Question
Book Icon
Chapter 5, Problem 34P
To determine

Which of the two alternatives should be selected.

Expert Solution & Answer
Check Mark

Answer to Problem 34P

The option to be implemented is the automated process, since it results in an overall lower cash outflow over a period of 15 years.

Explanation of Solution

Given information:

Initial Cost:

Labor Intensive Process $0

Automated Process $55,000

Installation Cost:

Labor Intensive Process $0

Automated Process $15,500

Operation and Maintenance costs:

Labor Intensive Process $1,500

Automated Process $4,800

Increase in Operation and Maintenance costs:

Labor Intensive Process $200

Automated Process $600

Labor Costs:

Labor Intensive Process $116,000

Automated Process $41,000

Increase in Labor Costs:

Labor Intensive Process 4%

Automated Process 4%

Salvage Value in year 15:

Labor Intensive Process $5,000

Automated Process $19,000

Rate of Interest for Calculation: 25%

Based on the above information, the following tables outlines the net present value calculation of the two options.

Labor Intensive Process:

Year Particulars Cash flow Present value Factor @25% Present value
0 Installation Cost $- 1.0000 $-
1 Annual Operating costs $ 1,500.00 0.8000 $ 1,200.00
2 Annual Operating costs $ 1,700.00 0.6400 $ 1,088.00
3 Annual Operating costs $ 1,900.00 0.5120 $ 972.80
4 Annual Operating costs $ 2,100.00 0.4096 $ 860.16
5 Annual Operating costs $ 2,300.00 0.3277 $ 753.71
6 Annual Operating costs $ 2,500.00 0.2621 $ 655.25
7 Annual Operating costs $ 2,700.00 0.2097 $ 566.19
8 Annual Operating costs $ 2,900.00 0.1678 $ 486.62
9 Annual Operating costs $ 3,100.00 0.1342 $ 416.02
10 Annual Operating costs $ 3,300.00 0.1074 $ 354.42
11 Annual Operating costs $ 3,500.00 0.0859 $ 300.65
12 Annual Operating costs $ 3,700.00 0.0687 $ 254.19
13 Annual Operating costs $ 3,900.00 0.0550 $ 214.50
14 Annual Operating costs $ 4,100.00 0.0440 $ 180.40
15 Annual Operating costs $ 4,100.00 0.0352 $ 144.32
1 Annual Labor costs $116,000.00 0.8000 $92,800.00
2 Annual Labor costs $120,640.00 0.6400 $77,209.60
3 Annual Labor costs $125,465.60 0.5120 $64,238.39
4 Annual Labor costs $130,484.22 0.4096 $53,446.34
5 Annual Labor costs $135,703.59 0.3277 $44,470.07
6 Annual Labor costs $141,131.74 0.2621 $36,990.63
7 Annual Labor costs $146,777.01 0.2097 $30,779.14
8 Annual Labor costs $152,648.09 0.1678 $25,614.35
9 Annual Labor costs $158,754.01 0.1342 $21,304.79
10 Annual Labor costs $165,104.17 0.1074 $17,732.19
11 Annual Labor costs $171,708.34 0.0859 $14,749.75
12 Annual Labor costs $178,576.67 0.0687 $12,268.22
13 Annual Labor costs $185,719.74 0.0550 $10,214.59
14 Annual Labor costs $193,148.53 0.0440 $ 8,498.54
15 Annual Labor costs $200,874.47 0.0352 $ 7,070.78
15 Salvage Value $ (5,000.00) 0.0352 $(176.00)
Net Present value $525,658.58

Automated Process:

