Question
Book Icon
Chapter 7.S, Problem 15P

a)

Summary Introduction

To determine: The bottleneck operation.

Bottleneck time:

The bottleneck time of the system is the process in the system that takes the most amount of time to complete its activity. The bottleneck time will reduce the overall efficiency of the system.

b)

Summary Introduction

To determine: The bottleneck time of the bottleneck operation.

Bottleneck time:

The bottleneck time of the system is the process in the system that takes the most amount of time to complete its activity. The bottleneck time will reduce the overall efficiency of the system.

c)

Summary Introduction

To determine: The throughput time of the overall system.

Throughput time:

The throughput time of a system is the time taken for a product to pass from the raw materials stage to the finished goods stage. The higher the throughput time, the more efficient the system will be.

d)

Summary Introduction

To determine: The monthly capacity of the manufacturing process.

Bottleneck time:

The bottleneck time of the system is the process in the system that takes the most amount of time to complete its activity. The bottleneck time will reduce the overall efficiency of the system.

Monthly capacity:

The monthly capacity is the number of units the firm is able to produce in a month’s time. It will be calculated taking into consideration the resources and constraints present in the manufacturing process.

Blurred answer
Students have asked these similar questions
Refer to Table S6.1 - Factors for Computing Control Chart Limits (3 sigma) for this problem. Sampling 4 pieces of precision-cut wire (to be used in computer assembly) every hour for the past 24 hours has produced the following results: Hour x R Hour R Hour x R Hour x R 1 3.15" 0.71" 7 3.15" 0.53" 13 3.11" 0.80" 19 3.31" 1.56" 2 3.10 1.13 8 2.75 1.13 14 2.93 1.36 20 2.99 1.14 3 3.22 1.48 9 3.12 0.71 15 3.02 1.06 21 2.75 1.08 4 3.39 1.21 10 2.95 5 3.17 1.12 11 2.93 6 2.96 0.32 12 3.07 1.33 16 1.22 17 2.76 0.35 18 2.74 1.29 2.74 0.45 22 3.28 0.46 1.38 23 2.84 1.58 24 2.64 0.97 Based on the sampling done, the control limits for 3-sigma x chart are (round all intermediate calculations to three decimal places before proceeding with further calculations): Upper Control Limit (UCL) = inches (round your response to three decimal places).
Which of the following aspects of a person’s personal life seem to make them more suited to becoming a counselor?   All of the above   a natural interest in people   the ability to listen   introspection
The need of a strategy for an organization is to develop a sound and equitable:   manipulation policy   labor agreement   compensation strategy   discriminatory practice   customer profile

Chapter 7 Solutions

OPEARATIONS MANAG.REV CUSTOM 2017

Ch. 7.S - Explain how net present value is an appropriate...Ch. 7.S - Prob. 12DQCh. 7.S - What are the techniques available to operations...Ch. 7.S - Amy Xias plant was designed to produce 7,000...Ch. 7.S - For the past month, the plant in Problem S7.1,...Ch. 7.S - If a plant has an effective capacity of 6,500 and...Ch. 7.S - Prob. 4PCh. 7.S - Material delays have routinely limited production...Ch. 7.S - Prob. 6PCh. 7.S - Southeastern Oklahoma State Universitys business...Ch. 7.S - Under ideal conditions, a service bay at a Fast...Ch. 7.S - A production line at V. J. Sugumarans machine shop...Ch. 7.S - A work cell at Chris Ellis Commercial Laundry has...Ch. 7.S - The three-station work cell Illustrated in Figure...Ch. 7.S - The three-station work cell at Pullman Mfg., Inc....Ch. 7.S - The Pullman Mfg., Inc., three-station work cell...Ch. 7.S - Klassen Toy Company, Inc., assembles two parts...Ch. 7.S - Prob. 15PCh. 7.S - Prob. 16PCh. 7.S - Markland Manufacturing intends to increase...Ch. 7.S - Using the data in Problem S7.17. a. What is the...Ch. 7.S - Given the data in Problem S7.17, at what volume...Ch. 7.S - Janelle Heinke, the owner of HaPeppas!, is...Ch. 7.S - Prob. 21PCh. 7.S - Prob. 22PCh. 7.S - Prob. 23PCh. 7.S - Prob. 24PCh. 7.S - Prob. 25PCh. 7.S - As a prospective owner of a club known as the Red...Ch. 7.S - Prob. 27PCh. 7.S - James Lawsons Bed and Breakfast, in a small...Ch. 7.S - Prob. 29PCh. 7.S - Prob. 30PCh. 7.S - Prob. 31PCh. 7.S - What is the present value of 5,600 when the...Ch. 7.S - Prob. 33PCh. 7.S - Prob. 34PCh. 7.S - Bolds Gym, a health club chain, is considering...Ch. 7.S - Prob. 1VCCh. 7.S - Prob. 2VCCh. 7.S - Prob. 3VCCh. 7 - What is process strategy?Ch. 7 - Prob. 2DQCh. 7 - Prob. 3DQCh. 7 - What is process redesign?Ch. 7 - Prob. 5DQCh. 7 - Name the tour quadrants of the service process...Ch. 7 - Prob. 7DQCh. 7 - Prob. 8DQCh. 7 - Identify manufacturing firms that compete on each...Ch. 7 - Identify the competitive advantage of each of the...Ch. 7 - Prob. 11DQCh. 7 - Identify the competitive advantage of each of the...Ch. 7 - Prob. 13DQCh. 7 - Prob. 14DQCh. 7 - Prob. 15DQCh. 7 - Explain what a flexible manufacturing system (FMS)...Ch. 7 - Prob. 17DQCh. 7 - Prepare a flowchart tor one of the following: a....Ch. 7 - Prob. 2PCh. 7 - Prepare a time-function map for one of the...Ch. 7 - Prepare a service blueprint for one of the...Ch. 7 - Prob. 5PCh. 7 - Prob. 6PCh. 7 - Prob. 7PCh. 7 - Prob. 8PCh. 7 - Prob. 9PCh. 7 - Ski Boards, Inc., wants to enter the market...Ch. 7 - Prob. 11PCh. 7 - Prob. 12PCh. 7 - Using Figure 7.6 in the discussion of value-stream...Ch. 7 - Metters Cabinets, Inc., needs to choose a...Ch. 7 - Rochester Manufacturings Process Decision...Ch. 7 - Prob. 2CSCh. 7 - Prepare the case for an optimistic sales manager...Ch. 7 - Prob. 1.1VCCh. 7 - Prob. 1.2VCCh. 7 - Prob. 1.3VCCh. 7 - Prob. 1.4VCCh. 7 - Prob. 2.1VCCh. 7 - Prob. 2.2VCCh. 7 - Process Strategy at Wheeled Coach Video Case Video...Ch. 7 - Prob. 2.4VC
Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
  • Text book image
    Practical Management Science
    Operations Management
    ISBN:9781337406659
    Author:WINSTON, Wayne L.
    Publisher:Cengage,
    Text book image
    Marketing
    Marketing
    ISBN:9780357033791
    Author:Pride, William M
    Publisher:South Western Educational Publishing
    Text book image
    MARKETING 2018
    Marketing
    ISBN:9780357033753
    Author:Pride
    Publisher:CENGAGE L
  • Text book image
    Purchasing and Supply Chain Management
    Operations Management
    ISBN:9781285869681
    Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
    Publisher:Cengage Learning
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Marketing
Marketing
ISBN:9780357033791
Author:Pride, William M
Publisher:South Western Educational Publishing
Text book image
MARKETING 2018
Marketing
ISBN:9780357033753
Author:Pride
Publisher:CENGAGE L
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning