a)
To determine: The output at which two locations will have same profit.
Introduction: Location is one of the important element for a business that controls the cost and expenses. Location strategies support in framing other strategies for a firm where optimal location point will provide competitive advantage to a firm.
a)

Answer to Problem 19P
At 120 machine tools, the profits at both the locations are identical.
Explanation of Solution
Given information:
Site | Fixed cost per year | Variable cost per year |
B | $800,000 | $14,000 |
Mc | $920,000 | $13,000 |
Calculation to find the output at which two locations will have same profit:
Denote the volume of production of machine tools as “x”.
Given the selling price of each machine tool at $29,000, the total revenues, denoted by TR are
Given the B location has a fixed cost of $800,000 per year and a variable cost of $14,000, express the total cost TCB for a production volume of “x” machine tools as follows.
Given the Mc location has a fixed cost of $920,000 per year and a variable cost of $13,000, express the total cost TCMc for a production volume of “x” machine tools as follows.
Calculate the volume of output “x” where both locations have the same profit
Equating the equations and solving for x, the volume of production of 120 machine tools, the profits at both the locations are identical.
Hence, at 120 machine tools, the profits at both the locations are identical
b)
To determine: The output at which location B will have high profit than location Mc.
Introduction: Location is one of the important element for a business that controls the cost and expenses. Location strategies support in framing other strategies for a firm where optimal location point will provide competitive advantage to a firm.
b)

Answer to Problem 19P
Upto production level of 120 units Location B will have high profit.
Explanation of Solution
Given information:
Site | Fixed cost per year | Variable cost per year |
B | $800,000 | $14,000 |
Mc | $920,000 | $13,000 |
Calculation to find the output at which location B will have high profit than location Mc:
To find out at what range of output the location B will have higher profits compared to the location Mc draw graphs of the two cost functions TCB and TCMc besides the revenues TR as shown below.
The graph lines for TCB and TCMc intersect at a production volume of 120 machine tools.
The location B is cost effective up to a production volume of 120 units. Therefore, profitability also will be higher at location B upto a production level of 120 units.
Hence, upto production level of 120 units Location B will have high profit.
c)
To determine: The output at which location Mc will have high profit than location B.
c)

Answer to Problem 19P
For production level above 120 units Location Mc will have high profit.
Explanation of Solution
Given information:
Site | Fixed cost per year | Variable cost per year |
B | $800,000 | $14,000 |
Mc | $920,000 | $13,000 |
Calculation to find the output at which location Mc will have high profit than location B:
For production volumes above 120 machine tools, the Mc location is preferable as costs are lower and the profitability improves.
Hence, above production level of 120 units Location Mc will have high profit.
d)
To determine: The break-even point of each location.
d)

Answer to Problem 19P
The break-even point for location B is 54 machine tools and for location Mc is 58 machine tools.
Explanation of Solution
Given information:
Site | Fixed cost per year | Variable cost per year |
B | $800,000 | $14,000 |
Mc | $920,000 | $13,000 |
Calculation of break-even point:
Calculate the break even point for Bhnm location by linking equations (1) and (2), since at the break even point the total revenues are same as total costs.
Ignoring the fractional part, the location B breaks even at a production volume of 54 machine tools.
Similarly calculate the break even point for Mckny location by linking equations (1) and (3), since at the break even point the total revenues are same as total costs.
Ignoring the fractional part, the Mc location breaks even at a production volume of 58 machine tools. Breakeven production volumes for both the locations are much below the crossover production volume of 120 machine tools.
Hence, the break-even point for location B is 54 machine tools and for location Mc is 58 machine tools.
Want to see more full solutions like this?
Chapter 8 Solutions
Principles Of Operations Management
- what would the reccomended course of action be in the Cervus Equipment Corp., Harvestinga Future case? including a Justification and Integration of recommendations and dentification + use of suitable decision criteriato rank options▪ Development of practical options in relation toidentified issue(s) + prior analysis▪ Qualitative + financial evaluation andcomparison of optionsarrow_forwardwhat would the reccomended course of action be in the Cervus Equipment Corp., Harvestinga Future case?arrow_forwardMaria Gutierrez bought a computer system for $1350. She made a down payment of $ 135 and arranged to make 29 monthly payments of $48.88. After making 20 payments she decided to pay the loan in full. Use the Rule of 78 to determine the unearned interest and the amount necessary to pay the loan in full. The unearned interest is $ (Round to the nearest cent.) Part 2 The amount required to pay the loan in full is $ (Round to the nearest cent.)arrow_forward
- 2. A community health system’s nurse team consists of 12 nurses working in the local community. It takes a nurse 1.5 hours to complete one patient visit (including travel time and breaks). a. What is the capacity of the nurse team over the course of a 9-hour workday? b. Assuming the demand for the nurses is 60 patients per day, what is the utilization of the nurse team? c. Assuming the demand for the nurses is 60 patients per day, what is the cycle time?arrow_forwardLO3-2, 3-4, 3-5 6. Consider the following production process for manufacturing biscuits. The first step of the process is mixing, where all of the ingredients are combined in the correct proportion to form dough. In the next step of the process, the dough is formed into sheets and cut into pieces in preparation for baking. The cut dough is then baked into biscuits and subsequently must be cooled. The final step of the process is packaging the biscuits for the consumer. The following table summarizes the production process along with the processing times at each step of the process. The process is highly automated, so assume that this is a machine-paced process with one machine available at each step. Process Step Mixing Activity Time (Minutes per Batch) Forming Baking Cooling Packing 15 10 12 18 10 a. What is the capacity of the baking process step (in batches per hour)? b. What is the bottleneck of the manufacturing process? c. Assuming unlimited demand, what is the process flow rate…arrow_forwardLO3-1, 3-2, 3-4, 3-5 3. Consider a process consisting of three resources. Assume there exists unlimited demand for the product. a. Resource 1 has a processing time of 6 minutes per unit. b. Resource 2 has a processing time of 3 minutes per unit. c. Resource 3 has a processing time of 5 minutes per unit. All three resources are staffed by one worker. a. Draw a process flow diagram of this process. b. What is the capacity of resource 2? c. What is the bottleneck in the process? d. What is the utilization of resource 2? e. How long does it take the process to produce 200 units starting with an empty system, assuming this is a worker-paced process?arrow_forward
- 1. It takes a barber 15 minutes to serve one customer. a. What is the capacity of the barber expressed in customers per hour? b. Assuming the demand for the barber is two customers per hour, what is the flow rate? c. Assuming the demand for the barber is two customers per hour, what is the utilization? d. Assuming the demand for the barber is two customers per hour, what is the cycle time?arrow_forward12 points) Jonathon's Restaurant is looking to open a new location. Caitlin Elizabeth has been developing a project plan and has identified tasks, precedence relations, and normal task durations shown in the table below: Assuming an indirect and overhead cost rate of 115, find the makespan and cost for a standard Early Start schedule: Makespan: Cost: Because Caitlin has studied project management at the University of Portland, she knows that a wise project manager should consider the trade-off between indirect/overhead costs and direct resource costs when establishing the "baseline" schedule. Assuming indirect/overhead costs of $115 per period and the direct compression costs and compression limits shown in the table above, find the following: Makespan: Cost: Compression strategy (enter answer as a vector: begin with "<", comma separated values, end with ">", e.g. < 0, 0, 5, ..., 2, 0>): Evidently this project is a very high priority project for Caitlin's boss.…arrow_forwardProblem 1. (2 points) Jimbo's Java & Jerk is looking to implement a new labor scheduling system. Colin Alexander has been developing a project plan and has identified the following tasks, precedence relations, and normal task durations. Because Colin has studied project management at the University of Portland, he knows that the he should incorporate a time buffer into any estimates for the project's makespan. If Colin wants to quote a 90% makespan: Quoted Makespan = Time Buffer = Note: state all answers to two decimal places.arrow_forward
- 1 point) Saint Teresa's Hospital is looking to implement a new ERP system. Ray Bones has been developing a project plan and has identified the following tasks, precedence relations, and normal task durations. Ray has studied project management at the University of Portland and knows that the starting and ending time of any task may be determined from the information in the table using the critical path method. Assume the following notation when answering the questions below: Please provide the CPM result for each of the following metrics:arrow_forwardWhy might there be commonalities or patterns in the retail industry between gross margin percentage and inventory turns with references?arrow_forwardIs there a pattern between gross margin percentage and inventory turns in the retail industry?arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage Learning