OPEARATIONS MANAG.REV CUSTOM 2017
17th Edition
ISBN: 9781323590058
Author: Pearson
Publisher: PEARSON C
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 7.S, Problem 3P
If a plant has an effective capacity of 6,500 and an efficiency of 88%, what is the actual (planned) output?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
If a plant has an effective capacity of 6,500 andan efficiency of 88%, what is the actual (planned) output?
A company has a factory that is designed so that it is most eficient (average unit cost is minimized) when producing 15,000 units of output each month. However, it has an absolute maximum output capability of 17,250 units per month, and can produce as little as 7,000 units per month without corporate headquarters shifting production to another plant. If the factory produces 10,925 units in October, what is the capacity utilization rate in October for this factory?
A company has a factory that is designed so that it is most efi cient (average unit cost is minimized) when producing 15,000 units of output each month. However, it has an absolute maximum output capability of 17,250 units per month, and can produce as little as 7,000 units per month without corporate headquarters shifting production to another plant. If the factory produces 10,925 units in October, what is the capacity utilization rate in October for this factory?
Chapter 7 Solutions
OPEARATIONS MANAG.REV CUSTOM 2017
Ch. 7.S - Prob. 1DQCh. 7.S - Prob. 2DQCh. 7.S - Prob. 3DQCh. 7.S - How is actual, or expected, output computed?Ch. 7.S - Explain why doubling the capacity of a bottleneck...Ch. 7.S - Distinguish between bottleneck time and throughput...Ch. 7.S - Prob. 7DQCh. 7.S - Prob. 8DQCh. 7.S - Prob. 9DQCh. 7.S - Prob. 10DQ
Ch. 7.S - Explain how net present value is an appropriate...Ch. 7.S - Prob. 12DQCh. 7.S - What are the techniques available to operations...Ch. 7.S - Amy Xias plant was designed to produce 7,000...Ch. 7.S - For the past month, the plant in Problem S7.1,...Ch. 7.S - If a plant has an effective capacity of 6,500 and...Ch. 7.S - Prob. 4PCh. 7.S - Material delays have routinely limited production...Ch. 7.S - Prob. 6PCh. 7.S - Southeastern Oklahoma State Universitys business...Ch. 7.S - Under ideal conditions, a service bay at a Fast...Ch. 7.S - A production line at V. J. Sugumarans machine shop...Ch. 7.S - A work cell at Chris Ellis Commercial Laundry has...Ch. 7.S - The three-station work cell Illustrated in Figure...Ch. 7.S - The three-station work cell at Pullman Mfg., Inc....Ch. 7.S - The Pullman Mfg., Inc., three-station work cell...Ch. 7.S - Klassen Toy Company, Inc., assembles two parts...Ch. 7.S - Prob. 15PCh. 7.S - Prob. 16PCh. 7.S - Markland Manufacturing intends to increase...Ch. 7.S - Using the data in Problem S7.17. a. What is the...Ch. 7.S - Given the data in Problem S7.17, at what volume...Ch. 7.S - Janelle Heinke, the owner of HaPeppas!, is...Ch. 7.S - Prob. 21PCh. 7.S - Prob. 22PCh. 7.S - Prob. 23PCh. 7.S - Prob. 24PCh. 7.S - Prob. 25PCh. 7.S - As a prospective owner of a club known as the Red...Ch. 7.S - Prob. 27PCh. 7.S - James Lawsons Bed and Breakfast, in a small...Ch. 7.S - Prob. 29PCh. 7.S - Prob. 30PCh. 7.S - Prob. 31PCh. 7.S - What is the present value of 5,600 when the...Ch. 7.S - Prob. 33PCh. 7.S - Prob. 34PCh. 7.S - Bolds Gym, a health club chain, is considering...Ch. 7.S - Prob. 1VCCh. 7.S - Prob. 2VCCh. 7.S - Prob. 3VCCh. 7 - What is process strategy?Ch. 7 - Prob. 2DQCh. 7 - Prob. 3DQCh. 7 - What is process redesign?Ch. 7 - Prob. 5DQCh. 7 - Name the tour quadrants of the service process...Ch. 7 - Prob. 7DQCh. 7 - Prob. 8DQCh. 7 - Identify manufacturing firms that compete on each...Ch. 7 - Identify the competitive advantage of each of the...Ch. 7 - Prob. 11DQCh. 7 - Identify the competitive advantage of each of the...Ch. 7 - Prob. 13DQCh. 7 - Prob. 14DQCh. 7 - Prob. 15DQCh. 7 - Explain what a flexible manufacturing system (FMS)...Ch. 