Chapter 7.S, Problem 9P
a)
Summary Introduction
To determine: The unit cost for 20 units.
Introduction: Learning curve is referred as the cost curve, experience curve, efficiency curve or productivity curve. The leaving curve gives information about the cost, efficiency, productivity and performance of an organization.
b)
Summary Introduction
To determine: The minimum production quantity necessary to make the production cost less than the purchase cost.
Introduction: Learning curve is referred as the cost curve, experience curve, efficiency curve or productivity curve. The leaving curve gives information about the cost, efficiency, productivity and performance of an organization.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
You have been asked to estimate the selling price per unit of a new production line
of a certain product. Pertinent data are as follows:
Direct labor rate
Production material
Factory overhead
Packing costs
Desired profit
RO 15.00 per hour
RO 375 per 100 items
125% of direct labor
25% of direct cost
30% of total manufacturing cost
Past experience has shown that 83% learning curve applies to the labor required for
production these items. The time to complete the first item has been estimated to
be 1.86 hours. Use the estimated time to complete the 50h item as your standard
time for the purpose of estimating the unit selling price.
Please do not give solution in image format thanku
For a production process of 30 units with a learning rate of 85% and a cost of $75 to produce the first unit, construct a table displaying the Cost to Product the Nth Unit and the Cumulative Cost for units 1 through 30.
National Company is planning to introduce a new product with an 85 percent learning rate for production for batches of 1,000 units. The variable labor costs are P30 per unit for the first 1,000-unit batch. Each batch requires 100 hours. There are P10,000 in fixed costs not subject to learning.
What is the cumulative average time per batch using the incremental unit-time learning curve for 2,000 units?
Chapter 7 Solutions
STEVENSON OPERATIONS MANAGEMENT W/CONNEC
Ch. 7.S - Prob. 1DRQCh. 7.S - Prob. 2DRQCh. 7.S - Prob. 3DRQCh. 7.S - Prob. 4DRQCh. 7.S - Prob. 5DRQCh. 7.S - Prob. 6DRQCh. 7.S - Prob. 7DRQCh. 7.S - Prob. 8DRQCh. 7.S - Prob. 9DRQCh. 7.S - Prob. 10DRQ
Ch. 7.S - Prob. 1PCh. 7.S - Prob. 2PCh. 7.S - Prob. 3PCh. 7.S - Prob. 4PCh. 7.S - Prob. 5PCh. 7.S - Prob. 6PCh. 7.S - Prob. 7PCh. 7.S - Prob. 8PCh. 7.S - Prob. 9PCh. 7.S - Prob. 10PCh. 7.S - Prob. 11PCh. 7.S - Prob. 12PCh. 7.S - Prob. 13PCh. 7.S - Prob. 14PCh. 7.S - Prob. 15PCh. 7.S - Prob. 16PCh. 7.S - Prob. 17PCh. 7.S - Prob. 18PCh. 7.S - Prob. 19PCh. 7.S - Prob. 1CQCh. 7.S - Prob. 2CQCh. 7.S - Prob. 3CQCh. 7 - Prob. 1DRQCh. 7 - What are some of the main advantage and...Ch. 7 - Prob. 3DRQCh. 7 - Prob. 4DRQCh. 7 - Prob. 5DRQCh. 7 - Prob. 6DRQCh. 7 - Prob. 7DRQCh. 7 - What are motion study principles? How are they...Ch. 7 - Prob. 9DRQCh. 7 - Prob. 10DRQCh. 7 - Prob. 11DRQCh. 7 - Prob. 12DRQCh. 7 - Prob. 13DRQCh. 7 - Prob. 14DRQCh. 7 - Prob. 15DRQCh. 7 - Prob. 16DRQCh. 7 - Prob. 17DRQCh. 7 - Prob. 18DRQCh. 7 - Prob. 19DRQCh. 7 - Prob. 1TSCh. 7 - Prob. 2TSCh. 7 - Prob. 3TSCh. 7 - Prob. 1CTECh. 7 - Prob. 2CTECh. 7 - Prob. 1PCh. 7 - Prob. 2PCh. 7 - Prob. 3PCh. 7 - Given these observed times (in minutes) for four...Ch. 7 - Prob. 5PCh. 7 - Prob. 6PCh. 7 - Prob. 7PCh. 7 - Prob. 8PCh. 7 - Prob. 9PCh. 7 - Prob. 10PCh. 7 - Prob. 11PCh. 7 - Prob. 12PCh. 7 - Prob. 13PCh. 7 - An analyst made the following observations about...Ch. 7 - Prob. 15PCh. 7 - Prob. 16PCh. 7 - Prob. 17PCh. 7 - Prob. 18PCh. 7 - Prob. 19P
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- The labor cost to produce a certain item is $8.50 per hour. Job setup costs $50 and material costsare $20 per unit. The item can be purchased for $88.50 per unit. The learning rate is 90 percent.Overhead is charged at a rate of 50 percent of labor, materials, and setup costs.a. Determine the unit cost for 20 units, given that the first unit took 5 hours to complete.b. What is the minimum production quantity necessary to make production cost less than purchasecost?arrow_forwardA manager wants to determine an appropriate learning percentage for a certain activity. Times of the first six units are given below: a. Determine the learning percentage using Excel. b. Using your answer from part a, estimate the average time if a total of 30 units are planned.arrow_forwardYou are setting up a new production line for a new type of delivery drones. You observed that the cost for the 10th unit was $6296.33 and the cost for the 80th unit was $4146.15. a) What is the K for the learning curve model of this production line? b) What is the s for the learning curve model of this production line? c) At which unit does its production cost start to be less than $1500?arrow_forward
