Metters Cabinets, Inc., needs to choose a production method for its new office shelf, the Maxistand. To help accomplish this, the firm has gathered the following production cost data:
Metters Cabinets projects an annual demand of 24,000 un1ts for the Maxistand. The Maxistand will sell for $120 per unit.
- a. Which process type will maximize the annual profit from producing the Maxistand?
- b. What is the value of this annual profit?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Reducing In-Process Inventory
a. To provide a basis of comparison, begin by evaluating the status quo. Determine the expected amount of in-process inventory at the presses and at the inspection station. Then calculate the expected total cost per hour of the in-process inventory, the presses, and the inspector.
b. What would be the effect of proposal 1? Why? Make specific comparisons to the results from part a. Explain this outcome to Jerry Carstairs.
d. Make your recommendations for reducing the average level of in-process inventory at the inspection station and at the group of machines. Be specific in your recommendations, and support them with quantitative analysis like that done in part a. Make specific comparisons to the results from part a, and cite the improvements that your recommendations would yield.
Pls include step by step solution using MS Excel
Based on the information above, Develop a SCM performance measurement design for OAK Leather using a Process-based framework approach (Chan & Qi, 2003). You may add assumptions if needed
Your company is planning to organize a workshop on quality managem ent. There are 10managers
in your company all of whom have received free passes for the workshop. These passes would
allow five free seats to the indivi duals. The managers from other companies can also attend the
event, however they need to pay $60 per pers on. All the people attending the workshop would get
complimentary lunch, snacks and parking facilities without any extra fees. There are certain costs
associated with the workshop including lunch cost of $5 per person, snacks cost of $3 per person,
parking cost of $4 per person, speakers cost of $800 per speaker (total 5 speakers are used),
registrati on fee of $7.50 per person, and auditorium cost of $200. Approximately how many
managers from outsi de the company require to attend the meeting so that the workshop would
reach break-even?
(A) 128
(B) 210
(C) 365
(D) 517
Chapter 7 Solutions
Operations Management
Ch. 7.S - Prob. 1DQCh. 7.S - Prob. 2DQCh. 7.S - Prob. 3DQCh. 7.S - How is actual, or expected, output computed?Ch. 7.S - Explain why doubling the capacity of a bottleneck...Ch. 7.S - Distinguish between bottleneck time and throughput...Ch. 7.S - Prob. 7DQCh. 7.S - Prob. 8DQCh. 7.S - Prob. 9DQCh. 7.S - Prob. 10DQ
Ch. 7.S - Explain how net present value is an appropriate...Ch. 7.S - Prob. 12DQCh. 7.S - What are the techniques available to operations...Ch. 7.S - Amy Xias plant was designed to produce 7,000...Ch. 7.S - For the past month, the plant in Problem S7.1,...Ch. 7.S - If a plant has an effective capacity of 6,500 and...Ch. 7.S - Prob. 4PCh. 7.S - Material delays have routinely limited production...Ch. 7.S - Prob. 6PCh. 7.S - Southeastern Oklahoma State Universitys business...Ch. 7.S - Under ideal conditions, a service bay at a Fast...Ch. 7.S - A production line at V. J. Sugumarans machine shop...Ch. 7.S - A work cell at Chris Ellis Commercial Laundry has...Ch. 7.S - The three-station work cell Illustrated in Figure...Ch. 7.S - The three-station work cell at Pullman Mfg., Inc....Ch. 7.S - The Pullman Mfg., Inc., three-station work cell...Ch. 7.S - Klassen Toy Company, Inc., assembles two parts...Ch. 7.S - Prob. 15PCh. 7.S - Prob. 16PCh. 7.S - Markland Manufacturing intends to increase...Ch. 7.S - Using the data in Problem S7.17. a. What is the...Ch. 7.S - Given the data in Problem S7.17, at what volume...Ch. 7.S - Janelle Heinke, the owner of HaPeppas!, is...Ch. 7.S - Prob. 21PCh. 7.S - Prob. 22PCh. 7.S - Prob. 23PCh. 7.S - Prob. 24PCh. 7.S - Prob. 25PCh. 7.S - As a prospective owner of a club known as the Red...Ch. 7.S - Prob. 27PCh. 7.S - James Lawsons Bed and Breakfast, in a small...Ch. 7.S - Prob. 29PCh. 7.S - Prob. 30PCh. 7.S - Prob. 31PCh. 7.S - What is the present value of 5,600 when the...Ch. 7.S - Prob. 33PCh. 7.S - Prob. 34PCh. 7.S - Bolds Gym, a health club chain, is considering...Ch. 7.S - Prob. 1VCCh. 7.S - Prob. 2VCCh. 7.S - Prob. 3VCCh. 7 - What is process strategy?Ch. 7 - Prob. 2DQCh. 7 - Prob. 3DQCh. 7 - What is process redesign?Ch. 7 - Prob. 5DQCh. 7 - Name the tour quadrants of the service process...Ch. 7 - Prob. 7DQCh. 7 - Prob. 8DQCh. 7 - Identify manufacturing firms that compete on each...Ch. 7 - Identify the competitive advantage of each of the...Ch. 7 - Prob. 11DQCh. 7 - Identify the competitive advantage of each of the...Ch. 7 - Prob. 13DQCh. 7 - Prob. 14DQCh. 7 - Prob. 15DQCh. 7 - Explain what a flexible manufacturing system (FMS)...Ch. 7 - Prob. 17DQCh. 7 - Prepare a flowchart tor one of the following: a....Ch. 7 - Prob. 2PCh. 7 - Prepare a time-function map for one of the...Ch. 7 - Prepare a service blueprint for one of the...Ch. 7 - Prob. 5PCh. 7 - Prob. 6PCh. 7 - Prob. 7PCh. 7 - Prob. 8PCh. 7 - Prob. 9PCh. 7 - Ski Boards, Inc., wants to enter the market...Ch. 7 - Prob. 11PCh. 7 - Prob. 12PCh. 7 - Using Figure 7.6 in the discussion of value-stream...Ch. 7 - Metters Cabinets, Inc., needs to choose a...Ch. 7 - Rochester Manufacturings Process Decision...Ch. 7 - Prob. 2CSCh. 7 - Prepare the case for an optimistic sales manager...Ch. 7 - Prob. 1.1VCCh. 7 - Prob. 1.2VCCh. 7 - Prob. 1.3VCCh. 7 - Prob. 1.4VCCh. 7 - Prob. 2.1VCCh. 7 - Prob. 2.2VCCh. 7 - Process Strategy at Wheeled Coach Video Case Video...Ch. 7 - Prob. 2.4VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- 2arrow_forwardMarco, a plumbing, heating and AC company located in California, has a simple butpowerful product strategy: ‘Solve the customer’s problem no matter what, solve theproblem when the customer needs it solved, and make sure the customer feels goodwhen you leave’. The company guaranteed, same day service for customers requiringit. The company provides 24 x 7 services at no extra charge for customers whose ACdies in hot summer Sunday or whose toilet overflows at 2.30 AM. The companyguarantees the price of a job to the penny before the work begins. Whereas mostcompetitors guarantee their work for 30 days, Marco guarantees all parts and labourfor one year. The company assesses no travel charges as “it’s not fair to charge customers for driving out.” The company owner says: “We are in an industry thatdoesn’t have best reputation. If we start making money our main goal, we are introuble. So I stress customer satisfaction; money is a by-product.”The company uses hiring, ongoing training and…arrow_forwardThe Chineke Group of Company manufactures two products, namely product B and product P, and provides you with the following information: Prod. B Prod. P Selling price per unit 80.00 50.00 Less cost of sales: Direct material A @ R5.00 per kg 15.00 10.00 Direct material B @ R4.00 per kg 8.00 12.00 Direct labour @ R6.00 per hour 12.00 6.00 Variable manufacturing overhead @ R5.00 per labour hour 10.00 5.00 Fixed manufacturing overhead per unit 5.00 5.00 Gross profit 30.00 12.00 Less sales & administrative costs: Variable 6.00 4.00 Fixed 10.00 5.00 Net profit per unit 14.00 3.00 Take note of the following constraints: Material A available 360 kg Material B available 360 kg Labour hours available…arrow_forward
- What is Process Capability Ratio (Cp)?arrow_forwardThe one in bold, I already sold. Spartan Castings must implement a manufacturing process that reduces the amount of particulates emitted into the atmosphere. Two processes have been identified that provide the same level of particulate reduction. The first process is expected to incur $340,000 of fixed cost and add $40 of variable cost to each casting Spartan produces. The second process has fixed costs of $100,000 and adds $70 of variable cost per casting. a. What is the break-even quantity beyond which the first process is more attractive? The break-even quantity is 8000 castings. b. What is the difference in total cost if the quantity produced is 5,000? The total cost of process 1 is greater. Find the difference in total cost?arrow_forward79) Which of the following best describes the benefit of Balanced Scorecard? a) The Balanced Scorecard guarantees a firm financial success for its shareholders and employees. b) The balanced Scorecard guards against the sub -optimization of individual functions by providing a holistic view of different operational measures. c) The balanced scorecard ensures that a firms product strategy is leading the market. d) The balanced scorecard protects the firm from having over-reaching government regulations.arrow_forward
