Question
Chapter 4, Problem 111P
Summary Introduction
To determine: The number of workers to be working and the way allocation should be made for the next five weeks.
Linear programming:
It is a mathematical modeling procedure where a linear function is maximized or minimized subject to certain constraints. This method is widely useful in making a quantitative analysis which is essential for making important business decisions.
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
E2-20 (Algo) Recording Manufacturing Costs [LO 2-3, 2-4, 2-5]
Reyes Manufacturing Company uses a job order cost system. At the beginning of January, the company had one job in process
201) and one job completed but not yet sold (Job 200). Job 202 was started during January. Other select account balances follo
(ignore any accounts that are not listed).
During January, the company had the following transactions:
a. Purchased $63,000 worth of materials on account.
b. Recorded materials issued to production as follows:
Job Number
201
Total Cost
202
Indirect materials
$ 11,100
21,800
6,000
$ 38,900
c. Recorded factory payroll costs from labor time tickets that revealed the following:
Job Number
201
202
Hours
101
392
Total Cost
Factory supervision
$ 2,600
10,200
4,700
$ 17,500
d. Applied overhead to production at a rate of $27.00 per direct labor hour for 493 actual direct labor hours.
e. Recorded the following actual manufacturing overhead costs:
Item
Factory rent
Depreciation
Factory…
Blackstone Diary products Limited is a leading producer of dairy products in Western Jamaica. Blackstone Dairy Ltd has customers throughout Jamaica and the Northern Caribbean . The Accounting Information Division prints monthly statements and sends them to the accounts receivable (AR) department, where a clerk mails them to the customers. Blackstone’s customers mail their payments back to the head office, where a clerk in AR batches the cheques and sends them to the cashier. The AR clerk then uses the payment stub to enter the payments into the computer, where the AR master data are updated to record the payment.
REQUIRED
1. Draw a context diagram to depict Blackstone’s Accounts receivable System
2. Draw a logical level 0 DFD to document Blackstone’s System.
3. Draw a physical DFD of Blackstone’s AR system.
Could someone please me with these three questions? A is question 1 B Is 2 and the last one is split but is only one question which is 3
Chapter 4 Solutions
Practical Management Science, Loose-leaf Version
Ch. 4.2 - Prob. 1PCh. 4.2 - Prob. 2PCh. 4.2 - Prob. 3PCh. 4.2 - Prob. 4PCh. 4.2 - Prob. 5PCh. 4.2 - Prob. 6PCh. 4.3 - Prob. 7PCh. 4.3 - Prob. 8PCh. 4.3 - Prob. 9PCh. 4.3 - Prob. 10P
Ch. 4.3 - Prob. 11PCh. 4.3 - Prob. 12PCh. 4.4 - Prob. 13PCh. 4.4 - Prob. 14PCh. 4.4 - Prob. 15PCh. 4.4 - Prob. 16PCh. 4.4 - Prob. 17PCh. 4.4 - Prob. 18PCh. 4.4 - Prob. 19PCh. 4.5 - Prob. 20PCh. 4.5 - Prob. 21PCh. 4.5 - Prob. 22PCh. 4.5 - Prob. 23PCh. 4.5 - Prob. 24PCh. 4.5 - Prob. 25PCh. 4.6 - Prob. 26PCh. 4.6 - Prob. 27PCh. 4.6 - Prob. 28PCh. 4.6 - Prob. 29PCh. 4.7 - Prob. 30PCh. 4.7 - Prob. 31PCh. 4.7 - Prob. 32PCh. 4.7 - Prob. 33PCh. 4.7 - Prob. 34PCh. 4.7 - Prob. 35PCh. 4.7 - Prob. 36PCh. 4.7 - Prob. 37PCh. 4.7 - Prob. 38PCh. 4.7 - Prob. 39PCh. 4.7 - Prob. 40PCh. 4.8 - Prob. 41PCh. 4.8 - Prob. 42PCh. 4.8 - Prob. 43PCh. 4.8 - Prob. 44PCh. 4 - Prob. 45PCh. 4 - Prob. 46PCh. 4 - Prob. 47PCh. 4 - Prob. 48PCh. 4 - Prob. 49PCh. 4 - Prob. 50PCh. 4 - Prob. 51PCh. 4 - Prob. 52PCh. 4 - Prob. 53PCh. 4 - Prob. 54PCh. 4 - Prob. 55PCh. 4 - Prob. 56PCh. 4 - Prob. 57PCh. 4 - Prob. 58PCh. 4 - Prob. 59PCh. 4 - Prob. 60PCh. 4 - Prob. 61PCh. 4 - Prob. 62PCh. 4 - Prob. 63PCh. 4 - Prob. 64PCh. 4 - Prob. 65PCh. 4 - Prob. 66PCh. 4 - Prob. 67PCh. 4 - Prob. 68PCh. 4 - Prob. 69PCh. 4 - Prob. 70PCh. 4 - Prob. 71PCh. 4 - Prob. 72PCh. 4 - Prob. 73PCh. 4 - Prob. 74PCh. 4 - Prob. 75PCh. 4 - Prob. 76PCh. 4 - Prob. 77PCh. 4 - Prob. 78PCh. 4 - Prob. 79PCh. 4 - Prob. 80PCh. 4 - Prob. 81PCh. 4 - Prob. 82PCh. 4 - Prob. 83PCh. 4 - Prob. 84PCh. 4 - Prob. 85PCh. 4 - Prob. 86PCh. 4 - Prob. 87PCh. 4 - Prob. 88PCh. 4 - Prob. 89PCh. 4 - Prob. 90PCh. 4 - Prob. 91PCh. 4 - Prob. 92PCh. 4 - Prob. 93PCh. 4 - Prob. 94PCh. 4 - Prob. 95PCh. 4 - Prob. 96PCh. 4 - Prob. 97PCh. 4 - Prob. 98PCh. 4 - Prob. 99PCh. 4 - Prob. 100PCh. 4 - Prob. 101PCh. 4 - Prob. 102PCh. 4 - Prob. 103PCh. 4 - Prob. 104PCh. 4 - Prob. 105PCh. 4 - Prob. 106PCh. 4 - Prob. 107PCh. 4 - Prob. 108PCh. 4 - Prob. 109PCh. 4 - Prob. 110PCh. 4 - Prob. 111PCh. 4 - Prob. 112PCh. 4 - Prob. 113PCh. 4 - Prob. 114PCh. 4 - Prob. 115PCh. 4 - Prob. 116PCh. 4 - Prob. 117PCh. 4 - Prob. 118PCh. 4 - Prob. 119PCh. 4 - Prob. 120PCh. 4 - Prob. 121PCh. 4 - Prob. 122PCh. 4 - Prob. 123PCh. 4 - Prob. 124PCh. 4 - Prob. 125PCh. 4 - Prob. 126PCh. 4 - Prob. 127PCh. 4 - Prob. 128PCh. 4 - Prob. 129PCh. 4 - Prob. 130PCh. 4 - Prob. 131PCh. 4 - Prob. 132PCh. 4 - Prob. 133PCh. 4 - Prob. 134PCh. 4 - Prob. 135P
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Consider the bill of materials (BOM) shown to the right. What is the lead time (in weeks) to respond to a customer order for product A, assuming no existing inventories or scheduled receipts? The lead time to respond to a customer order for product A is response as an integer.) weeks. (Enter your C (1) LT=3 B (1) LT=1 D (1) LT=6 A LT=5 E (1) ON LT=5 F (1) LT=3arrow_forwardDescribe the Monte Carlo technique and how random numbers are employed in the Monte Carlo procedure?arrow_forwardA manufacturing plant produces a product 'A' that requires one unit of 'B' and ½ unit of 'C'. Each unit of 'B' is comprised of one unit of 'D', two units of 'E', and one unit of 'F'. Each unit of 'C' requires ½ unit of 'G' and three units of 'H'. The manufacturing lead times for the components are as follows: 'A' - two weeks, 'B' - one week, 'C' - two weeks, 'D' - two weeks, 'E' - three weeks, 'F' - one week, 'G' - two weeks, 'H' - one week. There are 20 units in stock for each of these components. 100 units of 'A' are needed for delivery in seven weeks: a) Develop the product structure and indexed bill of materials for the product. b) Create a gross and net requirements plan for the manufacturer of the product.arrow_forward
- Consider the bill of materials (BOM) shown to the right. What is the lead time (in weeks) to respond to a customer order for product A, assuming no existing inventories or scheduled receipts? The lead time to respond to a customer order for product A is weeks. (Enter your response as an integer.) C (1) LT=4 B (1) LT=4 D (1) LT=8 LT = 4 E (1) LT=2 F (1) LT=3arrow_forwardLynn Jennings is the IT manager at Lazy Eddie, a chain that specializes in beanbag chairs and recliners. She asked Jan Lauten, a senior systems analyst, to review the large number of printed reports that are distributed to Lazy Eddie’s 35 store managers. “Jan, I just can’t believe that our people really read all of those reports,” Lynn said. “We constantly add new reports, and we never seem to eliminate the old ones. Sometimes I think all we’re doing is keeping the paper companies in business!” Jan replied, “I agree, but what can we do? The managers say they want the reports, but I always see them stacked on top of file cabinets. I’ve never seen anyone read a report.” “I have an idea,” Lynn said. “I want you to come up with a procedure that requires users to review and justify their information needs to see if they really use the reports we send them. You could design a form that asks if the information still is required, and why. Try to get users to decide if a report is worth the…arrow_forwardThis is for management class, Roshaun is a shipping manager for a company called “Soy to the World” that makes and sells soy candles. The soy candles are made in the company’s production area: mixed by hand and poured into glass jars, labelled, and moved to the shipping department to be sent out all over the country. Customers are usually individuals who find out about the candles from social media. They mostly order small numbers of candles at one time. Sometimes, though, companies order larger amounts of candles to be shipped as a single order. Roshaun’s team consists of eight people who pack and ship orders. Orders arrive via email to the shipping clerk who creates and prints labels, and passes the order to the shipping team that packs the candles into boxes and applies the label. Then the clerk calls an express shipping company to pick up the candles. Roshaun’s team takes such good care of packing each shipment that they have a record of no shipments ever being returned for…arrow_forward
