Question
Book Icon
Chapter 4, Problem 7PA

a)

Summary Introduction

To determine: The labor content.

a)

Expert Solution
Check Mark

Explanation of Solution

Given information:

OPERATIONS MANAGEMENT LL W/CONNECT CODE, Chapter 4, Problem 7PA , additional homework tip  1

Labor content:

The labor content is total time required to perform all the tasks of by the workers. It is 215 seconds.

The labor content is 215 seconds.

b)

Summary Introduction

To determine: The cost of direct labor for a toothbrush.

b)

Expert Solution
Check Mark

Explanation of Solution

Given information:

OPERATIONS MANAGEMENT LL W/CONNECT CODE, Chapter 4, Problem 7PA , additional homework tip  2

Calculation of time per worker:

The time for Worker A is 65 seconds.

The time for Worker B is 35 seconds.

The time for Worker C is 25 seconds.

The time for Worker D is 30 seconds.

The time for Worker E is 60 seconds.

The bottleneck is Worker A with 65 seconds. Therefore, the flow rate will be:

Flow rate=60 minutes×60 secondsBottleneck time=60×6065=55.38=55.4 brushes per hour

Cost of direct labor:

Cost of direct labor=Wage rate×Number of workersFlow rate=$15×555.4=7555.4=$1.35

The cost of direct labor per toothbrush is $1.35.

c)

Summary Introduction

To determine: The utilization of worker A.

c)

Expert Solution
Check Mark

Explanation of Solution

Given information:

OPERATIONS MANAGEMENT LL W/CONNECT CODE, Chapter 4, Problem 7PA , additional homework tip  3

Utilization of Worker A:

The time for Worker A is 65 seconds. It is the bottleneck time of the entire process. Therefore, the utilization is 100%.

The utilization of 100%.

d)

Summary Introduction

To determine: The average labor utilization of the process.

d)

Expert Solution
Check Mark

Explanation of Solution

Given information:

OPERATIONS MANAGEMENT LL W/CONNECT CODE, Chapter 4, Problem 7PA , additional homework tip  4

Average labor utilization of the process:

The cycle time will be equal to the bottleneck time which is 65 seconds. The average labor utilization will be:

Average labor utilization=Total timeNumber of workers×Cycle time×100=2155×65×100=215325×100=66.15%

The average labor utilization of 66.15%.

e)

Summary Introduction

To determine: The Takt time.

e)

Expert Solution
Check Mark

Explanation of Solution

Given information:

OPERATIONS MANAGEMENT LL W/CONNECT CODE, Chapter 4, Problem 7PA , additional homework tip  5

Demand rate = 40 toothbrushes per hour

Takt time:

Takt time=Minutes per hour×Seconds per minuteDemand rate per hour=60×6040=90 seconds

The Takt time is 90 second per toothbrush.

f)

Summary Introduction

To determine: The target manpower.

f)

Expert Solution
Check Mark

Explanation of Solution

Given information:

OPERATIONS MANAGEMENT LL W/CONNECT CODE, Chapter 4, Problem 7PA , additional homework tip  6

Takt time = 50 seconds

Target manpower

Target manpower=Total timeTakt time=21550=4.3

The target manpower is 4.3 workers.

g)

Summary Introduction

To determine: The capacity of the process after hiring the new worker.

g)

Expert Solution
Check Mark

Explanation of Solution

Given information:

OPERATIONS MANAGEMENT LL W/CONNECT CODE, Chapter 4, Problem 7PA , additional homework tip  7

New capacity of the process:

The new worker is added to Task 1 and Task 2 as it is the bottleneck of the process. After the addition of the new worker, the bottleneck is Worker E with a total time of 60 seconds. Therefore, the new capacity will be:

Capacity=60 minutes×60 secondsBottleneck time=60×6060=60 toothbrushes per hour

The capacity of process is 60 toothbrushes per hour.

h)

Summary Introduction

To determine: The capacity of the process.

h)

Expert Solution
Check Mark

Explanation of Solution

Given information:

OPERATIONS MANAGEMENT LL W/CONNECT CODE, Chapter 4, Problem 7PA , additional homework tip  8

New capacity of the process:

The tasks are assigned to minimize the maximum work across the various workers. Task 1 is assigned to Worker A. Tasks 2, 3 is assigned to Worker B. Tasks 4, 5, 6, and 7 is assigned to Worker C. Tasks 8, 9 is assigned to Worker D. Task 10 is assigned to Worker E. The bottleneck time now is Worker 3 with 50 seconds. Therefore, the capacity is:

Capacity=60 minutes×60 secondsBottleneck time=60×6050=72 toothbrushes per hour

The capacity of process is 60 toothbrushes per hour.

i)

Summary Introduction

To determine: The capacity of the process with the new method

i)

Expert Solution
Check Mark

Explanation of Solution

Given information:

OPERATIONS MANAGEMENT LL W/CONNECT CODE, Chapter 4, Problem 7PA , additional homework tip  9

New capacity of the process:

Capacity=Number of workers×60 minutes×60 secondsTotal process time=5×60×60215=83.7 toothbrushes per hour

The capacity of process is 83.7 toothbrushes per hour.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Note: A waiting line model solver computer package is needed to answer these questions. The Kolkmeyer Manufacturing Company uses a group of six identical machines, each of which operates an average of 23 hours between breakdowns. With randomly occurring breakdowns, the Poisson probability distribution is used to describe the machine breakdown arrival process. One person from the maintenance department provides the single-server repair service for the six machines. Management is now considering adding two machines to its manufacturing operation. This addition will bring the number of machines to eight. The president of Kolkmeyer asked for a study of the need to add a second employee to the repair operation. The service rate for each individual assigned to the repair operation is 0.40 machines per hour. (a) Compute the operating characteristics if the company retains the single-employee repair operation. (Round your answers to four decimal places. Report time in hours.) La = L = Wa W = h…
Burger Dome sells hamburgers, cheeseburgers, french fries, soft drinks, and milk shakes, as well as a limited number of specialty items and dessert selections. Although Burger Dome would like to serve each customer immediately, at times more customers arrive than can be handled by the Burger Dome food service staff. Thus, customers wait in line to place and receive their orders. Burger Dome analyzed data on customer arrivals and concluded that the arrival rate is 40 customers per hour. Burger Dome also studied the order-filling process and found that a single employee can process an average of 56 customer orders per hour. Burger Dome is concerned that the methods currently used to serve customers are resulting in excessive waiting times and a possible loss of sales. Management wants to conduct a waiting line study to help determine the best approach to reduce waiting times and improve service. Suppose Burger Dome establishes two servers but arranges the restaurant layout so that an…
Agan Interior Design provides home and office decorating assistance to its customers. In normal operation, an average of 2.6 customers arrive each hour. One design consultant is available to answer customer questions and make product recommendations. The consultant averages 10 minutes with each customer. (a) Compute the operating characteristics of the customer waiting line, assuming Poisson arrivals and exponential service times. (Round your answers to four decimal places. Report time in hours.) λ= μ = = L = Wa W = P. W h (b) Service goals dictate that an arriving customer should not wait for service more than an average of 5 minutes. Is this goal being met? (Round your answer to one decimal place.) W₁ (in minutes) = min, which is ---Select--- than the desired wait time, so the goal ---Select--- met. What action do you recommend? (Select all that apply.) Hire another consultant. Increase the hours of operation. Decrease the mean service rate. Increase the mean service rate. There is…
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Understanding Management (MindTap Course List)
Management
ISBN:9781305502215
Author:Richard L. Daft, Dorothy Marcic
Publisher:Cengage Learning
Text book image
Management, Loose-Leaf Version
Management