- #4- The mean number of air conditioning units assembled per month by Freeze, Inc. is 750 and the standard deviation is 100 units. a. If the number of air conditioning units assembled per month follows a normal distribution, calculate the probability of Freeze, Inc to assemble a quantity of air conditioning units greater than the monthly break-even point calculated in problem 3-a. b. An improved assembling process is proposed to Freeze, Inc. to reduce the variable cost from $500 per unit to $400 per unit., increase the mean number of air conditioning units assembled per month from 750 to 850 and reduce the standard deviation to 90 units. As a result of the improvements, monthly fixed costs would go up from $250,000 to $300,000. Once these improvements are implemented, calculate the new number of air conditioning units that Freeze Inc. must sell every month to break-even, discuss and justify if you would recommend the process improvement initiative. c. If the number of air conditioning…arrow_forwardA bicycle component manufacturer produces hubs for bike wheels. Two processes are possible for manufacturing, and the parameters of each process are as follows: Process 1 Production rate Daily production time Process 2 35 parts/hour 4 hours/day 20% 15 parts/hour 7 hours/day 9% Percent parts rejected Assume that the daily demand for hubs allows all defect-free hubs to be sold. Select the process that maximizes profit per day if each part is made from $4 worth of material and can be sold for $30. Both processes are fully automated, and variable overhead cost is charged at the rate of $40 per hour.arrow_forwardMerrimac Manufacturing Company has always purchased acertain component part from a supplier on the East Coast for$50 per part. The supplier is reliable and has maintained thesame price structure for years. Recently, improvements in operations and reduced product demand have cleared up somecapacity in Merrimac’s own plant for producing componentparts. The particular part in question could be produced at$40 per part, with an annual fixed investment of $25,000.Currently, Merrimac needs 300 of these parts per year.a. Should Merrimac make or buy the component part?b. As another alternative, a new supplier located nearby isoffering volume discounts for new customers of $50per part for the first 100 parts ordered and $45 per partfor each additional unit ordered. Should Merrimacmake the component in-house, buy it from the newsupplier, or stick with the old supplier?c. Would your decision change if Merrimac’s annual demand increased to 2000 parts? increased to 5000 parts?d. Develop a set of…arrow_forward
- Draw a BPMN Diagram to implement the following business process. The steps are asfollows:1. The customer sends order (items and quantities).2. The order arrives at reseller.3. On arrival of an order message, for every order item, the reseller checks if the ordereditems and quantity is available in local inventory.a. If the item is enough in stock (Yes), ship item to the customer immediately.b. If the item is not available (No), order item from the supplier. Upon arrival of the item,send it to the customer.4. After sending an item to the customer, check if all order items have been shipped.a. If all items have been shipped, bill the customer.b. If all items have not been shipped, wait for items to arrivearrow_forwardthis question is on the Operations research subject. Please take a look at the image attached.arrow_forwardsecond image is the choices for the blanksarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Process selection and facility layout; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=wjxS79880MM;License: Standard YouTube License, CC-BY