- The Fly-Right Airplane Company builds small jet airplanes to sell to corporations for use by their executives. To meet the needs of these executives, the company's customers sometimes order a custom design of the airplanes being purchased. When this occurs, a substantial start-up cost is incurred to initiate the production of these airplanes. Fly-Right has recently received purchase requests from three customers with short deadlines. However, because the company's production facilities already are almost completely tied up filling previous orders, it will not be able to accept all three orders. Therefore, a decision now needs to be made on the number of airplanes the company will agree to produce (if any) for each of the three customers. The relevant data are given in the next table. The first row gives the start-up cost required to initiate the production of the airplanes for each customer. Once production is under way. the marginal net revenue (which is the purchase price minus the…arrow_forwardmoney borrowed for personal reasons; to be repaid within a specific time frame and with added interest money borrowed for the purchase of real estate; to be repaid within a specific time frame and with added interest money borrowed for business reasons; to be repaid within a specific time frame and with added interest money borrowed for the purchase of a vehicle; to be repaid within a specific time frame and with added interest : Business Loan :: Auto Loan :: Mortgage Loan :: Personal Loan 1 4 6. 8. 9. Finish Siarrow_forwardInvestment Manager: Works with the Investment Analyst to decide the number of stocks to be purchased, how much cash to hold and the timing of purchases.arrow_forward
- Company ZWZ manufactures three products in a serial system; Product XA is manufactured in Stage 1, Product XB in Stage 2, and XC in Stage 3. Product XB has a sales potential in the market; hence, some of it can be sold at the end of Stage 2, and the remaining can be moved to Stage 3. The third stage produces Product XC, and then delivers it to customers. Two units of Product XA produced in Stage 1 are required for each unit of Product XB in Stage 2. In addition, four units of Product XB produced in Stage 2 are required for each unit of Product XC in Stage 3. Stage 1 can only use regular time; however, Stage 2 has the options of using regular time and overtime in manufacturing. On the other hand, Stage 3 has only one alternative, which is subcontracting. The pertinent data are provided below: Stage 2 Stage 1 11 No overtime No subcontracting No sales 0.07 Unit regular time cost (TL) Unit overtime cost (TL) Unit subcontracting cost (TL) Unit selling price (TL) Unit processing time (hrs)…arrow_forwardProduction and Materials Purchases Budgets White Corporation’s budget calls for the following sales for next year:Quarter 1 90,000 units Quarter 3 68,000 unitsQuarter 2 76,000 units Quarter 4 96,000 unitsEach unit of the product requires 3 pounds of direct materials. The company’s policy is to begineach quarter with an inventory of product equal to 5% of that quarter’s estimated sales requirementsand an inventory of direct materials equal to 20% of that quarter’s estimated direct materials requirements for production.Required Determine the production and materials purchases budgets for the second quarter.arrow_forwardCan you please fill out the main boxes in a way that can be easily deciphered??arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.