Textbook Question
thumb_up100%
Chapter 7.S, Problem 8P
Under ideal conditions, a service bay at a Fast Lube can serve 6 cars per hour. The effective capacity and efficiency of a Fast Lube service bay are known to be 55 and 0.880 respectively. What is the minimum number of service bays Fast Lube needs to achieve an anticipated servicing of 200 cars per 8-hour day?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Under ideal conditions, a service bay at a Fast Lube can serve 7 cars per hour. The effective capacity of a Fast Lube service bay is 5.5 cars per hour, with efficiency known to be 0.88.
The minimum number of service bays Fast Lube needs to achieve an anticipated production of 150 cars per 8-hour day = service bays (enter your response rounded up to the next whole number).
Knott’s Industries manufactures standard and super premium backyard swing sets. Currently it has four identical swing-set-making machines, which are operated 250 days per year and 8 hours each day. A capacity cushion of 20 percent is desired. The following information is also known:
Standard Model
Super PremiumModel
Annual Demand
Standard Processing Time
Average Lot Size
Standard Setup Time per Lot
20,000
7 min
50
30 min
10,000
20 min
30
45 min
a. Does Knott’s have sufficient capacity to meet annual demand?b. If Knott’s was able to reduce the setup time for the Super Premium Model from 45 minutes to 30 minutes, would there be enough current capacity to produce 20,000 units of each type of swing set?
5. Under ideal conditions, a service bay at a Fast Lube can serve
8
cars per hour. The effective capacity of a Fast Lube service bay is
5.7
cars per hour, with efficiency known to be
0.85.
The minimum number of service bays Fast Lube needs to achieve an anticipated production of
150
cars per
8-hour
day =
3.93.9
service bays ( __________ ).
Chapter 7 Solutions
Operations Management
Ch. 7.S - Prob. 1DQCh. 7.S - Prob. 2DQCh. 7.S - Prob. 3DQCh. 7.S - How is actual, or expected, output computed?Ch. 7.S - Explain why doubling the capacity of a bottleneck...Ch. 7.S - Distinguish between bottleneck time and throughput...Ch. 7.S - Prob. 7DQCh. 7.S - Prob. 8DQCh. 7.S - Prob. 9DQCh. 7.S - Prob. 10DQ
Ch. 7.S - Explain how net present value is an appropriate...Ch. 7.S - Prob. 12DQCh. 7.S - What are the techniques available to operations...Ch. 7.S - Amy Xias plant was designed to produce 7,000...Ch. 7.S - For the past month, the plant in Problem S7.1,...Ch. 7.S - If a plant has an effective capacity of 6,500 and...Ch. 7.S - Prob. 4PCh. 7.S - Material delays have routinely limited production...Ch. 7.S - Prob. 6PCh. 7.S - Southeastern Oklahoma State Universitys business...Ch. 7.S - Under ideal conditions, a service bay at a Fast...Ch. 7.S - A production line at V. J. Sugumarans machine shop...Ch. 7.S - A work cell at Chris Ellis Commercial Laundry has...Ch. 7.S - The three-station work cell Illustrated in Figure...Ch. 7.S - The three-station work cell at Pullman Mfg., Inc....Ch. 7.S - The Pullman Mfg., Inc., three-station work cell...Ch. 7.S - Klassen Toy Company, Inc., assembles two parts...Ch. 7.S - Prob. 15PCh. 7.S - Prob. 16PCh. 7.S - Markland Manufacturing intends to increase...Ch. 7.S - Using the data in Problem S7.17. a. What is the...Ch. 7.S - Given the data in Problem S7.17, at what volume...Ch. 7.S - Janelle Heinke, the owner of HaPeppas!, is...Ch. 7.S - Prob. 21PCh. 7.S - Prob. 22PCh. 7.S - Prob. 23PCh. 7.S - Prob. 24PCh. 7.S - Prob. 25PCh. 7.S - As a prospective owner of a club known as the Red...Ch. 7.S - Prob. 27PCh. 7.S - James Lawsons Bed and Breakfast, in a small...Ch. 7.S - Prob. 29PCh. 7.S - Prob. 30PCh. 7.S - Prob. 31PCh. 7.S - What is the present value of 5,600 when the...Ch. 7.S - Prob. 33PCh. 7.S - Prob. 34PCh. 7.S - Bolds Gym, a health club chain, is considering...Ch. 7.S - Prob. 1VCCh. 7.S - Prob. 2VCCh. 7.S - Prob. 3VCCh. 7 - What is process strategy?Ch. 7 - Prob. 2DQCh. 7 - Prob. 3DQCh. 7 - What is process redesign?Ch. 7 - Prob. 5DQCh. 7 - Name the tour quadrants of the service process...Ch. 7 - Prob. 7DQCh. 7 - Prob. 8DQCh. 7 - Identify manufacturing firms that compete on each...Ch. 7 - Identify the competitive advantage of each of the...Ch. 7 - Prob. 11DQCh. 7 - Identify the competitive advantage of each of the...Ch. 7 - Prob. 13DQCh. 7 - Prob. 14DQCh. 7 - Prob. 15DQCh. 7 - Explain what a flexible manufacturing system (FMS)...Ch. 7 - Prob. 17DQCh. 7 - Prepare a flowchart tor one of the following: a....Ch. 7 - Prob. 2PCh. 7 - Prepare a time-function map for one of the...Ch. 7 - Prepare a service blueprint for one of the...Ch. 7 - Prob. 5PCh. 7 - Prob. 6PCh. 7 - Prob. 7PCh. 7 - Prob. 8PCh. 7 - Prob. 9PCh. 7 - Ski Boards, Inc., wants to enter the market...Ch. 7 - Prob. 11PCh. 7 - Prob. 12PCh. 7 - Using Figure 7.6 in the discussion of value-stream...Ch. 7 - Metters Cabinets, Inc., needs to choose a...Ch. 7 - Rochester Manufacturings Process Decision...Ch. 7 - Prob. 2CSCh. 7 - Prepare the case for an optimistic sales manager...Ch. 7 - Prob. 1.1VCCh. 7 - Prob. 1.2VCCh. 7 - Prob. 1.3VCCh. 7 - Prob. 1.4VCCh. 7 - Prob. 2.1VCCh. 7 - Prob. 2.2VCCh. 7 - Process Strategy at Wheeled Coach Video Case Video...Ch. 7 - Prob. 2.4VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- RideShare offers short-term rentals of vehicles that are kept in small lots in urbanneighborhoods with plenty of potential customers. With one lot, it has eight cars. Theinterarrival time of potential demand for this lot from its base of customers is 40 minutes.The average rental period is five hours. If a customer checks availability of vehicles in thislot online and finds that they are all rented for the desired time, the customer skips rentingand finds alternative arrangements. However, because customers pay a monthly fee tosubscribe to this service, RideShare does not want customers to be disappointed too often.a. What is the offered load?b. What is the implied utilization?c. What is the capacity of the process (rentals per hour)?d. What is the probability that all eight cars are rented at the same time?e. How many customers are served every hour?f. What is the utilization of the cars?g. How many cars should it have in this lot to ensure that it serves at least 90 percent ofdemand?arrow_forwardUnder ideal conditions, a service bay at a FastLube can serve 6 cars per hour. The effective capacity and efficiency of a Fast Lube service bay are known to be 5.5 and0.880, respectively. What is the minimum number of servicebays Fast Lube needs to achieve an anticipated servicing of200 cars per 8-hour day?arrow_forwardsniparrow_forward
- Agan Interior Design provides home and office decorating assistance to its customers. In normal operation, an average of 2.7 customers arrive each hour. One design consultant is available to answer customer questions and make product recommendations. Agan's management would like to evaluate two alternatives: Use one consultant with an average service time of 8 minutes per customer. Expand to two consultants, each of whom has an average service time of 10 minutes per customer. If the consultants are paid $19 per hour and the customer waiting time is valued at $29 per hour for waiting time prior to service, should Agan expand to the two-consultant system? No What is the total cost for each scenario? Round your answers to the nearest cent. The total cost for the first scenario where there is one consultant with an average service time of 8 minutes per customer is $ fill in the blank 2 . The total cost for the second scenario where there are two consultants with an average service time of…arrow_forwardAgan Interior Design provides home and office decorating assistance to its customers. In normal operation, an average of 2.1 customers arrive each hour. One design consultant is available to answer customer questions and make product recommendations. Agan's management would like to evaluate two alternatives: Use one consultant with an average service time of 8 minutes per customer. Expand to two consultants, each of whom has an average service time of 10 minutes per customer. If the consultants are paid $18 per hour and the customer waiting time is valued at $26 per hour for waiting time prior to service, should Agan expand to the two-consultant system? - No What is the total cost for each scenario? Round your answers to the nearest cent. The total cost for the first scenario where there is one consultant with an average service time of 8 minutes per customer is $____________. The total cost for the second scenario where there are two consultants with an average service time of 10…arrow_forwardThe Corner Cleaners 24-hour laundromat has 16 washing machines. A machine breaks down every 20 days(exponentially distributed). The repair service the laundromat contracts takes an average of one day to repair amachine (exponentially distributed). A washing machineaverages $5 per hour in revenue. The laundromat is considering a new repair service that guarantees repairs in0.50 day, but they charge $10 more per hour than thecurrent repair service. Should the laundromat switch tothe new repair service?arrow_forward
- Uberya Towing Services repair vehicles that break down at an average 8 vehicles per day. The mechanic crew can service an average of 11 vehicles per day. How many vehicles are likely to be in the system at any one time? The crew cost is approximately Php 900 per day. The cost associated with lost productivity from the breakdown is estimated at Php500 per vehicle per day. if an additional Service crew is added, What is the Expected or Total Cost (Waiting +Service Cost)?arrow_forwardA bank has 1 enquiries staff and six tellers. Customers enter the system and walk up to the enquires counter for the enquiries queue or they go to the tellers station where they join a single queue for the 6 tellers.The arrival rate at the enquiry counter, lambda 8 customers per hour and the service rate at the enquiry counter, Mu 6 minutes per customer. The arrival rate at the tellers’stations, lambda 10 clients per hour and the service rate at the tellerstations, Mu 4 minutes per client. Find the total time customers spend at the bankarrow_forwardA grocery store has three open checkout lanes. On average, 45 shoppers arrive at these lanes per hour. The coefficient of variation of the interarrival time is equal to 1. The average service times for all the lanes is 18 customers per hour, and the coefficient of variation of service time distribution for all three lanes is three minutes. What is the percentage decrease in utilization when one more checkout lane is added to the system? Select one: а. 62.5% b. 50% C. 25% d. 15%arrow_forward
- The Universal Manufacturing Company produces a par-ticular product in an assembly-line operation. One of the machines on the line is a drill press that has a single as-sembly line feeding into it. A partially completed unit ar-rives at the press to be worked on every 8 minutes, on average, according to an exponential distribution. Themachine operator can process an average of 10 parts perhour (Poisson distributed). Determine the average numberof parts waiting to be worked on, the percentage of timethe operator is working, and the percentage of time themachine is idle.arrow_forwardThe Delacroix Inn in Alexandria is a small exclusive hotelwith 20 rooms. Guests can call housekeeping from 8:00 A.M.to midnight for any of their service needs. Housekeepingkeeps one person on duty during this time to respond to guest calls. Each room averages 0.7 call per day to house-keeping (Poisson distributed), and a guest request requires an average response time of 30 minutes (exponentially dis-tributed) from the staff person. Determine the portion of time the staff person is busy and how long a guest must wait for his or her request to be addressed. Does the house-keeping system seem adequate?arrow_forwardUberya Towing Services repair vehicles that break down at an average 7.5 vehicles per day. The mechanic crew can service an average of 10 vehicles per day. The crew cost is approximately Php1406 per day. The cost associated with lost productivity from the breakdown is estimated at Php500 per vehicle per day. if an additional 2 Service crews are added, What is the Expected or Total Cost (Waiting +Service Cost)?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY