MyLab Operations Management with Pearson eText -- Access Card -- for Operations Management: Processes and Supply Chains
12th Edition
ISBN: 9780134742366
Author: Lee J. Krajewski, Manoj K. Malhotra, Larry P. Ritzman
Publisher: PEARSON
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 7, Problem 15P
Table 7.8 contains data for the installation of new equipment in a manufacturing process at Excello Corporation. Your company is responsible for the installation project. Indirect costs are $15,000 per week, and a penalty cost of $9,000 per week will be incurred by your company for every week the project is delayed beyond week 9.
- What is the shortest time duration for this project regardless of cost?
- What is the minimum total cost associated with completing the project in 9 weeks?
- What is the total time of the minimum-cost
schedule ?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
please answer all parts of the question within 30 minutes.
You are the project manager of the software installation project in Table. You would like to find the minimum- cost schedule for your project. There is a $1,000-per-week penalty for each week the project is delayed beyond week 25. In addition, your project team determined that indirect project costs are $2,500 per week. a. What would be your target completion week? b. How much would you save in total project costs with your schedule?
The table below contains data for the installation of new equipment in a manufacturing process for a steel corporation. Your company is responsible for the installation project. Indirect costs are $6,000 per week, and a penalty cost of $10,000 per week will be incurred by your company for every week the project is delayed beyond week 15.
Activity
Immediate
Predecessor(s)
Normal Time (weeks)
Crash Time (weeks)
Normal Cost ($)
Crash Cost ($)
A
None
2
1
7,000
10,000
B
None
2
2
3,000
3,000
C
A
3
1
12,000
40,000
D
B
3
2
12,000
28,000
E
C
1
1
8,000
8,000
F
D, E
5
3
5,000
15,000
G
E
3
2
9,000
18,000
H
F, G
8
6
14,000
32,000
Construct a network diagram for the project.
What are the project completion time and the total cost under normal conditions?
What is the shortest time duration for this project regardless of cost? What is the resulting total cost?
What is the…
Chapter 7 Solutions
MyLab Operations Management with Pearson eText -- Access Card -- for Operations Management: Processes and Supply Chains
Ch. 7 - One of your colleagues comments that software is...Ch. 7 - Explain how to determine the slack for each...Ch. 7 - Define risk as it applies to projects. What are...Ch. 7 - Consider the following data for a project to...Ch. 7 - The following information is known about a project...Ch. 7 - A project for improving a billing process has the...Ch. 7 - Prob. 4PCh. 7 - Prob. 5PCh. 7 - Consider the following information for a project...Ch. 7 - Consider the following data for a project to...
Ch. 7 - Paul Silver, owner of Sculptures International,...Ch. 7 - Prob. 9PCh. 7 - The following information concerns a project to...Ch. 7 - Consider a project to produce custom door moldings...Ch. 7 - Table 7.5 contains information about au...Ch. 7 - The Advanced Tech Company has a project to design...Ch. 7 - Prob. 14PCh. 7 - Table 7.8 contains data for the installation of...Ch. 7 - The diagram in Figure 7.12 was developed for the...Ch. 7 - Prob. 17PCh. 7 - Prob. 18PCh. 7 - You are the project manager of the software...Ch. 7 - Jordanne King, the project manager for Webjets...Ch. 7 - Recently, you were assigned to manage a project to...Ch. 7 - In Solved Problem 2, estimate the probability that...Ch. 7 - The director of continuing education at Bluebird...Ch. 7 - Gabrielle Kramer, owner of Pet Paradise, is...Ch. 7 - The project manager of Good Public Relations...Ch. 7 - Consider the office renovation project data in...Ch. 7 - Activity B and activity K are critical activities....Ch. 7 - Prob. 2AMECh. 7 - Prob. 3AMECh. 7 - Prob. 4AMECh. 7 - Prob. 5AMECh. 7 - Assess the four categories of a risk-management...Ch. 7 - Prob. 2VCCh. 7 - Assume you are Denise Tower and have...Ch. 7 - Prob. 1CCh. 7 - Prob. 2CCh. 7 - Prob. 3CCh. 7 - Prob. 4C
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Farihah is a project manager for a systems development project involving a new database application for her organization’s human resources department. Despite Farihah’s best efforts at estimating the time requirements for the project, the team has missed the deadline for completing the Analysis Phase and producing the System Proposal. Farihah had estimated during her 6-week Planning Phase that Analysis would require 2 months, but the team finished the System Proposal 2 weeks behind their planned target date. Based on her discussions with the team members, Farihah believes that the system is more complex than she originally thought. Should Farihah adjust her timeline, or can she try to make up for the lost two weeks? Farihah needs your advice.arrow_forwardplease solve for question Carrow_forwardOnly typed explanation The table below contains data for the installation of new equipment in a manufacturing process at Excello Corporation. Your company is responsible for the installation project. Indirect costs are $12,000 per week, and a penalty cost of $10,000 per week will be incurred by your company for every week the project is delayed beyond week 14. What is the shortest time duration for this project regardless of cost? What is the minimum total cost associated with completing the project in 14 weeks? What is the total time of the minimum-cost schedule?arrow_forward
