Principles Of Operations Management
11th Edition
ISBN: 9780135173930
Author: RENDER, Barry, HEIZER, Jay, Munson, Chuck
Publisher: Pearson,
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 8, Problem 16P
a)
Summary Introduction
To select: The range of production which has the optimal location.
Introduction: Location is one of the important element for a business that controls the cost and expenses. Location strategies support in framing other strategies for a firm where optimal location point will provide competitive advantage to a firm.
b)
Summary Introduction
To select: The best site for a production of 200 units.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Sap Manufacturing, a manufacturing company that manufactures football jerseys and located in Port Antonio, Jamaica, is preparing to build a new plant. J’s is considering three potential locations that are suitable for the construction of the plant. The fixed and variable costs for the three alternative locations are presented in the table below.
Costs
A
B
C
Fixed Costs ($)
700,000
1,000,000
1,100,000
Variable ($ per unit)
28
20
18
Identify the range over which each alternative (A, B and C) is best.
A manufacturing firm is considering three potential locations for a new parts manufacturing facility. A consulting firm has assessed three sites based on the four factors supplied by management as critical to the location's success. The factor weights and the consultant team scores are given in table 5 below. Scores are based on 50 = best.
Locations
Factors
Weights
A
B
C
Labor Climate
10
35
45
20
Taxes
30
30
40
40
Utilities
20
25
20…
snip
William Green, vice president of manufacturing for computer products (CPC), and his staff are studying three midwestern alternative locations for a new production facility for producing high-resolution scanners. His staff analysts predict that the scanners will be a growing market over the next ten years, and the analyst's group shares marketing's enthusiasm for planning facilities for producing this new product line. The analysts have developed these estimates for the three locations;
In what range of production volume would each of the locations be preferred (at the minimum cost)?
Variable cost
locations
Annual Fixed costs
per scanner
Cleveland, Ohio
$390,000
$34
South Bend, Indiana
$360,000
$37
Grand Rapids, Michigan
$310,000
$40
Chapter 8 Solutions
Principles Of Operations Management
Ch. 8 - Prob. 1EDCh. 8 - Prob. 1DQCh. 8 - Prob. 2DQCh. 8 - Prob. 3DQCh. 8 - Prob. 4DQCh. 8 - Prob. 5DQCh. 8 - Prob. 6DQCh. 8 - Prob. 7DQCh. 8 - Prob. 8DQCh. 8 - Prob. 9DQ
Ch. 8 - Prob. 10DQCh. 8 - Prob. 11DQCh. 8 - Prob. 12DQCh. 8 - Prob. 13DQCh. 8 - Prob. 14DQCh. 8 - Prob. 15DQCh. 8 - Prob. 16DQCh. 8 - Prob. 17DQCh. 8 - Prob. 18DQCh. 8 - Prob. 1PCh. 8 - Prob. 2PCh. 8 - Prob. 3PCh. 8 - Prob. 4PCh. 8 - Prob. 5PCh. 8 - Prob. 6PCh. 8 - Prob. 7PCh. 8 - Prob. 8PCh. 8 - Prob. 9PCh. 8 - Prob. 10PCh. 8 - Prob. 11PCh. 8 - Prob. 12PCh. 8 - Prob. 13PCh. 8 - Prob. 14PCh. 8 - Prob. 15PCh. 8 - Prob. 16PCh. 8 - Prob. 17PCh. 8 - Prob. 18PCh. 8 - Prob. 19PCh. 8 - Prob. 20PCh. 8 - Prob. 21PCh. 8 - Prob. 22PCh. 8 - Prob. 23PCh. 8 - Prob. 24PCh. 8 - Prob. 26PCh. 8 - Prob. 27PCh. 8 - Prob. 28PCh. 8 - Prob. 29PCh. 8 - Prob. 31PCh. 8 - Prob. 32PCh. 8 - Prob. 1CSCh. 8 - Prob. 2CSCh. 8 - Prob. 3CSCh. 8 - Prob. 4CSCh. 8 - Prob. 1.1VCCh. 8 - Prob. 1.2VCCh. 8 - Prob. 1.3VCCh. 8 - Prob. 2.1VCCh. 8 - Prob. 2.2VCCh. 8 - Prob. 2.3VCCh. 8 - Prob. 2.4VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Sap Manufacturing, a manufacturing company that manufactures football jerseys and located in Port Antonio, Jamaica, is preparing to build a new plant. J’s is considering three potential locations that are suitable for the construction of the plant. The fixed and variable costs for the three alternative locations are presented in the table below. Identify the range over which each alternative (A, B and C) is best.arrow_forwardWhen an organization is determining a location choice, what sustainability issues should it consider? What ethical issues should be considered?arrow_forwardThe fixed and variable costs for three potential manufacturing plant sites for a rattan chair weaver are shown: Site Fixed Cost Per Year Variable Cost per Unit 1 $800 $10.00 $5.00 $4.00 $1,100 3 $2,100 a) Afteř rounding to the nearest whole number, site 1 is best below V units. After rounding to the nearest whole number, site 2 is best between V and V units. After rounding to the nearest whole number, site 3 is best above V units. b) If the demand is 1010 units, then the best location for the potential manufacturing plant isarrow_forward
- The fixed and variable costs for four potential plant sites for Brent Snyder's Ski Supplies are shown here: a) Graph the total-cost lines for the four potential sites.b) Over what range of annual volume is each location the preferable one (that with lowest expected cost)?c) If expected volume of the ski equipment is 5,000 units, which location would you recommend?arrow_forwardThe following table shows the fixed cost and variable cost for 3 locations. Construct cost curves for these 3 locations for production from 0 to 200 units at 20 units intervals. What would be the range of production units that would give Location A a competitive advantage? What would be the range for Location B and Location C, respectively?arrow_forwardA location analysis for Cook Controls, a small manufacturer of parts for high-technology cable systems, has been narrowed down to four locations. Cook will need to train assemblers,testers, and robotics maintainers in local training centers. Lori Cook, the president, has asked each potential site to offer training programs, tax breaks, and other industrial incentives. The critical factors. their weights, and the ratings for each location are shown in the following table. High scores represent favorable values a) Compute the composite (weighted average) rating for each location.b) Which site would you choose?c) Would you reach the same conclusion if the weights for operating cost and labor cost were reversed? Recompute as necessary and explain.arrow_forward
- What does the term "nature of location decisions" mean?arrow_forwardTATA Motors is considering three sites - A, B, and C - at which to locate a factory to build its new-model automobile, the TATA SUV XL500. The goal is to locate at a minimum-cost site, where cost is measured by the annual fixed plus variable cost of production. TATA Motors has gathered the following data: Site Annualized Fixed Cost Variable Cost per Auto Produced A $11,000,000 $2,000 B $20,000,000 $1,400 C $27,000,000 $550 The firm knows it will produce between 0 and 60,000 SUV XL500s at the new plant each year, but, thus far, that is the extent of its knowledge about production plans. Find the range of the production volume for which a)site A is optimal. b)site B is optimal. c)site C is optimal.arrow_forwardPlease solve the attachedarrow_forward
- Hyundai Motors is considering three sites—A, B, and C—at which to locate a factory to build its new-model automo-bile, the Hyundai Sport C150. The goal is to locate at a minimum-cost site, where cost is measured by the annual fixed plus variable costs of production. Hyundai Motors has gathered the followingdata: SITE ANNUALIZEDFIXED COST VARIABLE COST PERAUTO PRODUCEDA $10,000,000 $2,500B $20,000,000 $2,000C $25,000,000 $1,000The firm knows it will produce between 0 and 60,000 Sport C150sat the new plant each year, but, thus far, that is the extent of itsknowledge about production plans.a) For what values of volume, V, of production, if any, is site C arecommended site?b) What volume indicates site A is optimal?c) Over what range of volume is site B optimal? Why?arrow_forwardDaniel Tracy, owner of Martin Manufacturing, must expand by building a new factory. The search for a location for this factory has been narrowed to four sites: A, B, C, or D. Thefollowing table shows the results thus far obtained by Tracy by using the factor-rating method to analyze the problem. The scale used for each factor scoring is I through 5. a) Which site should Tracy choose?b) If site D 's score for Energy costs increases from a 3 to a 5, do results change?c) If site A's Weather score is adj usted to a 4, what is the impact? What should Tracy do at this point?arrow_forwardA dental care facility location analysis has been narrowed down to two locations in Alexandria; Stanley and Camp-Cesar. The main factors in the decision will be the supply of dental clinic raw materials, which has a weight of 0.50, transportation cost, which has a weight of 0.40, and labor cost, which has a weight of 0.10. The scores for raw materials, transportation, and labor are for Stanley 60, 80, and 70, respectively; for Camp-Cesar 70, 50, and 90, respectively. Given this information and a minimum acceptable composite score of 75, we can say that the facility OM should: A. be indifferent between these locationsB. choose StanleyC. choose Camp-CesarD. reject both locationsE. build a dental care facility in both districts.Why? – Comment to justify your (the OM) decision.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,