Calculate number of painters that will require painting the house in 6 days.
Answer to Problem 62SR
Contractor will need 96 painters to paint a house in 6 days.
Explanation of Solution
Given:
Unit of measure = 24 person-days
Calculations:
According to contractors estimate, it will require 24 persons to paint a house in 24 days.
Now, we have to calculate number of painters require to paint house in 6 days.
Let the number of painters require to paint house be x.
Conclusion:
Therefore, contractor will need 96 persons to complete painting a house in 6 days.
Chapter 7 Solutions
Pre-Algebra Student Edition
Additional Math Textbook Solutions
Differential Equations and Linear Algebra (4th Edition)
College Algebra
Linear Algebra with Applications (9th Edition) (Featured Titles for Linear Algebra (Introductory))
College Algebra with Modeling & Visualization (5th Edition)
College Algebra
Intermediate Algebra (7th Edition)
- Algebra and Trigonometry (6th Edition)AlgebraISBN:9780134463216Author:Robert F. BlitzerPublisher:PEARSONContemporary Abstract AlgebraAlgebraISBN:9781305657960Author:Joseph GallianPublisher:Cengage LearningLinear Algebra: A Modern IntroductionAlgebraISBN:9781285463247Author:David PoolePublisher:Cengage Learning
- Algebra And Trigonometry (11th Edition)AlgebraISBN:9780135163078Author:Michael SullivanPublisher:PEARSONIntroduction to Linear Algebra, Fifth EditionAlgebraISBN:9780980232776Author:Gilbert StrangPublisher:Wellesley-Cambridge PressCollege Algebra (Collegiate Math)AlgebraISBN:9780077836344Author:Julie Miller, Donna GerkenPublisher:McGraw-Hill Education