Question
Book Icon
Chapter 5, Problem 31P
To determine

(a)

Which of the two alternatives should be selected assuming a 10% rate of interest.

Expert Solution
Check Mark

Answer to Problem 31P

The Option to be implemented is Option 2, since it results in a lower cash outflow for a period of 30 years.

Explanation of Solution

Given information:

Option 1:

Install one cable now for 4000 lines. Installation cost $20,000 and annual maintenance costs would be $1,500.

Option 2:

Install one cable for 2000 lines now and one cable for 2000 lines after 10 years. Installation cost $15,000 and annual maintenance costs would be $1,000.

Rate of interest for calculation: 10%.

Based on the above information, the following tables outlines the net present value calculation of the two options.

Option 1:

Year Particulars Cash flow Present value Factor @10% Present value
0 Installation Cost $20,000.00 1 $20,000.00
1 Operating costs $1,500.00 0.9091 $1,363.64
2 Operating costs $1,500.00 0.8264 $1,239.67
3 Operating costs $1,500.00 0.7513 $1,126.97
4 Operating costs $1,500.00 0.6830 $1,024.52
5 Operating costs $1,500.00 0.6209 $931.38
5 Operating costs $1,500.00 0.6209 $931.38
6 Operating costs $1,500.00 0.5645 $846.71
7 Operating costs $1,500.00 0.5132 $769.74
8 Operating costs $1,500.00 0.4665 $699.76
9 Operating costs $1,500.00 0.4241 $636.15
10 Operating costs $1,500.00 0.3855 $578.31
11 Operating costs $1,500.00 0.3505 $525.74
12 Operating costs $1,500.00 0.3186 $477.95
13 Operating costs $1,500.00 0.2897 $434.50
14 Operating costs $1,500.00 0.2633 $395.00
15 Operating costs $1,500.00 0.2394 $359.09
16 Operating costs $1,500.00 0.2176 $326.44
17 Operating costs $1,500.00 0.1978 $296.77
18 Operating costs $1,500.00 0.1799 $269.79
19 Operating costs $1,500.00 0.1635 $245.26
20 Operating costs $1,500.00 0.1486 $222.97
21 Operating costs $1,500.00 0.1351 $202.70
22 Operating costs $1,500.00 0.1228 $184.27
23 Operating costs $1,500.00 0.1117 $167.52
24 Operating costs $1,500.00 0.1015 $152.25
25 Operating costs $1,500.00 0.0923 $138.44
26 Operating costs $1,500.00 0.0839 $125.86
27 Operating costs $1,500.00 0.0763 $114.42
28 Operating costs $1,500.00 0.0693 $104.02
29 Operating costs $1,500.00 0.0630 $94.56
30 Operating costs $1,500.00 0.0573 $85.96
Net cash outflow $35,071.75

Option 2:

Year Particulars Cash flow Present value Factor @10% Present value
0 Installation Cost $15,000.00 1 $15,000.00
1 Operating costs $1,000.00 0.9091 $909.09
2 Operating costs $1,000.00 0.8264 $826.45
3 Operating costs $1,000.00 0.7513 $751.31
4 Operating costs $1,000.00 0.6830 $683.01
5 Operating costs $1,000.00 0.6209 $620.92
5 Operating costs $1,000.00 0.6209 $620.92
6 Operating costs $1,000.00 0.5645 $564.47
7 Operating costs $1,000.00 0.5132 $513.16
8 Operating costs $1,000.00 0.4665 $466.51
9 Operating costs $1,000.00 0.4241 $424.10
10 Operating costs $1,000.00 0.3855 $385.54
10 Installation Cost $15,000.00 0.3855 $5,783.15
11 Operating costs $2,000.00 0.3505 $700.99
12 Operating costs $2,000.00 0.3186 $637.26
13 Operating costs $2,000.00 0.2897 $579.33
14 Operating costs $2,000.00 0.2633 $526.66
15 Operating costs $2,000.00 0.2394 $478.78
16 Operating costs $2,000.00 0.2176 $435.26
17 Operating costs $2,000.00 0.1978 $395.69
18 Operating costs $2,000.00 0.1799 $359.72
19 Operating costs $2,000.00 0.1635 $327.02
20 Operating costs $2,000.00 0.1486 $297.29
21 Operating costs $2,000.00 0.1351 $270.26
22 Operating costs $2,000.00 0.1228 $245.69
23 Operating costs $2,000.00 0.1117 $223.36
24 Operating costs $2,000.00 0.1015 $203.05
25 Operating costs $2,000.00 0.0923 $184.59
26 Operating costs $2,000.00 0.0839 $167.81
27 Operating costs $2,000.00 0.0763 $152.56
28 Operating costs $2,000.00 0.0693 $138.69
29 Operating costs $2,000.00 0.0630 $126.08
30 Operating costs $2,000.00 0.0573 $114.62
Net cash outflow $34,113.33

