EP PRIN.OF OPERATIONS MGMT.-MYOMLAB
10th Edition
ISBN: 9780134183848
Author: HEIZER
Publisher: PEARSON CO
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 7.S, Problem 11P
The three-station work cell illustrated in Figure S7.7 has a product that must go through one of the two machines at station l (they are parallel) before proceeding to station 2.
Figure S7.7
a) What is the bottleneck time of the system?
b) What is the bottleneck station of this work cell?
c) What is the throughput time?
d) If the firm operates 10 hours per day, 5 days per week, what the weekly capacity of this work cell?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Please do not give solution in image format thanku
The three-station work cell at Pullman Mfg., Inc.is illustrated in Figure S7.8. It has two machines a t station I inparallel (i.e., the product needs to go through only one of the twomachines before proceeding to station 2). a) What is the throughput time of this work cell?b) What is the bottleneck time of this work cell?c) What is the bottleneck station?d) If the firm operates 8 hours per day, 6 days per week, what isthe weekly capacity of this work cell?
part d
Chapter 7 Solutions
EP PRIN.OF OPERATIONS MGMT.-MYOMLAB
Ch. 7.S - Prob. 1DQCh. 7.S - Prob. 2DQCh. 7.S - Prob. 3DQCh. 7.S - Prob. 4DQCh. 7.S - Prob. 5DQCh. 7.S - Distinguish between bottleneck time and throughput...Ch. 7.S - Prob. 7DQCh. 7.S - Prob. 8DQCh. 7.S - Prob. 9DQCh. 7.S - Prob. 10DQ
Ch. 7.S - Prob. 11DQCh. 7.S - Prob. 12DQCh. 7.S - What are the techniques available to operations...Ch. 7.S - Amy Xias plant was designed to produce 7,000...Ch. 7.S - For the post month, the plant in Problem S7.1,...Ch. 7.S - Prob. 3PCh. 7.S - Prob. 4PCh. 7.S - Prob. 5PCh. 7.S - The effective capacity and efficiency for the next...Ch. 7.S - Southeastern Oklahoma State Universitys business...Ch. 7.S - Prob. 8PCh. 7.S - Prob. 9PCh. 7.S - Prob. 10PCh. 7.S - The three-station work cell illustrated in Figure...Ch. 7.S - The three-station work cell at Pullman Mfg., Inc....Ch. 7.S - The Pullman Mfg., Inc., three-station work cell...Ch. 7.S - Prob. 14PCh. 7.S - 10 minutes per unit. Part 2 is simultaneously...Ch. 7.S - Prob. 16PCh. 7.S - Prob. 17PCh. 7.S - Using the data in Problem S7.17: a) What is the...Ch. 7.S - Prob. 19PCh. 7.S - Prob. 20PCh. 7.S - Prob. 21PCh. 7.S - Prob. 22PCh. 7.S - Prob. 23PCh. 7.S - Prob. 24PCh. 7.S - Prob. 25PCh. 7.S - Prob. 26PCh. 7.S - Prob. 27PCh. 7.S - Prob. 32PCh. 7.S - Prob. 33PCh. 7.S - Prob. 34PCh. 7.S - Prob. 35PCh. 7.S - Prob. 36PCh. 7.S - Prob. 37PCh. 7.S - Prob. 38PCh. 7.S - Prob. 39PCh. 7.S - Prob. 1VCCh. 7.S - a capacity expansion plan and a new 11-story...Ch. 7.S - a capacity expansion plan and a new 11-story...Ch. 7 - Ethical Dilemma For the sake of efficiency and...Ch. 7 - Prob. 1DQCh. 7 - Prob. 2DQCh. 7 - Prob. 3DQCh. 7 - Prob. 4DQCh. 7 - Prob. 5DQCh. 7 - Prob. 6DQCh. 7 - Prob. 7DQCh. 7 - Prob. 8DQCh. 7 - Prob. 9DQCh. 7 - Prob. 10DQCh. 7 - Prob. 11DQCh. 7 - Prob. 12DQCh. 7 - Prob. 13DQCh. 7 - Prob. 14DQCh. 7 - Prob. 15DQCh. 7 - Prob. 16DQCh. 7 - Prob. 17DQCh. 7 - Prob. 18DQCh. 7 - Prob. 19DQCh. 7 - Prob. 1PCh. 7 - Usingthedatain Problem 7.1, determinethemost...Ch. 7 - Prob. 3PCh. 7 - Refer to Problem 7.1. If a contract for the second...Ch. 7 - Stan Fawcetts company is considering producing a...Ch. 7 - Prob. 6PCh. 7 - Prob. 7PCh. 7 - Prob. 8PCh. 7 - Metters Cabinets, Inc., needs to choose a...Ch. 7 - Prob. 10PCh. 7 - Nagle Electric. Inc., of Lincoln, Nebraska, must...Ch. 7 - Stapleton Manufacturing intends to increase...Ch. 7 - Prepare a flowchart for one of the following: a)...Ch. 7 - Prepare a process chart for one of the activities...Ch. 7 - Prob. 15PCh. 7 - Prob. 16PCh. 7 - Prob. 17PCh. 7 - Prob. 1CSCh. 7 - Prob. 2CSCh. 7 - Prob. 3CSCh. 7 - Process Strategy at Wheeled Coach Wheeled Coach,...Ch. 7 - Prob. 1.2VCCh. 7 - Prob. 1.3VCCh. 7 - Prob. 1.4VCCh. 7 - Alaska Airlines: 20-Minute Baggage...Ch. 7 - Prob. 2.2VCCh. 7 - Prob. 2.3VCCh. 7 - Prob. 2.4VCCh. 7 - Prob. 2.5VCCh. 7 - Prob. 3.1VCCh. 7 - Prob. 3.2VCCh. 7 - Prob. 3.3VCCh. 7 - Prob. 3.4VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- b) What is the bottleneck time of this work cell? c) What is the bottleneck station? d) If the firm operates 8 hours per day, 6 days per week, what isthe weekly capacity of this work cell?arrow_forwardThe Pullman Mfg., Inc. three-station work cell illustrated in the figure below has two machines at station 1 in parallel. (The product needs to go through only one of the two machines before proceeding to station 2.) 12 min/unit Station 1 Machine A Station 1 Machine B 12 min/unit Station 2 4 min/unit The manager, Seimone Hartley, has asked you to evaluate the system if she adds a parallel machine at station 3. a) The throughput time of the new work cell is 26 minutes (enter your response as a whole number). b) The bottleneck time of the new work cell is minutes per unit (enter your response as a whole number). Station 3 10 min/unitarrow_forwardSuper Fun Industries manufactures four top-selling toys code-named A-148, B-356, B-457, and C-843. The following table shows how long it takes to process each toy through each required station. Note that all times are in minutes. Super Fun's manufacturing plant is open 12 hours a day, 5 days a week, and 8 hours on Saturday. b. If weekly demand for the four products are A-148=180 units, B-356=310 units, B-457=280 units, and C-843=300 units, which station is the bottleneck, and is it capable of producing all the toys demanded? The bottleneck for Super Fun Industries is ▼ Station 1 Station 2 Station 3 Station 4 , with a utilization of ______%. (Enter your response rounded to one decimal place.)arrow_forward
- A work cell at Chris Ellis Commercial Laundryhas a workstation with two machines, and each unit producedat the station needs to be processed by both of the machines.(The same unit cannot be worked on by both machines simultaneously.) Each machine has a production capacity of 4units per hour. What is the throughput time of the work cell?arrow_forwardThe three-station work cell illustrated in the figure below has a product that must go through one of the two machines at station 1 (they are parallel) before proceeding to station 2. Capacity: 20 units/hr Station 1 Machine A Station 2 Station 3 Station 1 Сарacity: Сарacity: Machine B 5 units/hr 10 units/hr Capacity: 20 units/hr a) The bottleneck time of the system is minutes per unit (enter your response as a whole number). b) V is the bottleneck station. c) The throughput time is minutes (enter your response as a whole number). d) If the firm operates 11 hours per day, 5 days per week, the weekly capacity of this work cell is units (enter your response as a whole number).arrow_forwardA work cell at Chris Ellis Commercial Laundry hasa workstation with two machines, and each unit produced at thestation needs to be processed by both of the machines. (The sameunit cannot be worked on by both machines simultaneously.)Each machine has a production capacity of 4 un its per hour.What is the throughput time of the work cell?arrow_forward
- The Pullman Mfg., Inc. three-station work cell illustrated in the figure below has two machines at station 1 in parallel. (The product needs to go through only one of the two machines before proceeding to station 2.) SEE PICTURE Answer Carrow_forwardThe Pullman Mfg., Inc. three-station work cell illustrated in the figure below has two machines at station 1 in parallel. (The product needs to go through only one of the two machines before proceeding to station 2.) Station 1 Machine A Capacity: 3 Units/hr Station 2 Station 3 Capacity: 6 Units/hr Capacity 5 Units/hr Station 1 Machine B Capacity: 3 Units/hr The manager, Mr. Heisler, has asked you to evaluate the system if she adds a parallel machine at station 2. What is the bottleneck time of the new work cell? (enter your response as a whole number). 12 minutes 6 minutes 10 minutes 20 minutesarrow_forwardFigure 9.22 illustrates an architect's drawing of Arnold PalmerHospital's new circular pod system. If nurse Susan Jones's dayincludes 7 trips from the nursing pod to each of the 12 rooms(back and forth), 20 trips to central medical supply, 6 trips tothe break room, and 12 trips to the pod linen supply, how many miles does she walk during her shift? What are the differences in the travel times between the two nurses for this random day?arrow_forward
- A city would like to know how many vehicles it could move through its streets in an emergency. The most likely situation is an evacuation starting at the school and ending at the park. The connections between these two locations, plus their capacity and direction, is shown below. Oak Street 1" Street School Park B Flm Street 2 Street E Path A B D. E Capacity 15 15 30 10 5 5 30 (Round your answer to the nearest whole number.) Maximum Flowarrow_forwardThe three-station work cell illustrated in Figure S7.7has a product that must go through one of the two machines atstation 1 (they are parallel) before proceeding to station 2. a) What is the bottleneck time of the system?b) What is the bottleneck station of this work cell?c) What is the throughput time?d) If the firm operates 10 hours per day, 5 days per week, what isthe weekly capacity of this work cell?arrow_forwardCompute the capacity (i.e. processing rate) for each of the following scenarios. Convertyour answers to parts per hour.a. A four-station line with single-machine stations, where the average processing timesare 15, 20, 10 and 12 minutes, respectively.b. A three-station line where the number of machines at stations 1, 2 and 3 is 2, 6, and3, respectively; and the average processing times are 10, 24 and 18 minutes,respectively.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY