Concept explainers
a
Interpretation: Tasks for each workstation, total time and idle time are to be calculated.
Concept Introduction:
Longest task time first rule:In this rule of line balancing, the task which has highest cycle time is assigned first to the workstation.
a
Explanation of Solution
Cycle Time:
It is the time between two consecutive outputs come out from a process.
Here CT = Cycle time; A = Available time to produce output; R = Demand
Assembly line:
It is a manufacturing process in which goods or services created in previous steps are joined together. Assembly line efficiency can be calculated by following formula:
Here t = Task time; N= Actual no. of workstations; CT = cycle time
Idle time:
It is time for which machines or employees do not work due to the stoppage or work for any causes.
Here N= Actual no. of work stations; CT= cycle time; t = task time
Assembly time per shift (A) = 480 min
No. of shifts each day = 1
Output forecasted per shift(R) = 60 units
The theoretical minimum no. of the workstation can be obtained as follows:
Here CT= Cycle time; t= Sum of tasks time;
Theoretically, minimum no. of the workstation is:
Line balancing by longest task time first rule can be calculated as follows:
Lines balanced by the assignable task are determined by longest task time first rule. It has following steps:
Task 2 has highest processing time and no prerequisite is required therefore it is assigned on station A.
Although task 1 has highest processing time after task 2 in that case, total time exceeds the cycle time, therefore, task 4 and 3 is assigned on station A along with task 2 as no prerequisite is required for these tasks.
Task 1 is assigned to station B and there is a tie between task 6 and 7 as both task time is same.
Task5 is assigned to station C as its preceding task 1, 2, 3 has already assigned.
Either task 6 or 7 is assigned to station D.
Finally, task 8 is assigned to station E.
In actual situation no. of workstation are 5 in order to follow precedence and cycle time rule.
Station | Tasks | Total Time(min) | Idle Time(min) |
A | 2,4,3 | 8 | 0 |
B | 1,6 (or 7 tie) | 7 | 1 |
C | 5 | 6 | 2 |
D | 7 (or 6) | 3 | 5 |
E | 8 | 8 | 0 |
Total | 32 | 8 |
Total time at station A= Task Time of task 2+ Task Time of task 3+ Task Time of task 4
Total time at station A = 5+1+2
= 8 min
Idle time at station A= Cycle time-Total tasks at station A
= 8-8
= 0 min
Total time at station B = Task Time of task 1+ Task Time of task (6 or 7)
Total time at station B = 4+3
=7 min
Idle time at station B= Cycle time-Total tasks time at station B
=8-7
=1 min
Total time at station C = 6 min
Idle time at station C= Cycle time-Total tasks time at station c
= 8-6
= 2 min
Total time at station D= Task time of task 7 or 6
Total time at station D= 3 min
Idle time at station D= Cycle time-Total tasks time at station D
= 8-3
= 5 min
Total time at station E= Task Time of task D
Total time at station E= 8 min
Idle time at station E= Cycle time- Total tasks time at Station E
= 8-8
= 0 min
Total time
Total idle time:
It can be calculated as follows:
b
Interpretation:Assembly line efficiency is to be determined.
Concept Introduction:
Assembly line:It is a manufacturing process in which goods or services created in previous steps are joined together. Assembly line efficiency can be calculated by following formula:
Here t = Task time; N= Actual no. of workstations; CT = cycle time
b
Explanation of Solution
Assembly line efficiency can be calculated as follows:
c
Interpretation:Whether assembly line balance solution is good or bad and a criterion for assessment is to be explained.
Concept Introduction:
Idle time:It is time for which machines or employees do not work due to the stoppage or work for any causes.
c
Explanation of Solution
The assembly line balancing goodness is assessing its assembly line efficiency and idle time. In present case, although the assembly line efficiency is 80% the idle time is 8 min which is very high. It is highest for station D i.e. 5 min and at station B and C has 1 and 2 min idle time respectively. Therefore a fair chance that station B and C becomes bottleneck station for the assembly line. So it is not the very good balancing solution.
Want to see more full solutions like this?
Chapter 8 Solutions
OM (with OM Online, 1 term (6 months) Printed Access Card)
- This area of emotional intelligence describes your ability to not only understand your strengths and weaknesses but to recognize your emotions and their effect on you and your team’s performance self management self awareness relationship management social awarenessarrow_forwardEmotional intelligence is defined as the ability to understand and manage your emotions, as well as recognize and influence the emotions of those around you. True Falsearrow_forwardAt the Ford automobile Highland plant, assume the one-millionth vehicle was produced in 1916 at a cost of $8084 (in 2013 US$), by how much did the Ford company reduce his cost with each doubling of cumulative output from 1916 to 1927?arrow_forward
- At the Ford automobile Highland plant,in 1913, how long did the average worker stay with the plant and what was the average tenure of a worker?arrow_forwardCommunity Federal Bank in Dothan, Alabama, recently increased its fees to customers who use employees as tellers. Management is interested in whether its new tee policy has increased the number of customers now using its automatic teller machines to that point that more machines are required. The following table provides the number of automatic teller transactions by week. Use trend projection with regression to forecast usage for weeks 13-16.arrow_forwardDavison Electronics manufactures three LED television monitors, identified as Model A, Model B, and Model C. Davison Electronics four manufacturing plants. Each model has its lowest possible production cost when produced at Plant 1. However, Plant 1 does not have the capacity to handle the total production of all three models. As a result, at least some of the production must be routed to the other manufacturing plants. The following table shows the minimum production requirements for next month, the plant capacities in units per month, and the production cost per unit at each plant: Model Production Cost per Unit Minimum Production Requirements Plant 1 Plant 2 Plant 3 Plant 4 A $25 $28 $37 $34 48,000 B $26 $35 $36 $41 75,000 C $20 $31 $26 $23 60,000 Production Capacity 65,000 50,000 32,000 43,000 Davison’s objective is to determine the cost-minimizing production planarrow_forward
- Anecdotally, entrepreneurs frequently encounter two critical dilemmas in managing human resources: the timing of hiring and the decision regarding hiring a generalist versus a specialist for their growing venture. Deciding when to expand a team is crucial, as premature hiring (i.e., hiring too soon) can strain resources, while delayed hiring (i.e., hiring too late) might hinder growth opportunities. Moreover, the choice between hiring a generalist or a specialist depends on the specific needs and stage of the venture, with each option presenting distinct advantages and challenges. To address these issues, a management scholar seeks to identify the factors shaping the hiring cycle throughout the entrepreneurial journey and to understand the criteria for choosing between generalists and specialists at various stages of a venture. The scholar has assembled a sample of 20 experienced South African entrepreneurs who have encountered both failure and success in the financial technology…arrow_forward3. [25 pts.] Four projects are available for investment. The projects require the cash flows and yield the net present values (NPV) (in millions) shown in the following table. Project id. 1 2 Cash outflow at time 0 (million Lira) 8 8 NPV (million Lira) 12 11 3 4 6 5 8 6 If 20 million Lira is available for investment at time 0, find the investment plan that maximizes NPV. All investments are required to be 0 or 1 (fractional investment values are not permitted). a. Formulate the mathematical model. (Write the decision variables, objective function and the constraints.) [10 pts.] b. Find the optimal solution by using Branch and Bound method (Draw the branch and bound tree clearly, write also lower bounds(LB)) (Left branches x=0, right branches x =1) [15 pts.].arrow_forwardexamine the production concept and operations management, what are the key steps required to achieve success? Be specific in your response.arrow_forward
- Produce a 3000 report with references on one international organization of your choice and Address the following: Provide a brief introduction of the organisation and sector it operates in, including its mission and vision statements, its core values, a summary of its financial performance and a general overview of the business’s operational activities. From the relevant literature explain the Total Quality Management (TQM) processes the chosen organization follows and identify one quality challenge/issue that the organization faced or is currently facing. Explain how the organization managed/or still managing the particular quality challenge/issue. Critically analyze whether the organization failed or succeeded in achieving and maintaining quality performance. Provide a few critical recommendations for business managers in order to highlight the importance of Total Quality Management (TQM) within an organization.arrow_forward問題2 Production system design involves determining the arrangement of workstations and the... O allocation of resources to workstations design of the process O production schedule all of the abovearrow_forwardElaborate on the need for and the benefits of an effective supply chain management (SCM) system in the context of a globalized and networked economy. In your answer, explain how organizations like Dell and Hewlett-Packard leverage supply chain networks to maintain competitiveness, and analyse the impact of globalization, technological advancements, and business environment changes on supply chain structures. Additionally, evaluate the key components of SCM, including distribution network configuration, inventory management, and cash-flow management, and discuss how these components contribute to creating an effective and integrated supply chain. (15) 3.2. Critically evaluate the requirements for effective inventory management within an organization. In your answer, discuss the importance of inventory accounting systems, the role of cost information (holding, ordering, and shortage costs), and the significance of classification systems like ABC analysis. Additionally, analyse how…arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
- MarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational Publishing