Net present value is the difference of Sum of Present values of cash inflows and Sum of Present values of cash outflows. If the value is positive then the project may be accepted. While evaluation of two or more alternatives takes place, then the proposal with the higher net present value may be selected since it results in a greater cash inflow over the duration of the project.

In the given scenario, Present values are calculated by calculating the present values of cash outflows such as installation cost and operating cost.

Present value factor is calculated as 1/1.10 ^ N where N is the year of operation of the refrigerator.

Deferment of capital expenditure to Year 10 in case of Option 2 results in a lower overall cash outflow despite increase in the annual operating costs from years 11-30. This is owing to the present value factor.

Conclusion:

Hence the Option to be implemented is Option 2 since it results in lower overall cash outflow.

To determine

(b)

Which of the two alternatives should be selected.

Expert Solution
Check Mark

Answer to Problem 31P

The Option to be implemented is Option 1, since it results in a lower cash outflow for a period of 30 years.

Explanation of Solution

Given information:

Option 1:

Install one cable now for 4000 lines. Installation cost $20,000 and annual maintenance costs would be $1,500.

Option 2:

Install one cable for 2000 lines now and one cable for 2000 lines after 5 years. Installation cost $15,000 and annual maintenance costs would be $1,000.

Rate of interest for calculation: 10%.

Based on the above information, the following tables outlines the net present value calculation of the two options.

Option 1:

Year Particulars Cash flow Present value Factor @10% Present value
0 Installation Cost $ 20,000.00 1.00 $ 20,000.00
1 Operating costs $ 1,500.00 0.91 $ 1,363.64
2 Operating costs $ 1,500.00 0.83 $ 1,239.67
3 Operating costs $ 1,500.00 0.75 $ 1,126.97
4 Operating costs $ 1,500.00 0.68 $ 1,024.52
5 Operating costs $ 1,500.00 0.62 $ 931.38
5 Operating costs $ 1,500.00 0.62 $ 931.38
6 Operating costs $ 1,500.00 0.56 $ 846.71
7 Operating costs $ 1,500.00 0.51 $ 769.74
8 Operating costs $ 1,500.00 0.47 $ 699.76
9 Operating costs $ 1,500.00 0.42 $ 636.15
10 Operating costs $ 1,500.00 0.39 $ 578.31
11 Operating costs $ 1,500.00 0.35 $ 525.74
12 Operating costs $ 1,500.00 0.32 $ 477.95
13 Operating costs $ 1,500.00 0.29 $ 434.50
14 Operating costs $ 1,500.00 0.26 $ 395.00
15 Operating costs $ 1,500.00 0.24 $ 359.09
16 Operating costs $ 1,500.00 0.22 $ 326.44
17 Operating costs $ 1,500.00 0.20 $ 296.77
18 Operating costs $ 1,500.00 0.18 $ 269.79
19 Operating costs $ 1,500.00 0.16 $ 245.26
20 Operating costs $ 1,500.00 0.15 $ 222.97
21 Operating costs $ 1,500.00 0.14 $ 202.70
22 Operating costs $ 1,500.00 0.12 $ 184.27
23 Operating costs $ 1,500.00 0.11 $ 167.52
24 Operating costs $ 1,500.00 0.10 $ 152.29
25 Operating costs $ 1,500.00 0.09 $ 138.44
26 Operating costs $ 1,500.00 0.08 $ 125.86
27 Operating costs $ 1,500.00 0.08 $ 114.42
28 Operating costs $ 1,500.00 0.07 $ 104.02
29 Operating costs $ 1,500.00 0.06 $ 94.56
30 Operating costs $ 1,500.00 0.06 $ 85.96
Net cash outflow 35,071.75

Option 2:

Year Particulars Cash flow Present value Factor @10% Present value
0 Installation Cost $ 15,000.00 1.00 $ 15,000.00
1 Operating costs $ 1,000.00 0.91 $ 909.09
2 Operating costs $ 1,000.00 0.83 $ 826.45
3 Operating costs $ 1,000.00 0.75 $ 751.31
4 Operating costs $ 1,000.00 0.68 $ 683.01
5 Operating costs $ 1,000.00 0.62 $ 620.92
5 Operating costs $ 1,000.00 0.62 $ 620.92
5 Installation Cost $ 15,000.00 0.62 $ 9,313.82
6 Operating costs $ 2,000.00 0.56 $ 1,128.95
7 Operating costs $ 2,000.00 0.51 $ 1,026.32
8 Operating costs $ 2,000.00 0.47 $ 933.01
9 Operating costs $ 2,000.00 0.42 $ 848.20
10 Operating costs $ 2,000.00 0.39 $ 771.09
11 Operating costs $ 2,000.00 0.35 $ 700.99
12 Operating costs $ 2,000.00 0.32 $ 637.26
13 Operating costs $ 2,000.00 0.29 $ 579.33
14 Operating costs $ 2,000.00 0.26 $ 526.66
15 Operating costs $ 2,000.00 0.24 $ 478.78
16 Operating costs $ 2,000.00 0.22 $ 435.26
17 Operating costs $ 2,000.00 0.20 $ 395.69
18 Operating costs $ 2,000.00 0.18 $ 359.72
19 Operating costs $ 2,000.00 0.16 $ 327.02
20 Operating costs $ 2,000.00 0.15 $ 297.29
21 Operating costs $ 2,000.00 0.14 $ 270.26
22 Operating costs $ 2,000.00 0.12 $ 245.69
23 Operating costs $ 2,000.00 0.11 $ 223.36
24 Operating costs $ 2,000.00 0.10 $ 203.05
25 Operating costs $ 2,000.00 0.09 $ 184.59
26 Operating costs $ 2,000.00 0.08 $ 167.81
27 Operating costs $ 2,000.00 0.08 $ 152.56
28 Operating costs $ 2,000.00 0.07 $ 138.69
29 Operating costs $ 2,000.00 0.06 $ 126.08
30 Operating costs $ 2,000.00 0.06 $ 114.62
Net cash outflow 39,997.78

Net present value is the difference of Sum of Present values of cash inflows and Sum of Present values of cash outflows. If the value is positive then the project may be accepted. While evaluation of two or more alternatives takes place, then the proposal with the higher net present value may be selected since it results in a greater cash inflow over the duration of the project.

In the given scenario, Present values are calculated by calculating the present values of cash outflows such as installation cost and operating cost.

Present value factor is calculated as 1/1.10 ^ N where N is the year of operation of the refrigerator.

Deferment of capital expenditure to Year 5 in case of Option 2 results in a higher overall cash outflow due to increase in the annual operating costs from years 6-30. This is owing to the present value factor.

Conclusion:

Hence the Option to be implemented is Option 1 since it results in lower overall cash outflow.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
After the ban is imposed, Joe’s firm switches to the more expensive biodegradable disposable cups. This increases the cost associated with each cup of coffee it produces. Which cost curve(s) will be impacted by the use of the more expensive biodegradable disposable cups? Why? Which cost curve(s) will not shift, and why not? Please use the table below to answer this question. For the second column (“Impacted? If so, how?”), please use one of the following three choices: No shift; Shifts up (i.e., increases: at nearly any given quantity, the cost goes up); or Shifts down (i.e., decreases: at nearly any given quantity, the cost goes down). $ Cost Curve Impacted? If so, how? Explanation of the Shift: Why or Why Not AFC No shift. Fix costs stay the same, regardless of quantity. Fixed cost is calculated as Fixed Cost/Quantity. Since fixed costs remain unchanged, AFC stays the same for each quantity. MC Shifts up. Since the biodegradable cups are more expensive, the…
Styrofoam is non-biodegradable and is not easily recyclable. Many cities and at least one state have enacted laws that ban the use of polystyrene containers. These locales understand that banning these containers will force many businesses to turn to other more expensive forms of packaging and cups, but argue the ban is environmentally important. Shane owns a firm with a conventional production function resulting in U-shaped ATC, AVC, and MC curves. Shane's business sells takeout food and drinks that are currently packaged in styrofoam containers and cups. Graph the short-run AFC0, AVC0, ATC0, and MC0 curves for Shane's firm before the ban on using styrofoam containers.
d-f

