Operations Management (Comp. Instructor's Edition)
Operations Management (Comp. Instructor's Edition)
13th Edition
ISBN: 9781259948237
Author: Stevenson
Publisher: MCG
Question
Book Icon
Chapter 7.S, Problem 3P

a)

Summary Introduction

To determine: The number of days for first 10 installations.

Introduction: Learning curve is referred as the cost curve, experience curve, efficiency curve or productivity curve. The leaving curve gives information about the cost, efficiency, productivity and performance of an organization.

a)

Expert Solution
Check Mark

Answer to Problem 3P

The number of days for first 10 installations is 56.93 days.

Explanation of Solution

Given information:

Initial unitT1=8daysLearningcurve=85%

Formula:

Tn=T1×Unitfactor

Calculation of number of days for first 10 installations:

At 85% learning curve, and 10 unit number, the unit factor is 7.116 (using learning curve coefficient table)

T110=8×7.116=56.93days (1)

The times for all 10 installations are calculated by multiplying first unit of 8 with the unit factor 7.116 which yields 56.93 days.

Hence, the number of days for first 10 installations is 56.93 days.

b)

Summary Introduction

To determine: The number of days for second 10 installations.

Introduction: Learning curve is referred as the cost curve, experience curve, efficiency curve or productivity curve. The leaving curve gives information about the cost, efficiency, productivity and performance of an organization.

b)

Expert Solution
Check Mark

Answer to Problem 3P

The number of days for second 10 installations is 42.29 days.

Explanation of Solution

Given information:

Initial unitT1=8daysLearningcurve=85%

Formula:

Tn=T1×Unitfactor

Calculation of number of days for second 10 installations:

To calculate the number of days for second 10 installations which is from 11 to 20, the numbers of days of installations for 1 to 20 have to be calculated and then it has to be subtracted from number of days of installations of 1 to 10.

Number of installation of first 20 units:

At 85% learning curve, and 20 unit number, the unit factor is 12.402 (using learning curve coefficient table)

T120=8×12.402=99.22days

The times for all 20 installations are calculated by multiplying first unit of 8 with the unit factor 12.402 which yields 99.22 days.

From the computed number of days, subtract the number of needed for first 10 installations,

Timefor11-20installations=(Timefor1-20installations-Timefor1-10installations)=99.22-56.93=42.29days

Hence, the number of days for second 10 installations is 42.29 days.

c)

Summary Introduction

To determine: The number of days for last 10 installations.

Introduction: Learning curve is referred as the cost curve, experience curve, efficiency curve or productivity curve. The leaving curve gives information about the cost, efficiency, productivity and performance of an organization.

c)

Expert Solution
Check Mark

Answer to Problem 3P

The number of days for last 10 installations is 37.51 days.

Explanation of Solution

Given information:

Initial unitT1=8daysLearningcurve=85%

Formula:

Tn=T1×Unitfactor

Calculation of number of days for last 10 installations:

To calculate the number of days for last10 installations which is from 21 to 30, the numbers of days of installations for 1 to 30 have to be calculated and then it has to be subtracted from number of days of installations of 1 to 20.

Number of installation of first 30 units:

At 85% learning curve, and 30 unit number, the unit factor is 17.091 (using learning curve coefficient table)

T130=8×17.091=136.73days

The times for all 30 installations are calculated by multiplying first unit of 8 with the unit factor 17.091 which yields 136.73 days.

From the computed number of days, subtract the number of needed for first 20 installations,

Timefor21-30installations=(Timefor1-30installations-Timefor1-20installations)=136.73-99.22=37.51days

Hence, the number of days for final 10 installations is 37.51 days.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
The strategy of Multiple Equivalent Simultaneous Offers involves presenting several equally valuable options to the other party during negotiations. This approach benefits negotiators by creating flexibility and increasing the chances of finding a mutually agreeable solution. By offering multiple options, negotiators show that they are open to compromise, which can build trust and make the negotiation process smoother. It also helps avoid getting stuck on one issue, as the other party can choose from several alternatives that meet their needs. In my experience, using MESOs in a work negotiation helped both parties reach an agreement more quickly because each option was carefully thought out to address different needs, and this made it easier for us to settle on one that worked for both sides. This strategy can also reveal what is most important to the other party, helping negotiators understand their priorities better. agree or disagree with the post
Examine the conflicts between improving customer service levels and controlling costs in sales.   Strategies to Balance Both customer service levels and controlling costs in sales 1.Outsourcing and workforce optimization 2. AI-driven customer support
how can you gain trust in a negotiation setting?

Chapter 7 Solutions

Operations Management (Comp. Instructor's Edition)

Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Understanding Management (MindTap Course List)
Management
ISBN:9781305502215
Author:Richard L. Daft, Dorothy Marcic
Publisher:Cengage Learning
Text book image
Management, Loose-Leaf Version
Management
ISBN:9781305969308
Author:Richard L. Daft
Publisher:South-Western College Pub
Text book image
Principles of Management
Management
ISBN:9780998625768
Author:OpenStax
Publisher:OpenStax College
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,