Year Particulars Cash flow Present value Factor @25% Present value
0 Installation Cost $70,500.00 1.0000 $70,500.00
1 Annual Operating costs $4,800.00 0.8000 $3,840.00
2 Annual Operating costs $5,400.00 0.6400 $3,456.00
3 Annual Operating costs $6,000.00 0.5120 $3,072.00
4 Annual Operating costs $6,600.00 0.4096 $2,703.36
5 Annual Operating costs $7,200.00 0.3277 $2,359.44
6 Annual Operating costs $7,800.00 0.2621 $2,044.38
7 Annual Operating costs $8,400.00 0.2097 $1,761.48
8 Annual Operating costs $9,000.00 0.1678 $1,510.20
9 Annual Operating costs $9,600.00 0.1342 $1,288.32
10 Annual Operating costs $10,200.00 0.1074 $1,095.48
11 Annual Operating costs $10,800.00 0.0859 $927.72
12 Annual Operating costs $11,400.00 0.0687 $783.18
13 Annual Operating costs $12,000.00 0.0550 $660.00
14 Annual Operating costs $12,600.00 0.0440 $554.40
15 Annual Operating costs $13,200.00 0.0352 $464.64
1 Annual Labor costs $41,000.00 0.8000 $32,800.00
2 Annual Labor costs $42,640.00 0.6400 $27,289.60
3 Annual Labor costs $44,345.60 0.5120 $22,704.95
4 Annual Labor costs $46,119.42 0.4096 $18,890.51
5 Annual Labor costs $47,964.20 0.3277 $15,717.87
6 Annual Labor costs $49,882.77 0.2621 $13,074.27
7 Annual Labor costs $51,878.08 0.2097 $10,878.83
8 Annual Labor costs $53,953.20 0.1678 $9,053.35
9 Annual Labor costs $56,111.33 0.1342 $7,530.14
10 Annual Labor costs $58,355.78 0.1074 $6,267.41
11 Annual Labor costs $60,690.02 0.0859 $5,213.27
12 Annual Labor costs $63,117.62 0.0687 $4,336.18
13 Annual Labor costs $65,642.32 0.0550 $3,610.33
14 Annual Labor costs $68,268.01 0.0440 $3,003.79
15 Annual Labor costs $70,998.73 0.0352 $2,499.16
15 Salvage Value ($19,000.00) 0.0352 ($668.80)
Net Present value $279,221.46

Net present value is the difference of Sum of Present values of cash inflows and Sum of Present values of cash outflows. If the value is positive then the project may be accepted. While evaluation of two or more alternatives takes place, then the proposal with the higher net present value may be selected since it results in a greater cash inflow over the duration of the project.

In the given scenario, Present values are calculated by calculating the present values of cash inflows in the form of salvage value and cash outflows such as installation cost and operating cost.

In case of the labor intensive process theInstallation Cost is $0, Annual Operating costs are $1,500 with an increase of $200 each year.AnnualLabor costs is $116,000 with an increase of 4% each year. Salvage value at the end of year 15 is $5,000.

In case of the automated process the Installation Cost is $70,500 i.e. $55,000 for the Initial cost and $15,500 for the installation costs, Annual Operating costs are $4,800 with an increase of $600 each year. Annual Labor costs is $41,000 with an increase of 4% each year. Salvage value at the end of year 15 is $19,000.

Present value factor is calculated as 1/1.25 ^ N where N is the year of operation

Conclusion:

Hence the process to be implemented is the automated process since it results in lower overall cash flow for a period of 15 years.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
1. Suppose that the two nations face the following benefits of pollution, B, and costs of abatement, C: BN = 10, Bs = 7; CN = 5, Cs = 4. Further assume that if the nation chooses to abate pollution, it still receives the benefits of pollution but now must pay the cost of abatement as well. a. Identify the payoffs that accrue to each nation under the four different possible outcomes of the game and present these payoffs in the normal form of the game. b. Recall that the term dominant strategy defines the condition that a player in a game would prefer to play that strategy (in this case either pollute or abate) regardless of the strategy chosen by the other player in the game. Does either nation have a dominant strategy in this game? If so, what is it? c. Identify the Nash equilibria, or non-cooperative equilibria, of this game.
agrody calming Inted 001 and me 2. A homeowner is concerned about the various air pollutants (e.g., benzene and methane) released in her house when she cooks with natural gas. She is considering replacing her gas oven and stove with an electric stove comprising an induction cooktop and convection oven. The new appliance costs $900 to purchase and install. Capping the old gas line costs an additional $150 (a one-time fee). The old line must be inspected for leaks each year after capping, at a cost of $35 for each inspection. a. If the homeowner plans to remain in the house for four more years and the discount rate is 4%, what is the minimum present value of the benefits that the homeowner would need to experience for this purchase to be justified based on its private net sub present value? b. While trying to understand how she might express the value of reduced exposure to indoor air pollutants in dollar terms, the homeowner consulted the EPA website and found estimates provided by…
After the ban is imposed, Joe’s firm switches to the more expensive biodegradable disposable cups. This increases the cost associated with each cup of coffee it produces. Which cost curve(s) will be impacted by the use of the more expensive biodegradable disposable cups? Why? Which cost curve(s) will not shift, and why not? Please use the table below to answer this question. For the second column (“Impacted? If so, how?”), please use one of the following three choices: No shift; Shifts up (i.e., increases: at nearly any given quantity, the cost goes up); or Shifts down (i.e., decreases: at nearly any given quantity, the cost goes down). $ Cost Curve Impacted? If so, how? Explanation of the Shift: Why or Why Not AFC No shift. Fix costs stay the same, regardless of quantity. Fixed cost is calculated as Fixed Cost/Quantity. Since fixed costs remain unchanged, AFC stays the same for each quantity. MC Shifts up. Since the biodegradable cups are more expensive, the…

Chapter 5 Solutions

ENGINEERING ECO ANALYSIS W/STUDY GUIDE

Ch. 5 - Prob. 8PCh. 5 - Prob. 9PCh. 5 - Prob. 10PCh. 5 - Prob. 11PCh. 5 - Prob. 12PCh. 5 - Prob. 13PCh. 5 - Prob. 14PCh. 5 - Prob. 15PCh. 5 - Prob. 16PCh. 5 - Prob. 17PCh. 5 - Prob. 18PCh. 5 - Prob. 19PCh. 5 - Prob. 20PCh. 5 - Prob. 21PCh. 5 - Prob. 22PCh. 5 - Prob. 23PCh. 5 - Prob. 24PCh. 5 - Prob. 25PCh. 5 - Prob. 26PCh. 5 - Prob. 27PCh. 5 - Prob. 28PCh. 5 - Prob. 29PCh. 5 - Prob. 30PCh. 5 - Prob. 31PCh. 5 - Prob. 32PCh. 5 - Prob. 33PCh. 5 - Prob. 34PCh. 5 - Prob. 35PCh. 5 - Prob. 36PCh. 5 - Prob. 37PCh. 5 - Prob. 38PCh. 5 - Prob. 39PCh. 5 - Prob. 40PCh. 5 - Prob. 41PCh. 5 - Prob. 42PCh. 5 - Prob. 43PCh. 5 - Prob. 44PCh. 5 - Prob. 45PCh. 5 - Prob. 46PCh. 5 - Prob. 47PCh. 5 - Prob. 48PCh. 5 - Prob. 49PCh. 5 - Prob. 50PCh. 5 - Prob. 51PCh. 5 - Prob. 52PCh. 5 - Prob. 53PCh. 5 - Prob. 54PCh. 5 - Prob. 55PCh. 5 - Prob. 56PCh. 5 - Prob. 57PCh. 5 - Prob. 58PCh. 5 - Prob. 59PCh. 5 - Prob. 60PCh. 5 - Prob. 61PCh. 5 - Prob. 62PCh. 5 - Prob. 63PCh. 5 - Prob. 64PCh. 5 - Prob. 65PCh. 5 - Prob. 66PCh. 5 - Prob. 67PCh. 5 - Prob. 68PCh. 5 - Prob. 69PCh. 5 - Prob. 70PCh. 5 - Prob. 71PCh. 5 - Prob. 72PCh. 5 - Prob. 73PCh. 5 - Prob. 74PCh. 5 - Prob. 75PCh. 5 - Prob. 76PCh. 5 - Prob. 77PCh. 5 - Prob. 78PCh. 5 - Prob. 79PCh. 5 - Prob. 80PCh. 5 - Prob. 81PCh. 5 - Prob. 82PCh. 5 - Prob. 83PCh. 5 - Prob. 84PCh. 5 - Prob. 85PCh. 5 - Prob. 86PCh. 5 - Prob. 87PCh. 5 - Prob. 88PCh. 5 - Prob. 89PCh. 5 - Prob. 90PCh. 5 - Prob. 91PCh. 5 - Prob. 92PCh. 5 - Prob. 93PCh. 5 - Prob. 94PCh. 5 - Prob. 95PCh. 5 - Prob. 96PCh. 5 - Prob. 97PCh. 5 - Prob. 98PCh. 5 - Prob. 99PCh. 5 - Prob. 100PCh. 5 - Prob. 101P
Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
ENGR.ECONOMIC ANALYSIS
Economics
ISBN:9780190931919
Author:NEWNAN
Publisher:Oxford University Press
Text book image
Principles of Economics (12th Edition)
Economics
ISBN:9780134078779
Author:Karl E. Case, Ray C. Fair, Sharon E. Oster
Publisher:PEARSON
Text book image
Engineering Economy (17th Edition)
Economics
ISBN:9780134870069
Author:William G. Sullivan, Elin M. Wicks, C. Patrick Koelling
Publisher:PEARSON
Text book image
Principles of Economics (MindTap Course List)
Economics
ISBN:9781305585126
Author:N. Gregory Mankiw
Publisher:Cengage Learning
Text book image
Managerial Economics: A Problem Solving Approach
Economics
ISBN:9781337106665
Author:Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:Cengage Learning
Text book image
Managerial Economics & Business Strategy (Mcgraw-...
Economics
ISBN:9781259290619
Author:Michael Baye, Jeff Prince
Publisher:McGraw-Hill Education