Chapter 5 Solutions

ENGINEERING ECO ANALYSIS W/STUDY GUIDE

Ch. 5 - Prob. 8PCh. 5 - Prob. 9PCh. 5 - Prob. 10PCh. 5 - Prob. 11PCh. 5 - Prob. 12PCh. 5 - Prob. 13PCh. 5 - Prob. 14PCh. 5 - Prob. 15PCh. 5 - Prob. 16PCh. 5 - Prob. 17PCh. 5 - Prob. 18PCh. 5 - Prob. 19PCh. 5 - Prob. 20PCh. 5 - Prob. 21PCh. 5 - Prob. 22PCh. 5 - Prob. 23PCh. 5 - Prob. 24PCh. 5 - Prob. 25PCh. 5 - Prob. 26PCh. 5 - Prob. 27PCh. 5 - Prob. 28PCh. 5 - Prob. 29PCh. 5 - Prob. 30PCh. 5 - Prob. 31PCh. 5 - Prob. 32PCh. 5 - Prob. 33PCh. 5 - Prob. 34PCh. 5 - Prob. 35PCh. 5 - Prob. 36PCh. 5 - Prob. 37PCh. 5 - Prob. 38PCh. 5 - Prob. 39PCh. 5 - Prob. 40PCh. 5 - Prob. 41PCh. 5 - Prob. 42PCh. 5 - Prob. 43PCh. 5 - Prob. 44PCh. 5 - Prob. 45PCh. 5 - Prob. 46PCh. 5 - Prob. 47PCh. 5 - Prob. 48PCh. 5 - Prob. 49PCh. 5 - Prob. 50PCh. 5 - Prob. 51PCh. 5 - Prob. 52PCh. 5 - Prob. 53PCh. 5 - Prob. 54PCh. 5 - Prob. 55PCh. 5 - Prob. 56PCh. 5 - Prob. 57PCh. 5 - Prob. 58PCh. 5 - Prob. 59PCh. 5 - Prob. 60PCh. 5 - Prob. 61PCh. 5 - Prob. 62PCh. 5 - Prob. 63PCh. 5 - Prob. 64PCh. 5 - Prob. 65PCh. 5 - Prob. 66PCh. 5 - Prob. 67PCh. 5 - Prob. 68PCh. 5 - Prob. 69PCh. 5 - Prob. 70PCh. 5 - Prob. 71PCh. 5 - Prob. 72PCh. 5 - Prob. 73PCh. 5 - Prob. 74PCh. 5 - Prob. 75PCh. 5 - Prob. 76PCh. 5 - Prob. 77PCh. 5 - Prob. 78PCh. 5 - Prob. 79PCh. 5 - Prob. 80PCh. 5 - Prob. 81PCh. 5 - Prob. 82PCh. 5 - Prob. 83PCh. 5 - Prob. 84PCh. 5 - Prob. 85PCh. 5 - Prob. 86PCh. 5 - Prob. 87PCh. 5 - Prob. 88PCh. 5 - Prob. 89PCh. 5 - Prob. 90PCh. 5 - Prob. 91PCh. 5 - Prob. 92PCh. 5 - Prob. 93PCh. 5 - Prob. 94PCh. 5 - Prob. 95PCh. 5 - Prob. 96PCh. 5 - Prob. 97PCh. 5 - Prob. 98PCh. 5 - Prob. 99PCh. 5 - Prob. 100PCh. 5 - Prob. 101P
Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
ENGR.ECONOMIC ANALYSIS
Economics
ISBN:9780190931919
Author:NEWNAN
Publisher:Oxford University Press
Text book image
Principles of Economics (12th Edition)
Economics
ISBN:9780134078779
Author:Karl E. Case, Ray C. Fair, Sharon E. Oster
Publisher:PEARSON
Text book image
Engineering Economy (17th Edition)
Economics
ISBN:9780134870069
Author:William G. Sullivan, Elin M. Wicks, C. Patrick Koelling
Publisher:PEARSON
Text book image
Principles of Economics (MindTap Course List)
Economics
ISBN:9781305585126
Author:N. Gregory Mankiw
Publisher:Cengage Learning
Text book image
Managerial Economics: A Problem Solving Approach
Economics
ISBN:9781337106665
Author:Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:Cengage Learning
Text book image
Managerial Economics & Business Strategy (Mcgraw-...
Economics
ISBN:9781259290619
Author:Michael Baye, Jeff Prince
Publisher:McGraw-Hill Education