- The table below contains data for the installation of new equipment in a manufacturing process at Excello Corporation. Your company is responsible for the installation project. Indirect costs are $12,000 per week, and a penalty cost of $6,000 per week will be incurred by your company for every week the project is delayed beyond week 12. Activity A B с D E F G Immediate Predecessor(s) AB Activity A B с D A C D, E E Normal Time Crash Time (weeks) (weeks) 3 1 2 2 1 3 4 1 6 3 Time according to schedule (weeks) 1 a. What is the shortest time duration for this project regardless of cost? The shortest project duration regardless of cost is 9 weeks. (Enter your response as a whole number.) b. What is the minimum total cost associated with completing the project in 12 weeks? The minimum total cost to complete the project in 12 weeks is $ 203500. (Enter your response as a whole number.) c. What is the total time of the minimum-cost schedule? (Enter your responses as whole numbers.) The total…arrow_forwardRoger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Immediate Predecessor(s) Activity A B C D E F G This exercise contains only parts b, c, and d. b) The critical activities for the leadership training program development project are A-E-G c) The project length for the leadership training program development project = 22 days. d) Slack time for each of the activities is: B A, D C E, F Activity A B Slack Time 0 Time (days) 10 6 3 2 4 8arrow_forwardThe table below contains data for the installation of new equipment in a manufacturing process a Excello Corporation. Your company is responsible for the installation project. Indirect costs are $10,000 per week, and a penalty cost of $9,000 per week will be incurred by your company for every week the project is delayed beyond week12. Activity Immediate Predecessor(s) ABCDEFG long dash- long dash- ABCDEFG A B C D, E E Normal Time Crash Time Normal Cost Crash Cost (weeks) (weeks) ($) ($) 1 14,000 2 3,000 1 40,000 3 22,000 1 8,000 4 13,000 2 16,000 3234 1 6 63 7,000 3,000 12,000 12,000 8,000 5,000 9,000 a. What is the shortest time duration for this project regardless of cost? (Enter your response as a whole number.) b. What is the minimum total cost associated with completing the project in 12 weeks? C. What is the total time of the minimum cost schedule? (enter your response as whole numbers). The total project's duration according to minimum cost schedule is? The minimum cost schedule…arrow_forward
- Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: a. the critical activities for the leadership training program development project are: _____ b. the project length for the leadership training program development project= __ days. c. Slack time for each of the activities is: Activity: Slack time: A ______ B ______ C ______ D ______ E ______ F ______ G ______arrow_forwardPlease solve my Problem as Soon as possible. Thank You!arrow_forwardThe table below contains data for the installation of new equipment in a manufacturing process at Excello Corporation. Your company is responsible for the installation project. Indirect costs are $12,000 per week, and a penalty cost of $8,000 per week will be incurred by your company for every week the project is delayed beyond week 12. Activity Immediate Predecessor(s) A B с D E F G || D, E Normal Time Crash Time Normal Cost (weeks) ($) 3 7,000 2 3,000 3 12,000 4 12,000 1 8,000 6 5,000 3 9,000 (weeks) 1 2 1 3 1 4 2 D Crash Cost ($) 14,000 3,000 40,000 22,000 8,000 13,000 16,000arrow_forward
- A competitor of Kozar International Inc. has begun marketing a new, instant-developing film project. Kozar has had a similar product under study in its research and development (R&D) department but has not yet been able to begin production. Because of the competitor’s action, top managers have asked for a speedup of R&D activities so that Kozar can produce and market instant film at the earliest possible date. The predecessor information and activity time estimates in months are as follows: Draw the Project Networkarrow_forwardA competitor of Kozar International Inc. has begun marketing a new, instant-developing film project. Kozar has had a similar product under study in its research and development (R&D) department but has not yet been able to begin production. Because of the competitor’s action, top managers have asked for a speedup of R&D activities so that Kozar can produce and market instant film at the earliest possible date. The predecessor information and activity time estimates in months are as follows: Develop an activity schedule for this project using early and late start and finish times, compute activity slack time and define the critical activities.arrow_forwardA competitor of Kozar International Inc. has begun marketing a new, instant-developing film project. Kozar has had a similar product under study in its research and development (R&D) department but has not yet been able to begin production. Because of the competitor’s action, top managers have asked for a speedup of R&D activities so that Kozar can produce and market instant film at the earliest possible date. The predecessor information and activity time estimates in months are as follows: A: Draw the Project Network B: Develop an activity schedule for this project using early and late start and finish times, compute activity slack time, and define the critical activities.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY