Operations Management (Comp. Instructor's Edition)
Operations Management (Comp. Instructor's Edition)
13th Edition
ISBN: 9781259948237
Author: Stevenson
Publisher: MCG
bartleby

Concept explainers

Question
Book Icon
Chapter 7, Problem 3P

a)

Summary Introduction

To determine: The average cycle time for each operation.

Introduction: The amount of the dependency on human effort by an organization in terms of achieving its goals is given by the work design. It is directly linked to the productivity of an organization where good work design helps in achieving high productivity.

a)

Expert Solution
Check Mark

Explanation of Solution

Given information:

Observation (minutes per cycle)
Element Performance rating 1 2 3 4 5 6
1 90 0.44 0.5 0.43 0.45 0.48 0.46
2 85 1.5 1.54 1.47 1.51 1.49 1.52
3 110 0.84 0.89 0.77 0.83 0.85 0.8
4 100 1.1 1.14 1.08 1.2 1.16 1.26

Calculation of average time per cycle:

Observation (minutes per cycle)
Performance rating 1 2 3 4 5 6 Average time per cycle
90 0.44 0.5 0.43 0.45 0.48 0.46 0.46
85 1.5 1.54 1.47 1.51 1.49 1.52 1.505
110 0.84 0.89 0.77 0.83 0.85 0.8 0.83
100 1.1 1.14 1.08 1.2 1.16 1.26 1.156667

Excel worksheet:

Operations Management (Comp. Instructor's Edition), Chapter 7, Problem 3P , additional homework tip  1

Average time per cycle is calculated by taking average of all cycle in each element which is average of 0.44, 0.5, 0.43, 0.45, 0.48 and 0.46 which gives 0.46 as average time per cycle for element 1 and similar method follows for element 2, 3 and 4.

b)

Summary Introduction

To determine: The normal time for the operation.

b)

Expert Solution
Check Mark

Explanation of Solution

Given information:

Observation (minutes per cycle)
Element Performance rating 1 2 3 4 5 6
1 90 0.44 0.5 0.43 0.45 0.48 0.46
2 85 1.5 1.54 1.47 1.51 1.49 1.52
3 110 0.84 0.89 0.77 0.83 0.85 0.8
4 100 1.1 1.14 1.08 1.2 1.16 1.26

Formula:

NT = Observedtime × PerformRating = OR × PR

Calculation of normal time:

Observation (minutes per cycle)
Element Performance rating 1 2 3 4 5 6 Average time per cycle NT
1 0.9 0.44 0.5 0.43 0.45 0.48 0.46 0.46 0.414
2 0.85 1.5 1.54 1.47 1.51 1.49 1.52 1.505 1.27925
3 1.1 0.84 0.89 0.77 0.83 0.85 0.8 0.83 0.913
4 1 1.1 1.14 1.08 1.2 1.16 1.26 1.156666667 1.156667

Excel worksheet:

Operations Management (Comp. Instructor's Edition), Chapter 7, Problem 3P , additional homework tip  2

Normal time is calculated by multiplying observed timing, 0.46 and performance rating, 0.9 which yields 0.414 minutes for element 1, 2, 3 and 4.

c)

Summary Introduction

To determine: The standard time for the operation.

c)

Expert Solution
Check Mark

Explanation of Solution

Given information:

Observation (minutes per cycle)
Element Performance rating 1 2 3 4 5 6
1 90 0.44 0.5 0.43 0.45 0.48 0.46
2 85 1.5 1.54 1.47 1.51 1.49 1.52
3 110 0.84 0.89 0.77 0.83 0.85 0.8
4 100 1.1 1.14 1.08 1.2 1.16 1.26

Formula:

Standard time = Normal time × Allowance factor = NT × AF

Calculation of standard time:

AF job = 1+A = 1+0.15 = 1.15

Allowance factor is calculated by dividing 1 with difference of 1 and 0.15 which yields 1.15.

Observation (minutes per cycle)
Element Performance rating 1 2 3 4 5 6 Average time per cycle NT Afjob ST
1 0.9 0.44 0.5 0.43 0.45 0.48 0.46 0.46 0.414 1.15 0.4761
2 0.85 1.5 1.54 1.47 1.51 1.49 1.52 1.505 1.27925 1.15 1.471138
3 1.1 0.84 0.89 0.77 0.83 0.85 0.8 0.83 0.913 1.15 1.04995
4 1 1.1 1.14 1.08 1.2 1.16 1.26 1.157 1.157 1.15 1.330167

Excel worksheet:

Operations Management (Comp. Instructor's Edition), Chapter 7, Problem 3P , additional homework tip  3

Standard time for the operation is calculated by multiplying normal time of 0.414 minutes with allowance factor of 1.15 which gives 0.4761 minutes for element 1 and same procedure goes with element 2, 3 and 4.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
This crosstab shows product sub-category sales within categories, broken out by sales quarter. The quarterly values for each sub-category increase within each category, with the largest value at the bottom. Using Running Total as the calculation type, which scope and direction option gives this result?
How do management leaders, in order top meet organizational objectives, modify group behavior by using terms and concepts of diagnose, explain, predict and modify with examples?
Not use ai please

Chapter 7 Solutions

Operations Management (Comp. Instructor's Edition)

Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Management, Loose-Leaf Version
Management
ISBN:9781305969308
Author:Richard L. Daft
Publisher:South-Western College Pub
Text book image
Principles of Management
Management
ISBN:9780998625768
Author:OpenStax
Publisher:OpenStax College
Text book image
Understanding Management (MindTap Course List)
Management
ISBN:9781305502215
Author:Richard L. Daft, Dorothy Marcic
Publisher:Cengage Learning
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Foundations of Business (MindTap Course List)
Marketing
ISBN:9781337386920
Author:William M. Pride, Robert J. Hughes, Jack R. Kapoor
Publisher:Cengage Learning
Text book image
Foundations of Business - Standalone book (MindTa...
Marketing
ISBN:9781285193946
Author:William M. Pride, Robert J. Hughes, Jack R. Kapoor
Publisher:Cengage Learning