7 - Prob. 17DQCh. 7 - Prepare a flowchart tor one of the following: a....Ch. 7 - Prob. 2PCh. 7 - Prepare a time-function map for one of the...Ch. 7 - Prepare a service blueprint for one of the...Ch. 7 - Prob. 5PCh. 7 - Prob. 6PCh. 7 - Prob. 7PCh. 7 - Prob. 8PCh. 7 - Prob. 9PCh. 7 - Ski Boards, Inc., wants to enter the market...Ch. 7 - Prob. 11PCh. 7 - Prob. 12PCh. 7 - Using Figure 7.6 in the discussion of value-stream...Ch. 7 - Metters Cabinets, Inc., needs to choose a...Ch. 7 - Rochester Manufacturings Process Decision...Ch. 7 - Prob. 2CSCh. 7 - Prepare the case for an optimistic sales manager...Ch. 7 - Prob. 1.1VCCh. 7 - Prob. 1.2VCCh. 7 - Prob. 1.3VCCh. 7 - Prob. 1.4VCCh. 7 - Prob. 2.1VCCh. 7 - Prob. 2.2VCCh. 7 - Process Strategy at Wheeled Coach Video Case Video...Ch. 7 - Prob. 2.4VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- A biotech firm is considering abandoning its old plant, built 23 years ago, andconstructing a new facility that has 50% more square footage. The original cost of the old facility was $300,000, and its capacity in terms of standardizedproduction units is 250,000 units per year. The capacity of the new laboratoryis to be 400,000 units per year. During the past 23 years, costs of laboratoryconstruction have risen by an average of 5% per year. If the cost-capacity factor, based on square footage, is 0.80, what is the estimated cost of the newlaboratory?arrow_forwardAn executive conference center has the physical ability to handle 1,100 participants. However, conference management personnel believe that only 1,000 participants can be handled effectively for most events. The last event, although forecasted to have 1,000 participants, resulted in the attendance of only 950 participants. What are the utilization and efficiency of the conference facility?arrow_forwardA company has a factory that is designed so that it is most efficient (average unit cost is minimized) when producing 28,500 units of output each month. However, it has an absolute maximum output capability of 35,000 units per month, and can produce as little as 7,000 units per month without corporate headquarters shifting production to another plant. If the factory produces 22,120 units in October, what is the capacity utilization rate in October for this factory? (Round your answer to 1 decimal place.)arrow_forward
- A manufacturer of ballet shoes has determined that its production facility has a design capacity of 300 shoes per week. Theeffective capacity, however, is 230 shoes per week. What is themanufacturer’s capacity utilization relative to both design andeffective capacity if output is 200 shoes per week?arrow_forwardWhy would an organization want to reduce its capacity?arrow_forwardExplain capacity planning concepts with examples ?arrow_forward
- A computer repair service has a design capacity of 80 repairs per day. Its effective capacity, however, is 64 repairs per day, and its actual output is 62 repairs per day. The manager would like to increase the number of repairs per day. Which of the following factors should the manager investigate: quality problems, absenteeism, or scheduling and balancing? Explain .arrow_forwardEstimate the cost of a 0.75 million gallon per day (MGD) induced-draft packed tower for air-stripping trihalomethanes from drinking water if the cost for a 2.9-MGD tower is $153,200. The exponent in the cost-capacity equation is 0.47. The cost of a 0.75 million gallon per day induced-draft packed tower is $arrow_forwardExplain Capacity Planning Concepts with an example?arrow_forward
- Define: output, design capacity, effective capacity, utilization % and efficiency %?arrow_forwardUnder what circumstances would a company want its capacity to go from lagging to leading demand?arrow_forwardIdentify the process's existing capacity and determining whether the process's present capacity cushion is adequate ?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY