OPERATIONS MANAGEMENT
OPERATIONS MANAGEMENT
2nd Edition
ISBN: 9781260238877
Author: CACHON
Publisher: RENT MCG
bartleby

Concept explainers

bartleby

Videos

Textbook Question
Book Icon
Chapter 19, Problem 1CQ

A project has four activities that take 4, 3, 6, and 7 days, respectively. What is the total completion time for the project?

  1. a. 3 days, because this is the minimum time
  2. b. 7 days, because this is the maximum time
  3. c. 20 days, because this is the sum of the times
  4. d. It is not possible to determine the total completion time from the given information.
Expert Solution & Answer
Check Mark
Summary Introduction

To determine: The total completion time for the project.

Answer to Problem 1CQ

D. It is not possible to determine the total completion time from the given information.

Explanation of Solution

Given information:

Four activities of a project take 4, 3, 6 and 7 days respectively.

The given scenario lacks basic information to find the completion time of the project. Details like precedence relationship is not given which makes it impossible to find the sequence of activities in which the project must be done.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Question content area Part 1 Oakwood Hospital is considering using ABC analysis to classify laboratory SKUs into three​ categories: those that will be delivered daily from their supplier​ (Class A​ items), those that will be controlled using a continuous review system​ (B items), and those that will be held in a two bin system​ (C items).   The following table shows the annual dollar usage for a sample of eight SKUs. Fill in the blanks for annual dollar usage below. ​(Enter your responses rounded to the nearest whole​ number.)   Part 2 Rank the SKUs in descending order on the basis of their annual dollar usage and fill in the table with the ranked​ SKU's percentage of dollar usage. ​(Enter your responses rounded to two decimal​ places.)
Sam's Pet Hotel operates 51 weeks per year, 6 days per week, and uses a continuous review inventory system. It purchases kitty litter for $13.00 per bag. The following information is available about these bags: > Demand 70 bags/week > Order cost $58.00/order > Annual holding cost 30 percent of cost > Desired cycle-service level = 80 percent >Lead time 4 weeks (24 working days) > Standard deviation of weekly demand = 15 bags > Current on-hand inventory is 320 bags, with no open orders or backorders. a. Suppose that the weekly demand forecast of 70 bags is incorrect and actual demand averages only 45 bags per week. How much higher will total costs be, owing to the distorted EOQ caused by this forecast error? The costs will be $ higher owing to the error in EOQ. (Enter your response rounded to two decimal places.)
a. The average aggregate inventory value of the product if​ Ruby-Star used vendor 1 exclusively is ​$enter your response here. ​(Enter your response as a whole number.​) b. The aggregate inventory value of the product if​ Ruby-Star used vendor 2 exclusively is shown below. c. How would your analysis change if average weekly demand increased to 160 units per​ week? The aggregate inventory values are shown below.

Additional Business Textbook Solutions

Find more solutions based on key concepts
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Principles of Management
Management
ISBN:9780998625768
Author:OpenStax
Publisher:OpenStax College
Text book image
Understanding Management (MindTap Course List)
Management
ISBN:9781305502215
Author:Richard L. Daft, Dorothy Marcic
Publisher:Cengage Learning
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY