much revenue will be reported in 2021? None 300,000 1,500,000arrow_forwardOn March 1, 2020, Pechstein Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,400,000. The building was completed by October 31, 2022. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2020, 2021, and 2022 are given below. 2020 2021 2022 Contract costs incurred during the year $2,880,000 $2,230,000 $2,190,000 Estimated costs to complete the contract at 12/31 3,520,000 2,190,000 –0– Billings to Fabrik during the year 3,200,000 3,500,000 1,700,000 Instructions a. Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2020, 2021, and 2022. (Ignore income taxes.) b. Using the completed-contract method, prepare schedules to compute the profit or loss to be recognized as a…arrow_forward
- On January 1, 2021. Robredo Co. started the construction of a building with a fixed contract price of P10,000,000. The outcome of the construction project can be estimated reliably and the contractor decided to employ cost to cost method. The following data are provided by the accountant and project manager concerning the construction costs for the three years of construction: Year 12/31/2021 12/31/2022 12/31/2023 P 3740000 Costs incurred during the year Realized gross profit/(loss) during the year Percentage of completion as of the end of the year ? ? P750,000 (P250,000) (P800,000) 50% 37.5% ? What is the balance of Construction in Progress on December 31, 2023?arrow_forwardOn February 1, 2023, Magicfort Contractors agreed to construct a building at a contract price of $5,840,000. Magicfort estimated total construction costs would be $4,032,000 and the project would be finished in 2025. Information relating to the costs and billings for this contract is as follows: 2023 2024 2025 Total costs incurred to date Estimated costs to complete $1,512,000 2,520,000 $2,664,000 $4,620,000 1,776,000 -0- Customer billings to date 2,240,000 4,032,000 5,640,000 Collections to date 2,040,000 3,540,000 5,540,000 Fill in the correct amounts on the following schedule. For percentage-of-completion accounting and cost-recovery accounting, show the gross profit that should be reported for 2023, 2024, and 2025. Percentage-of-Completion Gross Profit 2023 2023 Cost-Recovery Gross Profit 2024 $ 2025 $ SA 2024 2025 $arrow_forwardRogers Ltd. has entered into a contract beginning in February 2020 to build two warehouses for ocean Ltd. The contract is a non-cancellable fixed price contract for $9.4 million. The following data pertain to the construction period. 2020 2021 2022 Costs for the year $3,285,000 4,015,000 1,800,000 Estimated costs to complete 4,015,000 1,825,000 -0- Progress billings for the year (non-refundable) 2,960,000 3,440,000 3,000,000 Cash collected for the year 2,605,000 3,490,000 3,305,000 a) Using the percentage-of-completion method, calculate the percent complete for each year of the contract. b) Calculate the amount of the gross profit to be recognized each year of the contract. c) Prepare the journal entries for 2020 and 2021. (Use Materials, Cash, Payables for costs incurred to date.) d) What is the balance in the Contract Asset/Liability account at December 31, 2020 and 2021? Show how the construction contract would be reported on the SFP…arrow_forward
- In 2021, ABC Company agreed to construct a commercial building at a price of P7,500,000. ABC uses the percentage of completion method. The information relating to the costs and billings for the contract were as follows: 2021 2022 2023 Cost P2,100,000 P4,500,000 P5,887,500 incurred to date Estimated 3,900,000 1,500,000 cost to complete 7,500,000 Progress billings to date 1,125,000 3,000,000 Collection 900,000 2,400,000 7,050,000 to date How much is the contract asset (liability) as of December 31, 2022 using View 1 of the PIC? Group of answer choices (P2,625,000) (P1,500,000) P2,625,000 P1,500,000arrow_forwardIndarrow_forwardOn March 1, 2025, Pharoah Construction Company contracted to construct a factory building for Bloom Manufacturing Inc. for a total contract price of $8,330,000. The building was completed by October 31, 2027. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Bloom for 2025, 2026, and 2027 are given below. 2025 2026 2027 Contract costs incurred during the year $2,662,800 $2,188,000 $2,389,200 Estimated costs to complete the contract at 12/31 Billings to Bloom during the year 3,180,000 3,677,200 2,389,200 3,480,000 -0- 1,670,000 (a1) Using the percentage-of-completion method, prepare a schedule to compute the profit or loss to be recognized as a result of this contract for the year ended December 31, 2025. (Ignore income taxes.) (If answer is 0, please enter O. Do not leave any fields blank. Enter loss using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45).) 2025 LA %arrow_forward
- Swifty Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $598,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $894,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $263,120 $412,620 $607,000 Estimated costs to complete 334,880 185,380 –0– Progress billings to date 272,000 545,000 894,000 Cash collected to date 242,000 495,000 894,000 (a) Using the percentage-of-completion method, compute the estimated gross profit that would be recognized during each year of the construction period. (If answer is 0, please enter 0. Do not leave any fields blank.) Gross profit recognized in 2020 $ Gross profit recognized in 2021 $ Gross profit recognized in 2022 $ (b) Using the completed-contract method, compute the estimated…arrow_forwardOn January 1, 2021, Ka Leody Inc. entered into a long-term construction contract with fixed contract price of P 5,000,000. Ka Leody billed its client as follows: 30% during 2021, 40% during 2022 and the remainder at the end of project completion. The following data were provided by the cost accountant of the Ka Leody Inc: 2020 2021 2022 Cumulative cost incurred as of the end of the year P 2,200,000 P 3,600,000 P 4,800,000 Estimated remaining cost to complete at the end of the year P 3,300,000 P 900,000 What is the revenue to be recognized on December 31, 2021 under percentage of completion method ?arrow_forwardFender Construction Company receives a contract to construct a building over a period of 3 years for a price of $700,000. The contract represents a single performance obligation that will be satisfied over time. Information relating to the performance of the contract is summarized as follows: 2019 2020 2021 Construction costs incurred during the year $150,000 $242,000 $168,000 Estimated costs to complete 350,000 168,000 — Billings during the year 120,000 250,000 330,000 Collections during the year 100,000 260,000 340,000 Required: 1. Prepare journal entries for all 3 years. 2. Assume that the contract represents a single performance obligation that will be satisfied at a point in time. Prepare journal entries for all 3 years. Please dont provide image based answers thank youarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Intermediate Accounting: Reporting And AnalysisAccountingISBN:9781337788281Author:James M. Wahlen, Jefferson P. Jones, Donald PagachPublisher:Cengage Learning
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:9781337788281
Author:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:Cengage Learning