- 44arrow_forwardIf the time needed to assemble the first five units is approximately 11.2 hours and the learning curve slop is 0.8. Calculate the time needed for producing the first unit?arrow_forwardYou need to develop a labor time estimate for a customer order of 50 network installations. It is estimated that the first installation will require 75 labor hours and a learning curve of 85 percent is expected. a. How many labor hours are required for the 25th installation?b. How many labor hours are required to complete all 50 installations? c. If the average labor cost is $28 per hour, what is the total labor cost for installing all the networks?d. How many workers are needed to complete the job in a week? Assuming each worker works 8 hours per day 5 days per week. Show breakdown of workarrow_forward
- A) A company working on an 80 percent learning curve has decided that the production standard should be 90 hours the first unit? Show detailed solution i of production for the 128th unit. How much time should be required for B) In a job shop, effective capacity in only 50 percent of design capacity, and actual output is 90 percent of effective of 9 jobs per weeks? Show detailed solution capacity. What design capacity would be needed to achieve an actual output C) You are an engineer who has been assigned a task to perform a HAZOP (Hazard and Operability) study on a Reactor used as main equipment in a certain chemical production plant. i. What are the steps to be followed to perform this study? ii. Use a table to give an example of the parameters, related guide words and deviations that could be used to develop this study.arrow_forwardThe product adx takes 77 hours for production of 1 unit, where learning curve rate is 57% and what will be the total time taken by 2th unit of product S using incremental unit time method ?arrow_forwardOn RainTite Window’s manual assembly line, a newemployee can usually assemble their first window unit in30 minutes. Management assumes a 90 percent learning rate.a. How long should a new employee take to assemble theirsecond window if management is correct in their assumption? How long should the 16th window take?b. On RainTite’s semi-automated line, a new employeetakes 45 minutes to assemble their first window; however,the learning rate is 75 percent. At how many windowsproduced will the semi-automated line’s employee takeless time to produce a window than an employee on themanual line?arrow_forward
- You need to develop a labor time estimate for a customerorder of 20 network installations. It is estimated that the fi rstinstallation will require 60 hours of labor, and a learning curve of90 percent is expected.(a) How many labor-hours are required for the fi ft eenthinstallation?(b) How many labor-hours are required for the twentiethinstallation?(c) How many labor-hours are required to complete all 20installations?(d) If the average labor cost is $32, what is the total labor costfor installing the networks?arrow_forwardProblem 2 The labor cost to produce a certain item is $20 per hour. Material cost is $60 per unit. The overhead cost is charged as 70% of the labor and materials cost. The learning rate is 80%. a. Determine the average cost for 50 units, given that the first unit took 5 hours to complete. b. Assume the item can be purchased from a vendor for $162 per unit. Should we just buy the needed 50 units or produce them. Explain. c. What are your answers for a and b if the needed quantity is 100 units? Show all your workarrow_forwardA contractor is preparing a bid to install swimming pools at a new housing addition. The estimated time to build the first pool is 38 hours. The contractor estimates an 80 percent learning rate. Using POM for Windows or OM Explorer, how long do you estimate the time required to install the sixth pool? The time required to install the sixth pool is enter your response herehours. (Enter your response rounded to two decimal places.) Part 2 What is your estimate of the total time for all six pools? The total time for all six pools is enter your response here hours. (Enter your response rounded to two decimal places.)arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.