a)
To determine: The number of days for first 10 installations.
Introduction: Learning curve is referred as the cost curve, experience curve, efficiency curve or productivity curve. The leaving curve gives information about the cost, efficiency, productivity and performance of an organization.
a)
Answer to Problem 3P
Explanation of Solution
Given information:
Formula:
Calculation of number of days for first 10 installations:
At 85% learning curve, and 10 unit number, the unit factor is 7.116 (using learning curve coefficient table)
The times for all 10 installations are calculated by multiplying first unit of 8 with the unit factor 7.116 which yields 56.93 days.
Hence, the number of days for first 10 installations is 56.93 days.
b)
To determine: The number of days for second 10 installations.
Introduction: Learning curve is referred as the cost curve, experience curve, efficiency curve or productivity curve. The leaving curve gives information about the cost, efficiency, productivity and performance of an organization.
b)
Answer to Problem 3P
Explanation of Solution
Given information:
Formula:
Calculation of number of days for second 10 installations:
To calculate the number of days for second 10 installations which is from 11 to 20, the numbers of days of installations for 1 to 20 have to be calculated and then it has to be subtracted from number of days of installations of 1 to 10.
Number of installation of first 20 units:
At 85% learning curve, and 20 unit number, the unit factor is 12.402 (using learning curve coefficient table)
The times for all 20 installations are calculated by multiplying first unit of 8 with the unit factor 12.402 which yields 99.22 days.
From the computed number of days, subtract the number of needed for first 10 installations,
Hence, the number of days for second 10 installations is 42.29 days.
c)
To determine: The number of days for last 10 installations.
Introduction: Learning curve is referred as the cost curve, experience curve, efficiency curve or productivity curve. The leaving curve gives information about the cost, efficiency, productivity and performance of an organization.
c)
Answer to Problem 3P
Explanation of Solution
Given information:
Formula:
Calculation of number of days for last 10 installations:
To calculate the number of days for last10 installations which is from 21 to 30, the numbers of days of installations for 1 to 30 have to be calculated and then it has to be subtracted from number of days of installations of 1 to 20.
Number of installation of first 30 units:
At 85% learning curve, and 30 unit number, the unit factor is 17.091 (using learning curve coefficient table)
The times for all 30 installations are calculated by multiplying first unit of 8 with the unit factor 17.091 which yields 136.73 days.
From the computed number of days, subtract the number of needed for first 20 installations,
Hence, the number of days for final 10 installations is 37.51 days.
Want to see more full solutions like this?
Chapter 7 Solutions
Operations Management (Comp. Instructor's Edition)
- For a time study of a health insurance claims-adjusting process, the analyst uses the continuous method of recording times. The job is divided into four work elements. Shown in Figure are the performance rating factors, RF, and the continuous method recorded times, r, for each work element.a. Calculate the normal time for this job. b. Calculate the standard time for this job, assuming that the allowance is 20 percent of the normal time. c. What is the appropriate sample size for estimating the time for element 2 within {10 percent of the true mean with 95 percent confidence?arrow_forwardThe Scenario: Assume that you are applying for the HR officer position at the HR Department of International School (IS). As part of the assessment, they request you to support the recruitment of 10 lecturers in business administration. Candidates for the lecturer position must possess PhD degrees from English speaking countries and be able to teach in English. Specifically, they ask you to do the following task: Develop a plan for recruitment of the lecturers Write about 400-500 wordsarrow_forwardThe owner of Kat Motel wants to develop a time standard for the task of cleaning a cat cage. In a preliminary study, she observed one of her workers perform this task six times, with the following results: Observation 1 2 3 4 5 6 Time (seconds) 52.7 70 53.3 90.3 80.6 86.7 If the employee performance rating is 1.50, what is the standard time for this task with an allowance of 20 percent of job time is used? seconds.arrow_forward
- Providence Assessment Center screens and trains employees for a computer assembly firm in Boston. The progress of all trainees is tracked, and those not showing the proper progress are moved to less demanding programs. By the tenth repetition, trainees must be able to complete the assembly task in 1 hour or less. Susan has just spent 5 hours on the fourth unit and 4.5 hours completing her eighth unit, while another trainee, Julie took 4 hours on the third and 2.8 hours on the sixth unit. Should you encourage either or both of the trainees to continue? Why? Present calculation steps. [Hint: For each trainee, 1) Determine the learning rate (%) – use doubling concept. 2) Calculate time for the 1st unit (T1) – use table, 3) Calculate time for the 10th Unit (T10) –use table] Susan Julie Learning rate (%) – doubling concept Time for the 1st unit Time for the 10th unitarrow_forward8. A furniture company just completed a work analysis on the total completion time for dying process of handmade dining tables. They have concluded that on average the process takes 27 minutes. However they want to incorporate the performance of the workers and allowance time on this observed value. They think the people they observed was somehow slow, hence they want to use a performance rate of 0.93 and they also want to allow 10% (allow=0.1) of job time. Based on these parameters please calculate the normal and standard time estimates for this process.arrow_forwardA contractor is preparing a bid to install swimming pools at a new housing addition. The estimated time to build the first pool is 35 hours. The contractor estimates an 85 percent learning rate. Without using the computer: a. How long do you estimate the time required to install the second pool? b. How long do you estimate the time required to install the fourth pool?arrow_forward
- An analyst has timed a metal cutting operation for 60 bikes. The average time per cycle was 10.30 minutes, and the standard deviation was 1:20 minutes for a worker with a performance rating of 120 percent. Assume an allowance of 16 percent of job time. Find the standard time for this operation.arrow_forwardTOYS AND JOB DESIGN AT THE HOVEY AND BEARD COMPANY The following is a situation that occurred in the Hovey and Beard Company, as reported by J. V. Clark. This company manufactured a line of wooden toys. One part of the process involved spray painting partially assembled toys, after which the toys were hung on moving hooks that carried them through a drying oven. The operation, staffed entirely by women, was plagued with absenteeism, high turnover, and low morale. Each woman at her paint booth would take a toy from the tray beside her, position it in a fixture, and spray on the color according to the required pattern. She then would release the toy and hang it on the conveyor hook. The rate at which the hooks moved had been calculated so that each woman, once fully trained, would be able to hang a painted toy on each hook before it passed beyond her reach. The women who worked in the paint room were on a group incentive plan that tied their earnings to the…arrow_forwardNonearrow_forward
- The “worker” in this scenario had to perform a candy-sorting task and the rest of the class had to record the observed times (OT) for the task. It was decided that the rating for the “worker” was 100%. Given the following table, find the standard time for each element. Write your answers in order from Element #1 --> Element #5. Answers must have one decimal place: e.g. 3.0 or 12.5. Round up if necessary. Assume a total allowance of 5%. In your equation you will use for ST, consider allowance to be 0.05. Element Trail 1 Trial 2 Standard Time 1 Walk to podium 3 sec 3 sec 2 Fill mug 5 sec 6 sec 3 Walk to desk/sit 5 sec 4 sec 4 Sort Candy 12 sec 12 sec 5 Walk to desk 4 sec 4 secarrow_forwardA job was budgeted to require 5 hours of labor per unit at $11,00 per hour. The job consisted of 7,500 units and was completed in 36,500 hours at a total labor cost of $415,600 What is he total labor cost variance? Multiple Choice $3,100 untevorable. $6,475 unfavorable. $3,375 unfavorable. $620 unfavorable. $7,500 unfavorable.arrow_forwardManagment In the 2-period model, when on-the-job training is firm-specific, 3 The benefit of the training will go to the worker and the cost will go to the firm. a) The cost of the training will go to the worker and the benefit will go to the firm. b) The worker and firm will share the benefit and cost of training. c) The benefit will occur in the first period and the cost will occur in the second period.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.