Chapter 7, Problem 1P
Summary Introduction
To determine: The standard time for the operation.
Introduction: The amount of the dependency on human effort by an organization in terms of achieving its goals is given by the work design. It is directly linked to the productivity of an organization where good work design helps in achieving high productivity.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
An analyst has timed a metal cutting operation for 60 bikes. The average time per cycle was 10.30 minutes, and the standard deviation was 1:20 minutes for a worker with a performance rating of 120 percent. Assume an allowance of 16 percent of job time. Find the standard time for this operation.
help
please
Susan Cottenden clocked the observed time for weld-ing a part onto truck doors at 5.3 minutes. The performance rat-ing of the worker timed was estimated at 105%. Find the normal
time for this operation.Note: According to the local union contract, each welder isallowed 3 minutes of personal time per hour and 2 minutes offatigue time per hour. Further, there should be an average delayallowance of 1 minute per hour. Compute the allowance factorand then find the standard time for the welding activity.
Chapter 7 Solutions
OPERATIONS MANAGEMENT CONNECT AC
Ch. 7.S - Prob. 1DRQCh. 7.S - Prob. 2DRQCh. 7.S - Prob. 3DRQCh. 7.S - Prob. 4DRQCh. 7.S - Prob. 5DRQCh. 7.S - Prob. 6DRQCh. 7.S - Prob. 7DRQCh. 7.S - Prob. 8DRQCh. 7.S - Prob. 9DRQCh. 7.S - Prob. 10DRQ
Ch. 7.S - Prob. 1PCh. 7.S - Prob. 2PCh. 7.S - Prob. 3PCh. 7.S - Prob. 4PCh. 7.S - Prob. 5PCh. 7.S - Prob. 6PCh. 7.S - Prob. 7PCh. 7.S - Prob. 8PCh. 7.S - Prob. 9PCh. 7.S - Prob. 10PCh. 7.S - Prob. 11PCh. 7.S - Prob. 12PCh. 7.S - Prob. 13PCh. 7.S - Prob. 14PCh. 7.S - Prob. 15PCh. 7.S - Prob. 16PCh. 7.S - Prob. 17PCh. 7.S - Prob. 18PCh. 7.S - Prob. 19PCh. 7.S - Prob. 1CQCh. 7.S - Prob. 2CQCh. 7.S - Prob. 3CQCh. 7 - Prob. 1DRQCh. 7 - What are some of the main advantage and...Ch. 7 - Prob. 3DRQCh. 7 - Prob. 4DRQCh. 7 - Prob. 5DRQCh. 7 - Prob. 6DRQCh. 7 - Prob. 7DRQCh. 7 - What are motion study principles? How are they...Ch. 7 - Prob. 9DRQCh. 7 - Prob. 10DRQCh. 7 - Prob. 11DRQCh. 7 - Prob. 12DRQCh. 7 - Prob. 13DRQCh. 7 - Prob. 14DRQCh. 7 - Prob. 15DRQCh. 7 - Prob. 16DRQCh. 7 - Prob. 17DRQCh. 7 - Prob. 18DRQCh. 7 - Prob. 19DRQCh. 7 - Prob. 1TSCh. 7 - Prob. 2TSCh. 7 - Prob. 3TSCh. 7 - Prob. 1CTECh. 7 - Prob. 2CTECh. 7 - Prob. 1PCh. 7 - Prob. 2PCh. 7 - Prob. 3PCh. 7 - Given these observed times (in minutes) for four...Ch. 7 - Prob. 5PCh. 7 - Prob. 6PCh. 7 - Prob. 7PCh. 7 - Prob. 8PCh. 7 - Prob. 9PCh. 7 - Prob. 10PCh. 7 - Prob. 11PCh. 7 - Prob. 12PCh. 7 - Prob. 13PCh. 7 - An analyst made the following observations about...Ch. 7 - Prob. 15PCh. 7 - Prob. 16PCh. 7 - Prob. 17PCh. 7 - Prob. 18PCh. 7 - Prob. 19P
Knowledge Booster
Similar questions
- An analyst has timed a metal-cutting operation for 50 cycles. The average time per cycle was10.40 minutes, and the standard deviation was 1.20 minutes for a worker with a performance ratingof 125 percent. Assume an allowance of 16 percent of job time. Find the standard time for thisoperationarrow_forwardFrom a time study, the worker’s average observed time for a particular task is shown to be 5.6 minutes. The analyst feels the worker was performing their task, on average, about 25% faster than normal. What would be the resulting standard time assuming a 20% allowance for fatigue and personal needs?arrow_forwardA worker-machine operation was found to involve 3.3 minutes of machine time per cycle in the course of 40 cycles of stopwatch study. The worker’s time averaged 1.9 minutes per cycle, and the worker was given a rating of 120 percent (machine rating is 100 percent). Midway through the study, the worker took a 10-minute rest break. Assuming an allowance factor of 12 percent of work time, determine the standard time for this job.arrow_forward
- A worker-machine operation was found to involve 3.3 minutes of machine time per cycle in the course of 40 cycles of stopwatch study. The worker's time-averaged 1.9 minutes per cycle, and the worker was given a rating of 120% (machine rating is 100%). Midway through the study, the worker took a 10-minute rest break. Assuming an allowance factor of 12% of work time, determine the standard time for this job. Hints: you should consider both machine time and machine time together. Also, Allowance only applies to the man, not a machine.arrow_forwardYou want to know the standard time of a welding process. The analyst has obtained the followingi information: average timed time - 1.30 minutes rhythm assessment - 110 fixed supplements - 5% variable supplements - 2% Determine the standard time, in minutes, of the welding process: a) 143 min b) 145 min c) 150 min d) 153 minarrow_forwardA recently negotiated union contract allows workers in a shipping department 24 minutes for rest, 10 minutes for personal time, and 14 minutes for delays for each four hours worked. A time study analyst observed a job that is performed continuously and found an average time of 6.0 minutes percycle for a worker she rated at 95 percent. What standard time is applicable for that operation?arrow_forward
- The snapback timing method was used to obtain the average times and performance ratings for work elements in a manual repetitive task. (See table below). All elements are worker-controlled and were performance rated at 80%. Element e is an irregular element performed every five cycles. A 15% allowance for personal time, fatigue, and delays isapplied to the cycle. Determine (a) the normal time and (b) the standard time for this cycle. If the worker’s performance during actual production is 120% on all manual elements for 7 actual hours worked on an 8-hour shift, (c) how many units will be producedarrow_forwardA Methods and Measurements Analyst needs to develop a time standard for a certain task. The task involves use of a ruler, square, and portable electric saw to mark and cut the "notch" in a rafter (a standard carpentry task of home construction). In a preliminary study, he observed one of his workers performing this task five times. The observations were made in an air-conditioned, well-lit training facility, at ground level, with all tools and equipment clean and readily available. Observation: 1 2 3 4 5 Task time (seconds): 82 74 80 83 76 a. What is the actual average time for this task? b. What is the normal time for this task if the employee worked at a 20% faster pace than is typical for adequately trained workers? c. What is standard time for this task if allowances sum to 14%? d. If the analyst then thought more carefully about his experiment and decided that the allowances needed to be increased to match the real (outside, not air-conditioned)…arrow_forwardAt Dominos pizza the time study restaurant yielded an average observed time of 4.0 minutes. The analyst rates the observed worker at 85%.this means the worker performed at 85% of normal when the study was made. The firm uses a 13% allowance factor. What is the standard time for this operation. 9.3 min 3.4 min ✓ 3.9 min 3.8 minarrow_forward
- Susan Cottenden clocked the observed time for welding a part onto truck doors at 5.3 minutes. The performance rating of the worker timed was estimated at I 05%. Find the normal time for this operation. Note: According to the local union contract, each welder isallowed 3 mi nutes of personal time per hour and 2 minutes offatigue time per hour. Further, there should be an average delayallowance of I minute per hour. Compute the allowance factorand then find the standard time for the welding activity.arrow_forwardThe owner of Touchdown Sports Bar wants to develop a time standard for the task of mixing a specialty cocktail. In a preliminary study, he observed one of his bartenders perform this task seven times with an average of 90 seconds and a standard deviation of five seconds. What is the standard time for this task if the bartender worked at a 20 percent faster pace than is average, and an allowance of 10 percent of job time is used?arrow_forwardA job was timed for 60 cycles and had an average of 1.25 minutes per piece. The performance rating was 95 percent, and workday allowances are 9 percent. Determine each of the following: a. Observed time. (Round your answer to 2 decimal place.) Observed time minutes b. Normal time. (Round your answer to 2 decimal places.) Normal time minutes c. Standard time. (Round your answer to 2 decimal places.) Standard time minutesarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.